Worklist_(003).pdf
PDF 9 KB Posted
- Attached to
- Tonka Bridge Repair Project Federal contract opportunity
- Solicitation number
- AG-0112-S-16-0011
About this file
Worklist
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| amendment_002_.doc | DOC document | |
| amendment_001_.doc | DOC document | |
| newFinal_RFQ_Tonka_Road.rtf | RTF text file | |
| Past_Performance_Worksheet.docx | DOCX document | |
| Maps.pdf | ||
| SF-1442RFQ_Tonka.rtf | RTF text file | |
| Tonka_Bridge_Repair_FSSS_Specifications.docx | DOCX document | |
| 4-WD_AK160006.pdf | ||
| Final_RFQ_Tonka_Road.rtf | RTF text file | |
| Project_Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TONKA BRIDGE REPAIR PROJECT
ROAD: 6101 OPTION 1 WORK
MP Description of work
0.000 BMP. Road intersection with road 6256 at MP 1.800.
0.988 Remove 45' log stringer bridge.
Install 50' modular Bridge.
End road maintenance.
3.494 EMP.
Note: Installation of substructure is incidental to 57102 pay item.
ROAD: 6314 BASE WORK
MP Description of work
0.000 BMP. Road intersection with road 6040 at MP 12.325.
0.928 195' Hamilton Bridge.
1.905 6326 road junction.
2.236 45001 road junction.
3.388 6329 road junction.
3.919 6328 road junction.
4.379 Remove 50' Hamilton Bridge.
4.588 6337 road junction.
4.966 Remove 18" culvert.
4.989 Remove 18" culvert.
5.021 Remove 18" culvert.
5.064 Remove 50' Big R Bridge.
5.088 Remove 18" culvert.
5.665 Remove 24" culvert.
5.762 Remove 24" culvert.
5.954 Remove 50' Big R Bridge.
6.244 Remove 36" culvert.
End Road maintenance.
6.767 EMP
Note: One of the 50' bridges will be transported to the Tonka Sort Yard for storage, while another 50' bridge will be transported to Thomas Bay for storage.
These bridges will be installed if the Options are excercized.
Note: Removal of bridge substructures is incidental to 20301 pay item.
TONKA BRIDGE REPAIR PROJECT
ROAD: 6350 BASE WORK
MP Description of work
0.000 BMP. Tonka LTF located at MP 0.000.
Clean the settling ponds and ditches in sortyard. 70CY.
Ditch ahead 500'. Ditching material and settling pond material must be end hauled 2 miles to disposable waste area.
1.591 6352 road junction.
2.305 80' Western Wood Bridge.
2.989 6353 road junction.
4.861 60' Western Wood Bridge.
5.015 6354 road junction.
6.016 70' Big R Bridge
8.070 6357 road junction.
10.190 6356 road junction.
10.933 70' Western Wood Bridge.
11.059 6358 road junction.
13.467 6325 road junction.
15.225 Remove 50' log stringer bridge.
Install 50' modular Bridge.
End road maintenance.
Note: Installation of substructure is incidental to 57102 pay item.
ROAD: 6352 OPTION 2 WORK
MP Description of work
0.000 BMP. Road intersection with road 6352 at MP 1.591.
0.447 6355 road junction.
4.333 Remove 40' log stringer bridge.
Install 50' modular Bridge.
End road maintenance.
6.383 Bridge.
11.443 EMP.
Note: Installation of substructure is incidental to 57102 pay item.