Dynamic Positioning System Replacement Federal contract opportunity
Solicitation number
AB-133M-16-RQ-0550
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

Revised Statement of Work - Amendment 01

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

DYNAMIC POSITIONING SYSTEMS (DPS) REPLACEMENT FOR

NOAA SHIPS BELL M SHIMADA and PISCES

BACKGROUND

NOAA Ships BELL M SHIMADA and PISCES are currently outfitted with Integrated Vessel

Control System Dynamic Positioning systems, which were installed when the vessels were launched. The PISCES was launched in 2003, while the BELL M SHIMADA was launched in

2005. Both of the vessels are powered by integrated diesel electric, 24-Pulse DC SCR Drive

Systems. Each system includes two 1,150 kW (1,542 hp) propulsion motors on a common shaft for a total shaft horsepower of 3,017 HP. Each vessel is equipped with one 4.3 meter diameter fixed pitch propeller and one 720 kW (966 HP) Elliott White Gill 360 degree Bow Thruster, model 40 T3S. All ship’s electrical systems including the two propulsion drives and bow thruster are powered by two 1,360 kW and two 910 kW diesel generators. Each ship has one

Becker FKSR High Performance Flap Rudder. These propulsion systems have been unchanged since vessel delivery and their existing propulsion characteristics shall be used as inputs to the new DPS. The existing DPS provides four (4) local control locations on the bridge and two (2) portable stations. The primary control station has a separate back up control station as required by ABS.

The new Dynamic Positioning System (DPS) shall be ABS and IMO classed as a DPS-1 and shall provide four stationary (4) control stations at the same locations as the current four (4) stationary stations. The central primary station shall have a separate backup control station that meets ABS requirements. Due to the fact that a bridge officer operating a stationary wing controls cannot look over the ship’s side to directly observe gear alongside the ship, please provide a separate line item quote for one portable DPS that can be connected to either wing DPS as necessary.

This SOW is for turn-key services leading to the replacement of the Dynamic Positioning System

(DPS) on the SHIMADA and PISCES. The DPS for the PISCES are optional CLINs that may or may not be exercised at time of award or any time after award is made. The procurement includes but not limited to; equipment selection meeting the performance criteria outlined below, design and integration Services, regulatory approval of the design and equipment selection by

American Bureau of Shipping (ABS), testing (Factory Acceptance Testing (FAT), commissioning, pier side, and at-sea tests and validation and crew familiarization, installation by a Factory Authorize Technical Representative, and Training (class room and ship board above any testing and familiarization of the system during testing and commissioning).

The Contractor shall provide all services to provide a complete package specific to the

SHIMADA and PISCES to fulfill the requirements for the Turn-key installation of a new DPS.

The Contractor will provide all the industrial services with required certifications needed to remove the old system components and cables and install the new equipment, components and cabling. This includes but not limited too; welders, burners, general labor, electricians, riggers, supervisors, On-site Project Manager, electronic technicians, painters, laggers, sheet metal worker and any other trade or Original Equipment Manufacturer/Factory Authorized Technical

Representatives for existing equipment, components and systems that the new DPS interfaces.

The Government will provide lifting services to transfer material from the pier to the vessel using either the ships crane or a pier-side crane. The Government will also provide space on the vessel or pier to store one 8 x 8 x 20 ISO container.

The Contractor shall provide a list of key people and substitute by as part of their offer. The

Government will review the qualifications and designate based on the qualifications the key person to fill the below roles throughout the project. The key person cannot be replaced without written approval by the Government. The same person can fill multiple roles and shall be noted in the offer. The key roles are:

Factory Authorized Technical Agent Design Engineer – available throughout the project

Project Manager – On-site single point of contact available throughout the project. On-site includes at all testing evolutions.

Project Manager - available throughout the project

Factory Authorized Testing Engineer

Factory Authorized Integration Engineer/Technician

The Contractor shall develop a design and integration package working with the Factory

Authorized Technical Representative to include:

Work specification in MS Word

Drawings in AutoCAD™ 12(or newer). The drawings will follow NOAA guidelines and

ANSI drawing practices for Computer Aided Design. The design package shall be submitted to ABS for approval in accordance with the applicable requirements for ABS and DPS-1 classification and the rules for when the vessel was constructed. The

Contractor will pay for all ABS review costs and clear all comments generated by ABS.

Work Specification and Drawings

The Contractor shall provide an integrated package that includes separate drawings for removals and installation. The Government will be an active participant in this process and requires meetings and independent review of the working product prior to submittal to ABS. The frequency and type of meeting including location will be determined after award.

o Removals package – Shall include the removal of the existing system, components and cabling. The Contractor shall use the provided GFI and ship visits to identify all that is needed for removal and depict such on the drawings

For bidding purposes this package shall assume all interface cabling will be removed. This includes all cabling between the existing DPS and ships sensors and systems.

o Installation package – Shall include all the new and modified material and equipment required for the installation and interfacing of the DPS onto the vessel o Drawing Content – All drawing shall include a Bill of Material. The Removal

Drawings shall list the major components and cabling to be removed. The

Installation drawing shall list all the new equipment, converter, power supplies, UPS, cabling, etc. The Installation Bill of Material shall include the manufacturers, part numbers and phone numbers. The Bill of Material does not need to include miscellaneous installation material, such as fasteners, nuts, bolts, washers, etc.

o Upon completion of the design package and with concurrence from NOAA the

Contractor shall submit the individual ship design package(s), Work

Specification(s) and Drawings to ABS for Review. The Contractor is responsible for clearing all ABS technical Comments prior to the start of any work and ensuring all Surveyor validations are accepted by ABS during the installation and commissioning phase.

Testing

The Contractor shall provide all the required test procedures in accordance with the applicable classification society. These include; FAT, Component and periodic tests, commissioning, pier-side and at-sea validation and testing evolutions.

The Government will review test procedures.

The Government will have a representative present to witness all tests to include Factory

Acceptance Testing (FAT) and any and all installation tests and commissioning evolution lead. The Contractor shall provide a testing schedule with notional dates to be updated as the actual work start date get confirmed.

Installation Services

The Contractor shall provide all the industrial services to remove and install a new fully functioning DPS in accordance with the approved design and meeting the requirement of the applicable classification regulations.

The Contractor shall provide the services of a Factory Authorized Technical

Representative, Factory Trained to be present starting at the installation through final acceptance sea trials.

System should be supplied with Factory certified acceptance test stamped by the applicable

Regulatory Body.

SHIP PRINCIPAL CHARACTERISTICS

NOAA Vessels SHIMADA and PISCES:

Integrated Diesel Electric, 24-Pulse DC SCR Drive System

Two 1,150kW(1,542 hp) Propulsion Motors on a Common Shaft

One 720 kW (966 hp) AC Induction Azimuthing Bow Thruster

Two 1,360 kW Diesel Generators

Two 910 kW Diesel Generators

One 4.3 m (14.1 ft) Diameter Fixed Pitch Propeller

Length Overall: 63.8 m (209ft)

Breadth: 15.0 m (49.2 ft)

Depth to Main Deck: 8.65 m (28.4 ft)

Draft: 6.0 m (19.4 ft) (Centerboard Retracted)

9.05 m (29.7 ft) (Centerboard Extended)

Full Load Displacement: 2479 mt

Light Ship Displacement: 1840 mt

Speed, Sustained: 14.0 kts

Speed, Hydroacoustic Survey: 0 to 11.0 kts

Endurance: 40 days/12,000 nm @ 12 kts

REFERENCES

SH-170- FC29-Mast Structural Calculations

SH-170- FH22-Mast, Rigging & Flagstaff Layout & Details

SH-300- FE01-Power One Line

SH-300- PE42-Bridge Deck Arrangement

SH-304- FE40-03AB - Cableway Details

SH-304- FE41-Penetration Details

SH-304- FE43-03AB - Bonding and Grounding Details

SH-304- FE44 cable way key plan

SH-420- 001 Dynamic Positioning Sys (DPS)

SH-420- FE73-Dynamic positioning block wiring diagram

SH-438- FE81-IBS System Block Wiring Diagram

SH-438- PE82-Integrated Bridge Sys Termination Sheets

SH-438- PE83-Integrated Bridge System Regulatory Submittal

SH-561- FM03-Steering Arrangement

SH-561- PE29-Steering Control System Terminal list

REQUIREMENTS

The below are the major CLIN(s) with partial requirements listed. These are intended as initial guidance for offerors and do not limit or restrict NOAA in any way from receipt of all requirements defined within the specification.

o CLIN 0001- Bell M Shimada Design: Incorporation of all requirements and configurations described in the SOW to provide a fully functional system.

o CLIN 0002 – Bell M Shimada Material: All materials required to provide a fully functioning system. The material shall include but not limited too; all hardware, software, cable and wiring, cable tags, labels, computer systems, controllers, displays, mounting hardware, etc) o CLIN 0003 – Bell M Shimada Installation and Commissioning: All services required to remove current system, install new system, light off new system, and demonstrate system capability to meet all performance requirements.

o CLIN 0004 – Bell M Shimada Logistics and Familiarization - Description of all support services, material, lifecycle of components, warranty, full operational and maintenance manuals with all codes, lights and messages defined with reference to troubleshooting procedures pages to support all requirements as defined in the SOW. Crew familiarization of system in a dock-side and at-sea environment to include but not limited too; operational procedures, light-off and emergency procedures, all error and warning codes defined with procedures to validate, crew questions, crew demonstrations, to support all requirements as defined in the SOW.

o CLIN 0005 – Bell M Shimada Travel: All travel costs associated with project on a NTE basis & IAW the Joint Travel Regulation to Newport, OR.

o CLIN 0006- Pisces Design. (OPTION) o CLIN 0007 – Pisces Material. (OPTION) o CLIN 0008 – Pisces Installation and Commissioning (OPTION).

o CLIN 0009 – Pisces Logistics and Familiarization (OPTION).

o CLIN 0010 – Pisces Travel: All travel costs associated with project on a NTE basis &

IAW the Joint Travel Regulation to Pascagoula, MS. (OPTION).

o CLIN 0011 – Training: Formal crew classroom training performed with system (onsite or offsite) (OPTION). Training does not apply to a specific ship but to the project overall.

o CLIN 0012 – Spare Parts: Contractor to provide a recommended spare parts and price list that becomes part of the contract. The government will order spare parts, if necessary, from this price list. Contractor shall invoice against this CLIN for all spare parts delivered and accepted. NOTE: Only the COR assigned to this project is authorized to order spare parts under this contract. (REIMBURSABLE, NOT TO EXCEED)

DYNAMIC POSITIONING SYSTEM (DPS)

1. The DPS provided by the contractor shall be the most recent version currently in production that has been fully tested and installed on a minimum of three (3) vessels of the same or larger size than NOAA Ships BELL M SHIMADA and PISCES and having the same general propulsion configuration. The contractor shall provide the applicable DP system specific software, including the latest Type approved Windows 7 (or newer) marine computer, this software and computer should have the ability to be upgradable as newer versions of Windows become available, software, all required software license keys and backup media and a single

LAN interface.

2. The newly installed system shall be fully supportable by the contractor, who shall also provide an end of life plan for any proposed system including all components.

3. The DPS shall meet all requirements of the International Maritime Organization’s “Guidelines for Vessels with Dynamic Positioning Systems.” (Maritime Safety Committee (MSC)

Circular 645 or latest published circular.)

4. The system must have a warranty covering technical assistance, parts and labor. The warranty shall start at the time of ABS approval.

5. System Specifications:

Direct interface to the propellers, thrusters, power plant, position-reference system, and sensors.

Control by manual joystick, automatic, or combination

Modes of operation o DPS Manual Mode

In the manual mode, control shall be by three axis joystick at the PHMC and portable operator terminals. The joystick shall include automatic heading capability. Joystick control response shall be adjustable by the operator to different scaling curves of thrust as a function of joystick deflection.

o DPS Autopilot Mode

The autopilot mode shall automatically control the ship's heading within +/-

2 degrees of the selected course at speeds from 0.5 knots to maximum. Propeller RPM shall be manually controlled at the propeller controls or the DPS joystick. This system shall allow course corrections without coming out of this mode.

o DPS Automatic Control Mode

The DPS shall automatically control propeller RPM, steering control surface angle, and thruster azimuth angle and RPM, as applicable, to meet the following requirements:

Dynamic positioning shall be required with the ship in full load condition

(with service life allowance) in the following conditions using the mean wave height and most probable modal period as defined in Table D-1 of

STANAG 4194:

Position Keeping – The ship shall hold position at best heading in sea conditions up through sea state five, a wind speed of 35 knots, and a 2 knot beam current. In this context, best heading is defined as when the ship is headed directly into collinear wind and waves. The ship shall be capable of maintaining a watch circle of one ship length diameter. The DPS shall sound an alarm when the ship falls off position beyond a user-selectable limit. The DPS shall include the ability to move from present position to a selected location in any direction while maintaining ship’s heading and rotating any amount up to 360 degrees while maintaining position.

o Independent Autopilot

A self-tuning, adaptive autopilot shall be provided. The autopilot shall be designed for general navigation and shall be independent of the DPS system. It shall be fully integrated with the ECDIS system and capable of automatically steering a route with turns through multiple waypoints as specified by ECDIS.

The independent autopilot system shall be switchable from hand steering to autopilot steering, and shall have a sensitivity adjustment for heavy weather. The autopilot shall be able to function without the DPS system being operational, including the ability to upload and download waypoint and track steering information from the ECDIS.

The autopilot shall automatically control the ship's heading within +/- 1 degree of the selected course at speeds from 0.5 knots to maximum.

Autopilot primary control shall be at the PHMC.

The adaptive autopilot shall be IMO compliant and wheelmarked.

o Follow Target

Automatic following of moving target and maintaining of position within a user-definable radius relative to the target.

o Anchor Assist

Provides thruster assistance when operating within a mooring pattern.

o Minimum Power Mode.

Vendors may use alternate terminology for this mode, such as Relaxed DP, Relaxed Control, Minimum Overall Thrust, Green DP, etc. The DPS shall provide the operator with a choice of fully automatic operation at reduced power and/or response time to maintain position within a user- configured operating envelope for the purpose of greater fuel reduction and reduced thruster/propeller force than what would be the normal thruster response as determined by the "optimum" thruster allocation algorithm determined by the Controller.

o Rate of Turn (ROT) Pilot

Enables operator to maneuver vessel using ROT control o Auto-track

Vessel follows a specified track described by a set of waypoints.

Track line - The ship shall follow a trackline over the bottom within +/- 20 m at any speed between 2 knots and full power speed in sea conditions up through sea state five, a wind speed of 35 knots, and a 2 knot current

(perpendicular to trackline). The DPS shall provide the capability of accepting multiple waypoints. Permissible maximum variation of the ship's heading from the track course (crab angle) shall be user-selectable up to a limit of +/- 45 degrees. When following a multiple waypoint trackline that requires a change in course after a waypoint, the DPS shall be capable of changing the ship's heading automatically to follow the new course of the next track segment. The DPS shall alert the operator that a turn is impending by sounding a local alarm at a fixed time interval before the turn. The DPS shall alert the operator by sounding a local alarm when the ship falls off track. Straight track segments shall be maintained without large and/or frequent heading changes.

Enables the vessel to follow a constant Course over Ground (COG).

The DPS primary control shall be located in the Pilot House main console (PHMC) and shall be directly adjacent to the electronic chart display and information system (ECDIS) display. Two portable operator terminals with joystick (with full heading capability), remote controller, video display, and interface cable shall be provided. Terminals shall be designed to be viewable in direct bright sunlight. Remote plug-in jacks for the portable terminal shall be provided at each bridge wing, aft end of Pilot House. Bridge wing control consoles shall include space to accommodate the portable operator terminals. Means of positively securing the portable operator terminals in the vicinity of the plug in jacks shall be provided. Remote plug-in jacks and interface cables shall be configured so the operator terminal is oriented correctly for ship control regarding correct graphical user interface (GUI) orientation. Station selection shall be located at the primary control in the Pilot House. Visual indications and voice channels shall be provided at the primary station and secondary stations to effect and accept control transfer. Full positive control shall be maintained during control transfer. Video display signals of the DPS screen shall be provided to the Scientific Computer System (SCS)

The DPS shall have an industry standard commercial operating system. The DPS application shall be programmed in a standard language code. A DPS color video display monitor and keyboard shall be provided in the PHMC. The DPS primary control shall have a menu selectable operating and setup capability and help library. Setup features shall include the following modes: manual, autopilot, and automatic control with local or remote input of commands.

The DPS system shall have operator selectable heading, speed, and tracking. The DPS waypoints and tracks shall be capable of being uploaded from or downloaded to electronic storage media or the

SCS. The DPS shall be capable of generating a survey track of multiple waypoints including parallel courses, cross line courses, lead-in and lead-out line, and turns from 0 degrees to 359 degrees. The DPS shall be capable of operating in the Follow Target mode, following Remote Operated Vehicles (ROV) and Autonomous

Underwater Vehicles (AUV) associated with the ANTS. The Follow

Target mode shall include operator adjustable settings for target reaction limits, position filtering, distance to target, vessel speed, vessel acceleration/deceleration, and rate of turn. The Follow Target mode shall also allow the operator to pause the movement of the vessel and then reactivate the mode to have the vessel move to be positioned at the previously defined distance from the target. Color video displays shall have dimming controls and shall indicate the following:

o operating mode selected: DPS Mode of Station Keeping or

Position Move, Course Tracking, Autopilot, or Follow Target o source of command information: Manual, automatic local, or automatic remote o commanded position and actual ship position o commanded heading and actual ship heading o commanded track course, actual ship track course made, and present cross track error o next track course selected o distance along track, distance to end of track waypoint, time to end of track waypoint, distance to last waypoint, and time to last point o commanded speed and actual speed o crab angle o tracking status: Tracking or not tracking o individual main diesel generator status and loading o individual thruster status and loading o navigation input source o ship heading o waypoint locations o any additional information needed for operation of the DPS in the various modes o The DPS shall be capable of operating in any mode with any combination of propellers, rudders, and thrusters disabled. Operators shall be capable of enabling or disabling each thruster and propeller. Any thruster disabled by DPS, shall revert to manual control automatically.

o The DPS shall be tuned to prevent cyclic loading and unloading of the propulsion motors, thruster(s) and main diesel generators. DPS command acceleration and deceleration ramp rates shall be tuned to match the time constants of each of the propulsors. The DPS shall accept industry standard interfaces for generator kW, amperage, throttle commands, propulsor RPM, and other required interfaces with the ship’s propulsion control and power generation systems.

o The DPS design and operation shall minimize noise, vibration, and adverse effects on the operation of acoustic systems as much as possible.

o The DPS shall be designed to operate continuously for long periods (up to full endurance) of on-station or trackline following work.

o The following inputs shall be provided to the DPS:

position sensor input from ship’s DGPS –two heading inputs from gyrocompasses two wind inputs

EM Speed Log input

Doppler speed log input remote control interface

Motion Reference Unit: The new DP system will include an Integrated

Vertical Reference System (VRS).

PISCES: One (1) each: PosMv and MAHRS, output: serial NMEA data

SHIMADA: One (1): PosMv output: serial NMEA data

Thruster Ready, One (1), digital input

Thruster Command (RPM), One (1), analog output

Thruster Feedback (RPM), One (1), analog output

Thruster Azimuth Command, One (1), analog output

Thruster Azimuth Feedback, One (1), analog output

Thruster Request, One (1), digital output

Propeller Ready, One (1), digital input

Propeller Command (RPM), One (1), analog output Propeller Feedback (RPM), One (1), analog output

Propeller Request, One (1), digital output o The DPS shall be capable of receiving inputs from the following:

at least two position sensor inputs from the GPS/DGPS, Wide Area

Differential Global Positioning System (WADGPS), or other satellite

GPS/DGPS inputs one additional heading input position/motion sensing input from the AHRS

ANTS for the Follow Target Mode

The DPS shall be capable of transferring waypoint data with ECDIS. The

DPS shall navigate tracks, routes, and position moves based on ECDIS generated waypoint tracks. The DPS shall be capable of interfacing with the

SCS and be capable of providing non-proprietary, industry-standard format output to science systems.

Basic System Hardware Envelope

The Main Operator Station and other three stations controls shall be in the Pilot House.

Replacement controls must fit within the existing footprint on the ship’s existing consoles.

Relocation to another area of the console is not possible. Primary CPU’s and all other key system components should be commercial off the shelf (COTS) units with standard frame size, allowing the ship to upgrade or change out CPU’s without the need for specialized parts. The computer hard drive should be a solid state drive with a minimum 5 year warranty and at least 60 percent of the drive available for future software updates.

18”

13 1/4”

20 1/4”

Above: photograph indicates existing integration of DP console into the BELL M SHIMADA’S bridge’s main console.

Above: Bridge wing station console with existing DP system.

5 5/8”

5 5/8”

At a minimum, Operator Station shall consist of following components:

1. ABS approved, color displays shall fit in each ship’s existing console, sunlight-viewable, flat panel touch screen.

2. Joystick (3-axis) control

3. Heading selector knob or similar control

4. For most common actions, provide rapid-access buttons that can be located tactilely by operators with divided attention. The buttons shall have status indicator lamps.

5 Hard Disk: solid state

6. DVD/CD and USB Read/Write

7. Motion Reference Unit: The new DP system will include an Integrated Vertical Reference

System (VRS).

Controller

1. One controller shall be provided, consisting of a minimum of a single, real- time processor.

2. Controller shall have single inputs as follows: Flash PROM, analog input, digital input, analog output, serial input, and power supply.

3. DP system must be on its own marine grade Uninterruptible Power Source (UPS), capable of lasting 30 min, and cannot be connected to the bridge UPS.

4. Controller shall be fitted with field termination provisions including installation of dedicated output contacts or discrete outputs for monitoring the DP system in MACS. Acceptable communication methods include RS232, Ethernet and dry contacts. DP commands are currently logged automatically in the bell logger however alarm conditions, backup system operation, etc.

must also communicate with MACS. At a minimum, software shall be provided with user-configurable Windows for display of position plot, capability plot, polar plot, status and position of thrusters and navigational data including course steered, course set, course error, rate of change of heading, latitude, longitude, cross-track error, course over ground, speed over ground.

Additionally, the contractor shall provide backup software and instructions on separate DVD/CDs such that, in the event of hard drive failure, the program can be reloaded by ship’s force.

Uninterruptible Power Source

The UPS shall be a double conversion marine grade UPS for shipboard use, sized to allow for continuous operation of the DP System in accordance with regulatory requirements.. The UPS should be rack mountable if possible, and if not possible shall include dedicated mounting fasteners and be securely mounted to the deck or bulkhead.

Secondary Operating Terminals with DP

Secondary operating terminals shall be provided for both the port and starboard bridge wings and the Aft Station. Each secondary operator panel shall consist of the same controls as the primary terminal. The secondary terminals must contain a 3 axis joystick, built in color display, control buttons and status indicators, junction box and a LAN interface. The display must be a color display, size at least 6.5 inches (diagonal). The terminal must meet IP44 or higher protection standards and consume no more than 30 Watts of power. The terminal must be ABS approved.

Data Exchange Data exchange between system components shall be carried out on an Ethernet Local Area

Network (LAN), TCP/IP. All cable supplied with the new DP system and supporting components shall be shipboard approved, low smoke cable, including all communications, power and data cables.

Remote Diagnostics

DPS shall be provided with capability to accomplish remote diagnostics and monitoring in real-time for DP via satellite data communications link.

The following interfaces shall be supplied by the contractor:

Miscellaneous System Hardware

Contractor shall supply all hardware and components necessary to interface with all existing system and thruster interfaces in order for the DP system to be fully functional with the existing suite of thrusters and navigation instruments.

ADDITIONAL DOCUMENTATION

In addition to other required documentation specified herein, the contractor shall deliver the following documentation to the Contracting Officer’s Representative (COR) with the DP system: All digital copies shall be in Microsoft Word or PDF format.

1. Three (3) sets of the Operator Manual in paper format, and one digital copy

2. Three (3) sets of the Technical Manual in paper format, and one digital copy

3. Three (3) sets of the Installation Manual in paper format, and one digital copy

4. One (1) one digital copy of the vessel's Mathematical Model

TESTING

o Factory Acceptance Test (FAT)- The Contractor shall provide the FAT plan to the COR in accordance with the applicable Rules and Regulations to ABS for review and approval.

Prior to submittal to ABS the plan shall be submitted to the COR with at least 10 working days to review the plan prior to submitting to ABS.

o Sea Trial Test Plan- A minimum of one month prior to the sea trial, the vendor shall deliver a sea trial "Tuning and Acceptance Test" document to the COR for review and comment.

After agreement of both parties on the format and procedures, a final document shall be delivered to the COR and to ABS (one) 1 week prior to sea trials. The document shall describe in detail the tests and procedures to be followed.

TRAINING

o At Sea Training - The contractor shall provide at least two sessions (one will be after normal working hours) of at-sea familiarization training for the bridge crew of each vessel upon completion of the DP system installation and sea trials.

o Sea- Trial - The services shall also include attendance at a thirty-two (32) hours testing and acceptance sea-trial. The sea trial will include a customer acceptance test with ABS in attendance; sea trial shall be to the satisfaction of the attending surveyor in order to issue an

ABS DPS-1 certification for the DPS. The sea trial shall test all inputs/alarms of the system and tune the system components. The government shall pay for the services of the ABS surveyor for a one-time sea trial; however, should a subsequent sea trial be required due to a contractor-responsible problem with the DPS, then the contractor shall be responsible for any additional ABS costs.

o For estimating purposes, sea trials will be held in Newport, Oregon for the BELL M

SHIMADA and Pascagoula, Mississippi for the PISCES.

o The above required training and installation requirements do not include travel time.

SPARE PARTS

The contractor shall provide a list of readily available spares, that can be purchased on a separate

CLIN of this contract, including relevant part numbers, serial numbers, model numbers, etc., and complete ordering information. In addition, the contractor shall provide complete ordering information for the following:

1. All components of a new remote system.

2. Additional components beyond the standard system that will improve autopilot reliability.

3. A completely separate, yet compatible autopilot system.

4. Controller with EEPROM pre-loaded (ready to be installed in all respects)

5. Spare input card and spare output card

6. Power supply

7. Network Interface Card (NIC) and switch if present

8. Pre-imaged hard drive (ready to be installed in all respects)

CLASSROOM TRAINING

o Contractor shall provide cost per person for a minimum of thirty-two (32) hours hands-on and theoretical training at the contractor’s US based training facility of the bridge team for each vessel. NOAA will provide necessary travel costs for all NOAA attendees.

PERFORMANCE PERIOD

The actual dates for completion of the Factory Authorized Technical Representative installation services and training will be determined based on the actual dates of performance of the DPS installations and sea trials for each vessel.

DELIVERABLES

The Contractor shall provide the following after award:

All working drawings in AutoCAD

All ABS stamped drawings and correspondence with ABS on subject drawings o All ABS stamped drawings shall be provided prior to commencement of ship board work.

Detailed work and testing schedule to include major milestones.

o The work schedule major milestones are;

Drawing and specifications for review by the COR and subsequently submitted to ABS

ABS drawings and ABS correspondence

FAT test plan and FAT schedule

Equipment order and receipt schedule

Work schedule for on-board vessel work to include start of work, inspections, tests, commissions and sea trials

As-Built drawings to reflect the final configuration of the specific vessel.

An approximate list of equipment and approximate associated costs associated with the system at end of service life. Equipment to include system upgrade, hardware, software, firmware, and operating system, but excluding cost of installation. The Government is not asking for a proposal for this end of service life equipment and costs at this time, but requires this information for planning purposes only. All estimated end of service life costs will be considered confidential and will not be released outside of the Government.