This is a solicitation for maintenance dredging of Silver Lake Harbor and Manteo Interior Channel in North Carolina. Approximately 323,000 cubic yards of material will be dredged from five ranges using a hydraulic pipeline dredge, with disposal on existing islands except for optional work which will use Island H as a confined disposal area. Additionally, around 300,000 cubic yards will be dredged from Big Foot Slough Channel and placed on Bigfoot Slough Island, also using a hydraulic pipeline dredge. There is an environmental window for island placement from September 1 to March 31. This solicitation is a 100% small business set-aside for a firm fixed price contract valued between $5-10 million. The North American Industry Classification System code is 237990 and size standard is $30 million. Offerors must register in SAM to be eligible for award. The bid opening date will be specified when the solicitation is issued on or around July 18, 2022 electronically without additional media. Interested parties should check the provided website and contact the listed contracting staff.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B1 - Bid Opening Sign In Sheet.pdf | ||
| B1 - Bid Abstract_Manteo-Silver Lake_Signed.pdf | ||
| A21 - Manteo_SilverLakeHarbor_RTA_Plans_unlocked.pdf | ||
| A21 - W912PM22B0027_Manteo_Silver Lake Harbor Solicitation.pdf | ||
| A21 - Manteo_SilverLakeHarbor_RTA_Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maintenance Dredging, Silver Lake Harbor and Manteo Interior Channel
North Carolina
RTA Specifications
July-2022
Solicitation No. W912PM22B0027 Contract No. W912PM22XXXXX
W912PM22B0027 RTA
FY23 Manteo Interior Channels and Silverlake Harbor
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 04/22 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 10 00.10 38 04/21 SUPPLEMENTARY SPECIAL CONTRACT
REQUIREMENTS
01 32 01.00 10 02/15 PROJECT PROGRESS SCHEDULE
01 33 00 05/11 SUBMITTAL PROCEDURES
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 11/18 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE(RMS CM)
01 50 00 08/09 TEMPORARY CONSTRUCTION FACILITIES
01 57 19 11/15, CHG 5: 08/21 TEMPORARY ENVIRONMENTAL CONTROLS
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 20 23 04/21 DREDGING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 01 15
LIST OF DRAWINGS
04/22
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.3 SUPPLEMENTARY DRAWINGS
1.3.1 The Reference Drawings
ATTACHMENTS:
Attachment 1-Index of Drawings
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
04/22
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as shown in Attachment 1-Index of Drawings.
1.3 SUPPLEMENTARY DRAWINGS
These supplementary drawings may not be a part of the contract but are included with the drawings for information.
1.3.1 The Reference Drawings
The reference drawings are intended only to show the original dredging.
Drawings are the property of the Government and shall not be used for any purpose other than that intended by the contract.
Reference drawings are as shown in Attachment 1-Index of Drawings.
-- End of Document --
DOCUMENT 00 01 15 Page 2
Sheet Number Sheet Title
G001 COVER SHEET
GI01 LOCATION MAP, PROJECT OVERVIEW AND INDEX OF DRAWINGS
CN101 RANGE 14A AND 14B (CONTRACT OPTION)
CN102 RANGE 16
CN103 RANGE 17
CN104 RANGE 17 EXTENSION
CN105 ISLAND H
CN106 ISLAND D
CN107 ISLAND L AND ISLAND MN
CN108 BIG FOOT SLOUGH CHANNEL
CN109 BIG FOOT SLOUGH ISLAND PLACEMENT AREA
INDEX OF DRAWINGS
ATTACHMENT 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 10 00.10 38
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
04/21
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS
1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.5 PERFORMANCE AND PAYMENT BONDS
1.6 SHOP DRAWINGS AND MATERIALS SUBMITTAL
1.7 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING
1.8 INSPECTION
1.9 FINAL EXAMINATION AND ACCEPTANCE
1.10 ACCOMMODATIONS AND MEALS FOR INSPECTORS
1.11 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS
1.12 REQUIRED CONSTRUCTION MEETINGS
1.13 BULLETIN BOARD
1.14 PLANT
1.15 PLANT LOCATION
1.16 SIGNAL LIGHTS
1.17 WORK IN QUARANTINED AREA
1.18 NCDOT SPECIFICATIONS
1.19 DEFINITIONS FOR NCDOT SPECIFICATIONS
1.20 IDENTIFICATION OF EMPLOYEES
1.21 PUBLIC CONVENIENCE AND SAFETY
1.22 LOAD RESTRICTIONS
1.23 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS
1.24 CONTRACT AREA AND TRESPASSING
1.25 PARTNERING
1.26 IN-WATER LINES
1.27 LOCAL NOTICE TO MARINERS
1.28 ADVANCE NOTICE REQUIREMENT
1.29 PROTECTION OF EXISTING FACILITIES
1.30 WATER CONSERVATION
1.31 COORDINATION WITH OTHER CONTRACTORS
1.32 SURVEY DATA
1.33 CONTRACT DRAWINGS AND SPECIFICATIONS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 10 00.10 38 Page 1
SECTION 01 10 00.10 38
SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS
04/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION (NCDOT)
NCDOT Standard Specifications For Roads And Structures
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
ER 1110-1-5 Plant Pest Quarantined Areas and Foreign Soil Samples
1.2 SUBMITTALS
Government approval is required for submittals with a "G, A" designation;
submittals not having a "G, A" designation are for information only. When used, a designation following the "G, A" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Subcontractors
Progress Chart; G, A
Quality Control Plan; G, A
SD-07 Certificates
Certificate of Insurance
Completion of Corps CQC Course
Letter Appointing Superintendent
1.3 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS
The Contractor shall be required to comply with the following security requirements mandated by the Department of the Army:
Short-term employees (working on site less than or equal to 6 months): If a criminal history is found, the employee MAY not be allowed to work at the project site at the sole discretion of the
SECTION 01 10 00.10 38 Page 2
Government.
Long-term employees (working on site more than 6 months):
ALL of the following is required WHEN REPORTING FOR WORK -
a) A completed OMB Form No. 3206-0182 (also designated as Optional Form 306).
b) A completed OMB Form No. 3206-0191 (also designated as Standard Form 85P).
c) A resume.
The Government will use all provided information to perform a National Agency Check and Inquiries (NACI) check and will pay the required fee.
The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer or his/her designated representative. All prescribed identification shall immediately be delivered to the Contracting Officer or his/her designated representative for cancellation upon the release of any employee.
(End of Clause)
1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be found to be satisfied in the sole discretion of the Contracting Officer:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
(b) Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.
(c) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. The Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "DEFAULT
(FIXED-PRICE CONSTRUCTION)."
SECTION 01 10 00.10 38 Page 3
(End of Clause)
1.5 PERFORMANCE AND PAYMENT BONDS
Each bidder shall include his premiums for performance and payment bonds under the "Performance and Payment Bonds" contract line item of the Bidding Schedule. Payment to the Contractor therefore, shall not exceed the bid price and shall be made in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount bid in excess of the actual bond premium will be included in the final pay estimate for this contract.
(End of Clause)
1.6 SHOP DRAWINGS AND MATERIALS SUBMITTAL
(a) Five (5) days prior to the preconstruction conference (see paragraph REQUIRED CONSTRUCTION MEETINGS), the Contractor shall complete and submit to the Contracting Officer or his/her designated representative, in duplicate, Submittal Register, listing all submittals and dates. In addition to those items listed on the Submittal Register, the Contractor will furnish submittals for any deviation from the plans or specifications.
The scheduled need dates must be recorded on the document for each item for control purposes. In preparing the document, adequate time (minimum of l5 days) will be allowed for review and approval and possible resubmittal.
Scheduling shall be coordinated with the approved progress schedule. The Contractor's Quality Control System Manager shall review the listing at least every 30 days and take appropriate action to maintain an effective system. Copies of updated or corrected listings shall be submitted to the Contracting Officer or his/her designated representative at least every 60 days in the quantity specified. Payment will not be made for any material or equipment which does not comply with contract requirements.
(b) Contractor submittals required by the Technical Provisions are indicated in those provisions and are listed on the Submittal Register furnished in Section 01 33 00 SUBMITTAL PROCEDURES. The list does not relieve the Contractor from furnishing submittals required elsewhere in the specifications, those inadvertently omitted from the listing; or from furnishing other submittals that the Government may deem necessary as the work progresses.
(c) Normal review levels for required approvals are indicated by letter designations as follows:
Contractor Quality Control System Manager --- (CQC) Area or Resident Engineer ------------------- (R) Engineering Branch -------------------------- (E) The Government reserves the right to vary the review levels for (R) and (E) to its convenience.
(d) The Contractor shall use ENG Form 4025, furnished in Section 01 33 00 SUBMITTAL PROCEDURES, to transmit Shop Drawings, Equipment Data, Material Samples or Manufacturer's Certificate of Compliance to the Government.
(End of Clause)
SECTION 01 10 00.10 38 Page 4
1.7 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING
(1998 January HQUSACE)
(a) Where the quantity of a pay item in this contract is an estimated quantity and where the actual quantity of material within the required dredging prism, including the associated side slopes, varies more than 15 percent above or below the stated estimated quantity within the required dredging prism, an equitable adjustment in the contract unit price will be made upon demand of either party. The equitable adjustment will be based upon any increase or decrease in the costs due solely to the variations above 115 percent or below 85 percent of the estimated quantity within the required dredging prism. Any equitable adjustment in the contract unit price will also apply to that part of the actual quantity of allowable over-depth material above 115 percent or below 85 percent of the estimated allowable over-depth quantity.
(b) If the quantity variation is such as to cause an increase in the time necessary for completion, the Contracting Officer or his/her designated representative shall upon receipt of a written request for an extension of time within 10 days from the beginning of such delay, or within such further period of time which may be granted by the Contracting Officer or his/her designated representative prior to the date of final settlement of the contract, ascertain the facts and make such adjustment for extending the completion date as in their judgment the findings justify.
(End of Clause)
1.8 INSPECTION
The Contractor shall be required:
(a) To furnish, on the request of the Contracting Officer or his/her designated representative or any Government inspector, the use of such boats, ATV's, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew as may be reasonably necessary in inspecting the work. However, the Contractor shall not be required to furnish such facilities for the surveys prescribed in the clause entitled
"FINAL EXAMINATION AND ACCEPTANCE".
(b) To furnish, on the request of the Contracting Officer or his/her designated representative or any Government inspector, suitable transportation from all points on shore designated by the Contracting Officer or his/her designated representative to and from the various pieces of plant, and to and from all work locations. The transportation, if by boat, shall comply with the requirements of paragraph 19.F of USACE
EM 385-1-1 .
(c) To furnish a 4X4 utility vehicle capable of safely transporting four persons for use by the Contracting Officer or his/her designated representative, official visitors to the site or any Government inspector for use off road i.e., beach fill projects. 4X4 utility vehicle shall be equipped with seat belts, ROPS, lights, back-up alarm and foul weather protection (same as contractor equipment). Contactor shall be responsible for 4X4 utility vehicle maintenance and fuel.
Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer or his/her designated representative and the cost
SECTION 01 10 00.10 38 Page 5 thereof will be deducted from any amounts due or to become due the Contractor.
(d) The Contractor shall perform a pre-existing inspection. The Contractor shall document the disposal area to include the adjoining structures, pipes, etc that may be affected by the dredging and placement operations.
The Contracting Officer or his/her designated representative or Government Inspector shall have full access at all times to any and all points on shore, and the various pieces of plant including but not limited to:
supporting plant and ancillary plant and or equipment. All Government Representatives will comply with the real-time/current time requirements of the Center for Disease Control (CDC). The Contractor shall not impose or enforce requirements and/or restrictions on the Government representatives which are more stringent than, or exceed the CDC requirements without the prior written approval of the Contracting Officer, and any delays or other costs attributable to the unauthorized imposition or enforcement of those requirements and/or restrictions shall be at the expense of the Contractor.
(End of Clause)
1.9 FINAL EXAMINATION AND ACCEPTANCE
As soon as practicable after the completion of the entire work or, if the work is divided into sections, or if any section which in the opinion of the Contracting Officer or his/her designated representative will not be subject to damage by further operations under the contract, such work will be thoroughly examined at the cost and expense of the Government by sounding or by sweeping, or both, as determined by the Contracting Officer or his/her designated representative. If any shoals, lumps, or the lack of contract depth are disclosed by this examination, the Contractor shall remove same by dredging the bottom with payment at the appropriate contract rate for dredging. The Contractor will be notified when soundings or sweepings are to be made and will be permitted to accompany the survey party. When the area is found to be in satisfactory condition, it will be accepted. If more than two sounding or sweeping operations by the Government over an area are necessary because of work for the removal of shoals disclosed by prior sounding or sweeping, the cost of such subsequent soundings or sweeping operations will be charged against the Contractor at the rate of $5,000 per day in which the Government plant is engaged in sounding or sweeping, is enroute to or from the site, or is held at or near the site for such operations.
(End of Clause)
1.10 ACCOMMODATIONS AND MEALS FOR INSPECTORS
(a) The Contractor shall furnish regularly to inspectors, for office purposes and sleeping purposes, when applicable, a suitable separate room onboard the dredge or other craft upon which they are employed. If no suitable office space is available thereon, the Contractor shall furnish suitable alternate accommodations ashore at a location approved by the Contracting Officer or his/her designated representative and furnish suitable transportation between the alternate accommodations and the dredge or other craft upon which they are employed.
SECTION 01 10 00.10 38 Page 6
(b) If the Contractor maintains an establishment for the subsistence of his own employees, he shall, when required, furnish to inspectors employed on the work, and to all Government agents who may visit the work on official business, meals of a quality satisfactory to the Contracting Officer or his/her designated representative. The meals furnished shall be paid for by the individual consuming the meal at a rate commensurate with the basic Government subsistence rate of: $5.00 Breakfast; $8.00 Lunch; $13.00 Dinner.
(End of Clause)
1.11 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS
(a) In accordance with Contract Clause 52.219-9, Small Business Subcontracting Plan, and 52.219-16, Liquidated Damages - Subcontracting Plan, retainage will be withheld from progress payments in an amount sufficient to protect the Government's ability to assess liquidated damages in accordance with Clause 52.219-16 for the contractor's failure to timely submit Standard Form 294, Subcontracting Report for Individual Contracts, and Standard Form 295, Summary Subcontract Report, reports.
(b) The retainage will be determined in accordance with the following formula:
Total dollar amount for subcontracting to small business multiplied by percentage of actual progress on the contract shall be withheld from the next progress payment due after the Contractor fails to submit a required report. If one or more reports have been submitted before such failure, formula for determining the amount of retainage will be adjusted by deducting any amounts reported as subcontracted to small business from the total dollar amount proposed to be subcontracted and the difference multiplied by the percentage of actual progress.
(c) Subcontracting plans are not required--
(1) For contracts or contract modifications that will be performed entirely outside of any State, territory, or possession of the United States, the District of Columbia, and the Commonwealth of Puerto Rico; or
(2) For modifications to contracts that do not contain the clause 52.219-8, Utilization of Small Business Concerns and Small Disadvantaged Business Concerns (or equivalent prior DAR, FPR, or NASA clauses); e.g., contracts awarded before Pub. L. 95-507 and which are within the scope of the contract.
(End of Clause)
1.12 REQUIRED CONSTRUCTION MEETINGS
(a) In addition to meetings required elsewhere in the specifications, the Contractor and any Subcontractors identified by the Contracting Officer or his/her designated representative shall be required to attend a preconstruction conference (after award of the contract but before Commencement of Work) and a post construction meeting (after final acceptance of the work but before final payment is made). The Contractor and identified Subcontractors shall meet with Corps of Engineers personnel at a time and place determined by the Contracting Officer or his/her designated representative.
SECTION 01 10 00.10 38 Page 7
(b) At the preconstruction conference, the Contractor shall be oriented with respect to Government procedures and line of authority in contractual, administrative, and construction matters. Additionally, a schedule of required submittals will be discussed.
(c) Five (5) days prior to the preconstruction conference, the Contractor shall submit the following items:
Certificate of Insurance
Quality Control Plan (see Section 01 45 00.00 10 QUALITY CONTROL, for additional information)
Certificate of Completion of Corps CQC Course
Preliminary Submittal Register (ENG Form 4288 exclusive of Contractor submittal dates)
Letter Appointing Superintendent (see Contract Clause entitled Superintendence by the Contractor, 52.236-6)
List of Subcontractors
Progress Chart
(d) The letter of record will be written documenting all items discussed at the conference and a copy will be furnished by the Contracting Officer or his/her designated representative to all in attendance.
(e) The Contractor and any Subcontractors identified by the Contracting Officer or his/her designated representative shall be required to participate in weekly progress meetings via phone or on site at the discretion of the Contracting Officer or his/her designated representative.
(End of Clause)
1.13 BULLETIN BOARD
Within one (1) calendar day after commencement of work under this contract, the Contractor shall provide at the job site a weatherproof, glass-covered bulletin board for displaying the Fair Employment poster, wage rates, posters and safety bulletins as noted in Section 01 35 26, paragraph DISPLAY OF SAFETY INFORMATION. The bulletin board shall be located in a conspicuous place, easily accessible to all employees, and legible copies of the aforementioned data shall be displayed until work under the contract is complete. No direct payment will be made for the bulletin board.
(End of Clause)
1.14 PLANT
Plant and equipment employed on the dredging work shall be in satisfactory operating condition capable of safely and efficiently performing the work as indicated or specified, and shall be subject to inspection and approval
SECTION 01 10 00.10 38 Page 8 by the Government at all times. A complete listing of all dredging plant and machinery to be used in the work, including booster pumps, skiffs, barges, and other related equipment, shall be submitted and included with the bid package. The listing shall include year and manufacturer, operational capacities, safety features, operating and licensing requirements for operators, and a description of where and how the item of equipment will be employed in the work. The contractor shall perform the scheduled dredging work on this contract with a cutterhead hydraulic pipeline dredge with a minimum of 1,000 horsepower continuous to the pump, and capable of safely and efficiently working in an open water environment in accordance with all of the construction requirements of this contract as indicated and specified. The Contractor shall provide documentation verifying the pumps to be utilized for this work have performed efficiently on previous work in conditions and for material similar to that to be encountered for this contract. The measure of the "Capacity of Plant" shall be its actual performance on the work or similar work to which these specifications apply. No reduction in the capacity of the plant, once inspected and approved by the Government to be sufficient for employment on the work, shall be made except by written permission of the Contracting Officer. Once the dredge certified as specified above has been mobilized to the project site, it shall not be removed from the project site until all scheduled work for the contract has been satisfactorily performed by the Contractor and accepted by the Government, except by written permission of the Contracting Officer. The Government will conduct a Pre-Award Survey for which the Contractor shall be required to provide as a part of his pre-award documentation a signed and notarized certificate that verifies his plant to be used on the scheduled work meets the horsepower and open water operating requirements as specified. The pre-award documentation shall also include verification documentation that indicates on which projects the plant has been used to dredge similar material in an open water environment and at a production rate sufficient to accomplish the work within the performance period stated for this contract.
(End of Clause)
1.15 PLANT LOCATION
The Contractor's plant shall be arranged and located in areas approved by the Contracting Officer or his/her designated representative. This requirement includes the construction plant; offices; shop and storage buildings; housing facilities and all other equipment and materials needed to construct the project.
(End of Clause)
1.16 SIGNAL LIGHTS
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Department of the Army and the Coast Guard governing lights and day signals to be displayed by towing vessels, tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipes or vessels involved in submarine or bank protection operations. The Contractor shall also be in accordance with those regulations governing lights to be displayed on dredge pipeline and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel and the passing by other vessels of floating plant working navigable channels, as approved by the Secretary of the Army and Commandant, U.S. Coast Guard.
SECTION 01 10 00.10 38 Page 9
(End of Clause)
1.17 WORK IN QUARANTINED AREA
USACE and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil (USACE ER 1110-1-5 ). Major portions of all southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations resulting from movement of soil from infested southeastern states. The Contractor shall thoroughly clean all construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds. Equipment shall be cleaned using water under pressure, and hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, all construction equipment and hand tools used for this USACE contract shall be thoroughly cleaned by the Contractor before they are removed from this job site. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements that may be necessary.
(End of Clause)
1.18 NCDOT SPECIFICATIONS
The North Carolina Department of Transportation "Standard Specifications for Roads and Structures English," 2012, (hereinafter referred to as the Standard Specifications) applies to this work when so referenced.
1.19 DEFINITIONS FOR NCDOT SPECIFICATIONS
Wherever in the North Carolina Department of Transportation "Standard Specifications for Roads and Structures" or on the drawings the following terms are used, the intent shall be as indicated below unless otherwise modified within the specifications:
State - - - - - - - - - - - - - - - - - U. S. Government Department or Department of Transportation - - - - - - - - - - - Corps of Engineers Engineer or Chief Engineer- - - - - - - Contracting Officer, Corps of Engineers Materials and Test Unit - - - - - - - - Corps of Engineers Division of Highways- - - - - - - - - - Corps of Engineers Board or Board of Transportation- - - - Corps of Engineers
Where NCDOT materials and test unit requirements are referenced in these specifications, they shall be taken as such and not Corps of Engineers Standards unless otherwise stated.
(End of Clause)
1.20 IDENTIFICATION OF EMPLOYEES
The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer or his/her designated representative. All prescribed identification shall immediately be delivered to the Contracting Officer or his/her designated
SECTION 01 10 00.10 38 Page 10 representative for cancellation upon the release of any employee. When required by the Contracting Officer or his/her designated representative the Contractor shall obtain and submit fingerprints of all persons employed or to be employed on the project.
At least 10 days before mobilizing, the Contractor shall furnish the Contracting Officer or his/her designated representative, names, driver's license, and vehicular tag numbers of each employee that will be working on this project. The Contractor shall require employees to display identification when requested.
If there are any changes in employees who are assigned to the work at any time after the information is submitted and prior to completion of work, the Contractor shall promptly furnish updated information to the Contracting Officer or his/her designated representative.
It will be the responsibility of the Contractor to take those measures which he/she deems necessary to protect his/her plant and personnel prior to beginning work.
(End of Clause)
1.21 PUBLIC CONVENIENCE AND SAFETY
(a) Roads to be closed. No road shall be closed to the public by the Contractor until construction of the new facilities infringe upon the public safety or until construction of the new facilities obliterate the existing facilities. The Contractor shall obtain the Contracting Officer or his/her designated representative's approval before closing any roads.
Barricades, danger, warning and detour signs, as required, shall be erected before closing any roads.
(b) Storage of materials. Materials and equipment shall not be stored within roadway rights-of-way or in such a manner as to pose possible danger or obstruction to the traveling public.
(End of Clause)
1.22 LOAD RESTRICTIONS
The Contractor shall comply with all legal load restrictions in the hauling of materials on public roads beyond the limits of the project. A special permit will not relieve the Contractor of liability for damage which may result from such hauling. The Contractor shall not operate equipment of such weight or so loaded as to cause damage to drainage structures or the roadway, or to any other type of improvement, either completed or under construction. Hauling of materials over the existing surface shall be limited as directed, and in no case shall legal load limits be exceeded unless permitted in writing. The Contractor shall repair, at his own expense, all damage to the work caused by his equipment.
(End of Clause)
1.23 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS
The Contractor shall provide, erect, and maintain all necessary traffic control devices in substantial conformance to Part 6 of the 2003 "Manual on Uniform Traffic Control Devices for Streets and Highways" with
SECTION 01 10 00.10 38 Page 11
Revisions 1 and 2 as published by the U.S. Department of Transportation, Federal Highway Administration, and available on the Internet at: http:// www.muted.fhwa.dot.gov. This requirement shall include flagman as shown in the manual when necessary and the use of electric flashers as conditions of construction may require during hours of darkness. The Contractor shall take all necessary precautions for protection of the work and for the safety of the public at or near the site of construction.
Signing, barricades, lights, and other devices shall be well maintained and repositioned or removed as the progress of the work requires. No substandard, poorly maintained device will be acceptable. Particular attention shall be given to the following:
(a) Removal of barricades and warning signs. As soon as construction advances to the extent that temporary barricades, and signs such as "Detour", "One Way Traffic," etc. are no longer needed to inform the traveling public, such signs shall be removed promptly.
(b) Replacement of signs. When new work is necessary during any period of construction or maintenance, necessary signs shall be replaced as are needed to adequately warn and protect the public in accordance with the provisions outlined above. As soon as the project has been accepted for maintenance, all temporary barricades and warning signs shall be removed promptly.
(c) Cost of protective devices. Unless otherwise shown in the Bidding Schedule, the cost of furnishing, erecting, maintaining, and removing protective devices will not be paid for as separate bid items.
Where the Contractor is required to perform any of these functions, the cost thereof shall be included in the overall bid submitted. Ownership of the temporary warning devices shall remain with the Contractor provided the devices are removed promptly after completion of the work as specified above. If such warning devices are left in place for more than 30 days after the specified time for removal, the Government shall have the right to remove such devices and to claim possession thereof.
(End of Clause)
1.24 CONTRACT AREA AND TRESPASSING
The Contractor shall not inflict damage upon land outside the contract area by unwarranted entry upon, passage through, or placement of material on such land. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, lands or facilities outside the contract area. If such an agreement is made, it shall be in writing and a copy shall be furnished the Contracting Officer or his/her designated representative. The Contractor shall hold and save the Government, its officers, and agents free from liability of any nature or kind arising from any trespassing or damage occasioned by his operations.
(End of Clause)
1.25 PARTNERING
In order to most effectively accomplish this contract, the Government proposes to form a cohesive partnership with the Contractor and its subcontractors. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project done right the first time, within budget and on schedule. Integral to the partnership would be a joint Contractor/Government effort to settle any disputes that
SECTION 01 10 00.10 38 Page 12 may arise without costly and time consuming litigation. To that end, a non-binding procedure such as the Alternate Dispute Resolution process could be developed and agreed upon by both parties when it is determined to be necessary. This partnership would be bilateral in make-up and participation will be totally voluntary. Any cost associated with developing this partnership will be agreed to by both parties and will be shared equally with no change in contract price.
(End of Clause)
1.26 IN-WATER LINES
In order to minimize the risk of sea turtle entanglement, in-water lines (rope, chain, and cable, including the lines to secure turbidity curtains) must be stiff, taut, and unable to loop or tangle. Examples of such lines are heavy metal chains or heavy cables that do not readily loop and tangle. For flexible in-water lines, such as nylon rope or any lines that could loop or tangle, care must be taken to ensure that all lines are rigged properly, utilizing the correct amount of line to best prevent the line from looping and tangling. In all instances, no excess line is allowed in the water.
1.27 LOCAL NOTICE TO MARINERS
(a) The Contractor shall coordinate Local Notice to Mariners with the U.S. Coast Guard (USCG) by contacting USCG District Five at (757) 398-6229 or, alternately, Sector North Carolina at (910) 772-2230.
Contractor shall provide the dredging schedule and location by shoal/tangent/section.
(b) Should the Contractor, during dredging operations, encounter any objects on the channel bottom which could be a hazard to navigation, the Contractor shall notify the USCG immediately with location and other pertinent information necessary for the USCG to issue a Local Notice to Mariners. The Contractor shall provide copies of this information to the Contracting Officer or his/her designated representative.
1.28 ADVANCE NOTICE REQUIREMENT
The Contractor shall provide the Contracting Officer no less than 15 days advance written notice of the date it plans to arrive at each work area and any subsequent remobilizations for any acceptance sections, if applicable, in order that before-dredging surveys can be performed in advance of the Contractor's dredging operations.
1.29 PROTECTION OF EXISTING FACILITIES
The Contractor will not be responsible for any alterations to existing structures or utilities except those made by him for his convenience. The Contractor shall protect all existing structures, including bridges, roadway embankments, utilities and improvements from damage, and, in the event of damage as a result of his operations, the Contractor shall be responsible for their repair, restoration, or for all cost of damage resulting therefrom. In addition, the Contractor shall be responsible for any damage to bridge or culvert structures or railway embankments or track caused by the unauthorized excavation or excavation beyond the project dimensions shown on the plans. If the Contractor elects to have alterations made to any existing structure, utility or other improvements
SECTION 01 10 00.10 38 Page 13 for his convenience, he shall make arrangements with the owner of the facility for such alterations and the agreement shall be reviewed and approved by the Contracting Officer or his/her designated representative prior to their alteration.
(End of Clause)
1.30 WATER CONSERVATION
Water is one of our valuable natural resources. Accordingly, the Contractor shall be judicious in its use in the performance of the work as specified. Water needed for compaction of materials, and dust control shall be obtained from uncontrolled stream flow instead of potable supply sources to the extent available and suitable as determined by the Contracting Officer or his/her designated representative.
(End of Clause)
1.31 COORDINATION WITH OTHER CONTRACTORS
Other Contractors may be working in the vicinity during the time period of this contract. The Contractor shall coordinate the contract operations with other Contractors in the area as needed to avoid conflicts and delays. Any potential delays due to conflicts with other contractors shall be reported to the Contracting Officer or his/her designated representative immediately.
(End of Clause)
1.32 SURVEY DATA
The Contractor shall maintain complete and accurate field notes, sketches, recordings and computations required in establishing the necessary horizontal and vertical control. All survey data shall be recorded in accordance with accepted standards and as approved by the Contracting Officer or his/her designated representative. All the above data shall be available at all times during the progress of the work for ready examination and use by the Contracting Officer or his/her designated representative. Upon request of the Contracting Officer or his/her designated representative, the Contractor shall furnish a copy of the survey data.
1.33 CONTRACT DRAWINGS AND SPECIFICATIONS
(AUG 2000)
(a) The Government will provide to the Contractor, without charge, electronic award plans and specifications via AMRDEC SAFE.
(b) The Contractor shall—
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer or his/her designated representative of any discrepancies;
SECTION 01 10 00.10 38 Page 14
(4) Be responsible for any errors that might have been avoided by complying with this subparagraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings;
and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified in Section 00 01 15 LIST OF DRAWINGS.
(End of Clause)
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 10 00.10 38 Page 15
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 10
PROJECT PROGRESS SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PROJECT SCHEDULER QUALIFICATIONS
PART 2 PRODUCTS
2.1 SOFTWARE
2.1.1 Government Default Software
2.1.2 Contractor Software
2.1.2.1 Primavera
2.1.2.2 Other Than Primavera
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
3.2.2 Activity Durations
3.2.3 Design and Permit Activities
3.2.4 Procurement Activities
3.2.5 Mandatory Tasks
3.2.6 Government Activities
3.2.7 Standard Activity Coding Dictionary
3.2.7.1 Workers Per Day (WRKP)
3.2.7.2 Area of Work Coding (AREA)
3.2.7.3 Modification Number (MODF)
3.2.7.4 Bid Item Coding (BIDI)
3.2.8 Contract Milestones and Constraints
3.2.8.1 Project Start Date Milestone and Constraint
3.2.8.2 End Project Finish Milestone and Constraint
3.2.8.3 Interim Completion Dates and Constraints
3.2.8.3.1 Start Phase
3.2.8.3.2 End Phase
3.2.9 Calendars
3.2.10 Open Ended Logic
3.2.11 Default Progress Data Disallowed
3.2.12 Out-of-Sequence Progress
3.2.13 Added and Deleted Activities
3.2.14 Original Durations
3.2.15 Leads, Lags, and Start to Finish Relationships
3.2.16 Retained Logic
3.2.17 Percent Complete
3.2.18 Remaining Duration
3.2.19 Early Completion Schedule and the Right to Finish Early
SECTION 01 32 01.00 10 Page 1
3.3 PROJECT SCHEDULE SUBMISSIONS
3.3.1 Initial Project Schedule Submission
3.3.1.1 Design Package Schedule Submission
3.3.2 Periodic Schedule Updates
3.4 SUBMISSION REQUIREMENTS
3.4.1 Data
3.4.2 Network Diagram
3.4.2.1 Continuous Flow
3.4.2.2 Project Milestone Dates
3.4.2.3 Critical Path
3.5 WEEKLY PROGRESS MEETINGS
3.6 REQUESTS FOR TIME EXTENSIONS
3.6.1 Justification of Delay
3.6.2 Time Impact Analysis (Prospective Analysis)
3.6.3 Fragmentary Network (Fragnet)
3.6.4 Time Extension
3.6.5 Impact to Early Completion Schedule
3.7 FAILURE TO ACHIEVE PROGRESS
3.7.1 Artificially Improving Progress
3.7.2 Failure to Perform
3.7.3 Recovery Schedule
3.8 OWNERSHIP OF FLOAT
3.9 TRANSFER OF SCHEDULE DATA INTO RMS/QCS
3.10 PRIMAVERA P6 MANDATORY REQUIREMENTS
SECTION 01 32 01.00 10 Page 2
SECTION 01 32 01.00 10
PROJECT PROGRESS SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Project Scheduler Qualifications; G
Initial Project Schedule; G
Periodic Schedule Update; G
1.3 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.
PART 2 PRODUCTS
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting requirements of this specification.
SECTION 01 32 01.00 10 Page 3
2.1.1 Government Default Software
The Government intends to use Primavera P6 and/or Microsoft Project Professional 2016.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required SDEF file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6 or Microsoft Project Professional 2016, that is compliant with this specification, the contractor must request permission from the Government to use the software prior to submission of associated submittals.
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM)
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
SECTION 01 32 01.00 10 Page 4
- Dredging sequencing
- Dredging plant(s) type, size, and anticipated daily production rate(s)
- Environmental windows to include applicable mobilization and demobilization of equipment to include but not limited to pipeline
- Acceptance Sections (by Reach per contract drawings and/or contractor requested areas approved by the Government)
- Mobilization and demobilization durations
- Minimum of one activity per CLIN
- Disposal Area Work (if applicable)
- Submitted schedule timeline calendar days for each month matches the calendar days per month for the respective year
3.2.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.2.3 Design and Permit Activities
Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.
Also include review and correction periods associated with each item.
3.2.4 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.2.5 Mandatory Tasks
Include the following activities/tasks, if applicable, in the initial project schedule and all updates f or each r espect i ve dr edge ar ea or r each.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each to include but not limited to QCP, APP, and EPP).
b. Environmental Windows (start to finish) submission, review and acceptance of design packages.
c. Acceptance Sections (as approved by Govt)
d. Disposal Area & Spillway Survey and Inspections - Pre-Dredge
e. Disposal Area & Spillway Survey and Inspections - Post-Dredge
f. Beach Placement Inspection w/ Agencies - Pre-Dredge
g. Beach Placement Inspection w/ Agencies - Post-Dredge
SECTION 01 32 01.00 10 Page 5
h. Mobilization
i. Demobilization
3.2.6 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: acceptance, design reviews, environmental permit approvals by State regulators, inspections, surveys (before dredge (B/D) and after dredge (A/D)) and Notice to Proceed (NTP) for phasing requirements.
3.2.7 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 AREA 4 Area of work (Government approved Acceptance Section)
3 MODF 6 Modification Number
4…