A21 - NEUSE_SPECS_RTA.PDF

PDF 5 MB Posted

Attached to
NEUSE RIVER-GOLDSBORO SECTION 1135 Federal contract opportunity
Solicitation number
W912PM20B0001
Issued by
Department of the Army Corps of Engineers Engineering District Wilmington

About this file

This solicitation document describes a federal contract opportunity for construction services. The U.S. Army Corps of Engineers, Wilmington District is seeking a contractor to construct a new steel sheet pile weir structure in Goldsboro, North Carolina between $5-10 million. The selected contractor will build the weir to an elevation of 58.0 feet NAVD 88, approximately two feet higher than an existing temporary weir, and 25 feet downstream of the city's temporary weir. As part of the work, the original Corps weir will be cut below grade and the city's temporary weir removed. The solicitation number is W912PM20B0001 and will be issued electronically on or around July 16, 2020, with the bid opening date specified then. The NAICS code is 237990 and size standard is $39.5 million. Offerors must register in SAM to be eligible for award.

View the file

Other files for this federal contract opportunity

Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Neuse River Goldsboro Section 1135 Environmental Improvements Weir Replacement

City of Goldsboro, North Carolina

RTA Design Submittal Specifications

SOLICITATION No. W912PM20B0001

July 2020

Neuse River Goldsboro Section 1135 Environmental Improvements Weir Replacement Solicitation W912PM20B0001

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 00.10 38

SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS

1.3 SUBMITTALS

1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.5 PERFORMANCE AND PAYMENT BONDS

1.6 WATER CONSERVATION

1.7 BULLETIN BOARD

1.8 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS

1.9 SAMPLING, CERTIFICATES, AND TESTING

1.10 CERTIFICATES OF COMPLIANCE

1.11 ACCEPTANCE

1.12 REQUIRED CONSTRUCTION MEETINGS

1.13 SURVEY DATA

1.14 ADDITIONAL SURVEY AND SURVEY PERSONNEL REQUIREMENTS

1.15 WORK IN QUARANTINED AREA

1.16 FINAL AND CONDITIONAL ACCEPTANCE OF GRASSING

1.17 NCDOT SPECIFICATIONS

1.18 DEFINITIONS FOR NCDOT SPECIFICATIONS

1.19 PUBLIC CONVENIENCE AND SAFETY

1.20 MAINTENANCE DURING CONSTRUCTION

1.21 PARTNERING

1.22 LOAD RESTRICTIONS

1.23 PROTECTION OF EXISTING FACILITIES

1.24 HAUL ROADS

1.25 CONTRACT AREA AND TRESPASSING

1.26 MAR MAC PROPERTY ACCESS AND RESTORATION

1.27 COORDINATION WITH OTHER CONTRACTORS

1.28 CONTRACT DRAWINGS AND SPECIFICATIONS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 10 00.10 Page 1

SECTION 01 10 00.10 38

SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

07/18

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NORTH CAROLINA DEPARTMENT OF TRANSPORTATION (NCDOT)

NCDOT Std. Specs. (2006) Standard Specifications for Roads and Structures

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1110-1-5 Plant Pest Quarantined Areas and Foreign Soil Samples

1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS

The Contractor shall be required to comply with the following security requirements mandated by the Department of the Army:

Short-term employees (working on site less than or equal to 6 months): If a criminal history is found, the employee MAY not be allowed to work at the project site at the sole discretion of the Government.

Long-term employees (working on site more than 6 months):

ALL of the following is required WHEN REPORTING FOR WORK -

a) A completed OMB Form No. 3206-0182 (also designated as Optional Form 306).

b) A completed OMB Form No. 3206-0191 (also designated as Standard Form 85P).

c) A resume.

The Government will use all provided information to perform a National Agency Check and Inquiries (NACI) check and will pay the required fee.

The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer or his/her designated representative. All prescribed identification shall immediately be delivered to the Contracting Officer or his/her designated representative for cancellation upon the release of any employee.

SECTION 01 10 00.10 Page 2

(End of Clause)

1.3 SUBMITTALS

Government approval is required for submittals with a "G, A" designation;

submittals not having a "G, A" designation are for information only. When used, a designation following the "G, A" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Subcontractors

Activity Hazard Analysis

Progress Chart ; G, A

Quality Control Plan ; G, A

Within 24 hours of conclusion of physical tests, 5 copies of test results including calibration curves and results of calibration tests.

SD-07 Certificates

Certificate of Insurance

Completion of Corps CQC Course

Letter Appointing Superintendent

Qualifications of the commercial testing laboratory or Contractor's testing facilities ; G, A

1.4 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

ER 415-1-15 dtd 31 OCT 89

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be found to be satisfied in the sole discretion of the Contracting Officer:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

SECTION 01 10 00.10 Page 3

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

( 6) (6) ( 6) (6) ( 6) ( 6) ( 8) ( 9) (5) (5) (5) ( 7)

(c) Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)".

(End of Clause)

1.5 PERFORMANCE AND PAYMENT BONDS

Each bidder shall include his premiums for performance and payment bonds under the appropriate, "Performance and Payment Bonds" contact line item of the Bidding Schedule. Payment to the Contractor therefore, shall not exceed the bid price and shall be made in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount bid in excess of the actual bond premium will be included in the final pay estimate for this contract.

(End of Clause)

1.6 WATER CONSERVATION

Water is one of our valuable natural resources. Accordingly, the Contractor shall be judicious in its use in the performance of the work as specified. Water needed for compaction of roadway and/or foundation materials, and dust control shall be obtained from uncontrolled stream flow instead of potable supply sources to the extent available and suitable as determined by the Contracting Officer.

(End of Clause)

1.7 BULLETIN BOARD

Within one (1) calendar day after commencement of work under this contract, the Contractor shall provide at the job site a weatherproof, glass-covered bulletin board for displaying the Fair Employment poster, wage rates, posters and safety bulletins as noted in Section 01 35 26 , paragraph DISPLAY OF SAFETY INFORMATION. The bulletin board shall be located in a conspicuous place, easily accessible to all employees, and legible copies of the aforementioned data shall be displayed until work

SECTION 01 10 00.10 Page 4 under the contract is complete. No direct payment will be made for the bulletin board.

(End of Clause)

1.8 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS

(a) In accordance with Contract Clause 52.219-9I, Small Business and Small Disadvantage Business Subcontracting Plan, and 52.219-16, Liquidated Damages - Small Business Subcontracting Plan, retainage will be withheld from progress payments in an amount sufficient to protect the Government's ability to assess liquidated damages in accordance with Clause 52.219-16 for the contractor's failure to timely submit Standard Form 294, Subcontracting Report for Individual Contracts, and Standard Form 295, Summary Subcontract Report, reports.

(b) The retainage will be determined in accordance with the following formula:

Total dollar amount for subcontracting to small business multiplied by percentage of actual progress on the contract shall be withheld from the next progress payment due after the Contractor fails to submit a required report. If one or more reports have been submitted before such failure, formula for determining the amount of retainage will be adjusted by deducting any amounts reported as subcontracted to small business from the total dollar amount proposed to be subcontracted and the difference multiplied by the percentage of actual progress.

(c) Subcontracting plans are not required--

(1) For contracts or contract modifications that will be performed entirely outside of any State, territory, or possession of the United States, the District of Columbia, and the Commonwealth of Puerto Rico; or

(2) For modifications to contracts that do not contain the clause 52.219-8, Utilization of Small Business Concerns and Small Disadvantaged Business concerns (or equivalent prior DAR, FPR, or NASA clauses); e.g., contracts awarded before Pub. L. 95-507 and which are within the scope of the contract.

(End of Clause)

1.9 SAMPLING, CERTIFICATES, AND TESTING

(a) General. Within 30 days after acknowledgment of Notice to Proceed, the Contractor shall submit to the Contracting Officer one (1) digital copy of a list of the items for which he proposes to furnish manufacturer's certificates and/or samples for inspection and testing.

The list shall include, but is not limited to the following information:

(1) Name of item

(2) Specification paragraph covering this item

(3) Date sample will be furnished

(4) Delivery date of product

SECTION 01 10 00.10 Page 5

(5) Items for which a certificate will be furnished

(b) Submittals. Any product or item mentioned in these specifications and required to meet Federal, ASTM, AASHTO, U. S. Army or Navy, AREMA, AWWA, and UL Specifications or Codes, specified herein with certain limiting or qualifying requirements, or any product or item which is required to be similar and equal to a specified product or item may require the submission, before delivery of the product or item to the job site, of one or more of the following:

(1) Certificate by the manufacturer that the item meets the contract requirements.

(2) Samples for inspection, comparison, and testing, including destructive tests.

(c) Sample delivery. Unless otherwise specified or authorized, all samples shall be delivered (without cost to the Government) to:

U.S. Army Engineer District, Wilmington Corps of Engineers ATTENTION: Construction Branch 69 Darlington Avenue Wilmington, North Carolina 28403

If required by the Contracting Officer, duplicate samples shall be shipped to the Wilmington District Office at no expense to the Government.

(d) Testing. All tests required in the Technical Provisions shall be made by and at the expense of the Contractor except those material tests specifically excluded which will be made by and at the expense of the Government. All instruments and personnel required for the required tests shall be furnished by the Contractor. The Government reserves the right to interrupt the work to make tests on all facets of concreting and other operations. These tests will be made as necessary to insure conformance to applicable specifications and drawings and will be made by and at the expense of the Government except Contractor sampling support as required by the Technical Provisions. In those instances where testing is specified to be made at the Government's expense, the cost of the initial testing will be at the Government's expense; however, any retesting due to failure of the materials to meet the requirements in the initial test shall be performed at the Contractor's expense. The retests shall be made at laboratories approved by the Contracting Officer. The costs of retests made at Government laboratories will be deducted from the total amount due the Contractor, at actual cost to the Government, unless otherwise specified.

(End of Clause)

1.10 CERTIFICATES OF COMPLIANCE

(l969 MAY OCE)

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 3 copies.

Each certificate shall be signed by an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply.

SECTION 01 10 00.10 Page 6

Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

(End of Clause)

1.11 ACCEPTANCE

(a) Partial Acceptance: If at any time during the prosecution of the project the Contractor completes a portion of the project, such as a bench cut, in its entirety, he may ask the Contracting Officer to make final inspection of such work. If the Contracting Officer finds upon inspection that the work conforms to the requirements of the Contract and that acceptance is in the interest of the Government, he may accept the work as being completed, and the Contractor will be relieved of further responsibility for the work, except as noted in paragraph FINAL AND CONDITIONAL ACCEPTANCE OF SEEDED PLANTING and as specified in paragraph Contractor's Responsibility for Work . Partial acceptance shall in no way void or alter any terms of the Contract.

If any damage attributable to causes beyond the control of the Contractor is sustained by the accepted section or portion of the project, the Contracting Officer may authorize the Contractor to make necessary repairs as a change to the contract.

(b) Final Acceptance: Upon receipt of a written notice from the Contractor of presumptive completion of the entire project, the Contracting Officer Representative will make an inspection. If all work specified in the Contract has been completed, the inspection will constitute the final inspection and the Contracting Officer will make the final acceptance. The Contractor will be notified of final acceptance in writing within 5 days.

If the inspection discloses that any work, in whole or in part, is incomplete or unacceptable, the Contractor shall immediately correct the deficiency. Upon completion or correction of the work, another inspection will be made that will constitute the final inspection. In such event, the Contracting Officer will make the final acceptance and the Contractor will be notified of final acceptance in writing within 5 days. In any event, the Contractor shall maintain the project until final acceptance except under conditions that may be specifically exempted.

(End of Clause)

1.12 REQUIRED CONSTRUCTION MEETINGS

(a) In addition to meetings required elsewhere in the specifications, the Contractor and any Subcontractors identified by the Contracting Officer's Representative shall be required to attend a preconstruction meeting (after award of the contract but before Commencement of Work) and a post construction meeting (after final acceptance of the work but before final payment is made). The Contractor and identified Subcontractors shall meet with Corps of Engineers personnel at a time and place determined by the Contracting Officer's Representative.

(b) At the preconstruction conference, the Contractor shall be

SECTION 01 10 00.10 Page 7 oriented with respect to Government procedures and line of authority in contractual, administrative, and construction matters. Additionally, a schedule of required submittals will be discussed.

(c) Five (5) days prior to the preconstruction conference, the Contractor shall submit the following items:

Certificate of Insurance Quality Control Plan (see Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM), for additional information) Certificate of Completion of Corps CQC Course Preliminary Submittal Register (ENG Form 4288 exclusive of Contractor submittal dates) Letter Appointing Superintendent (see Contract Clause entitled Superintendence by the Contractor, 52.236-6) List of Subcontractors

(d) The letter of record will be written documenting all items discussed at the conference and a copy will be furnished by the Contracting Officer's Representative to all in attendance.

(End of Clause)

1.13 SURVEY DATA

The Contractor shall maintain complete and accurate field notes, sketches, recordings and computations required in establishing the necessary horizontal and vertical control. All survey data shall be recorded in accordance with accepted standards and as approved by the Contracting Officer. All the above data shall be available at all times during the progress of the work for ready examination and use by the Contracting Officer. Upon request of the Contracting Officer, the Contractor shall furnish a copy of above survey data.

(End of Clause)

1.14 ADDITIONAL SURVEY AND SURVEY PERSONNEL REQUIREMENTS

(a) Survey personnel. All quantity surveys required by the Contractor, except those for any periods for which progress payments are requested, shall be made by personnel of a professional engineering and/or surveying firm experienced in the practice of such work including Global Positioning Systems (GPS) surveys. The survey personnel shall have the following minimum qualifications.

(1) Each party chief shall be a Professional Land Surveyor and shall be proficient in the operation of precise and semi-precise instruments. They shall be capable of running horizontal and vertical control of 2nd order accuracy. In the event it is considered advantageous to employ a party chief who is not a Professional Land Surveyor, detailed qualifications of the individual shall be submitted to the Contracting Officer for review and approval.

(2) Instrument men shall be proficient in the operation of precise and semi-precise instruments including transit, level, and alidade, and shall prepare all survey notes in a firm and legible manner.

(3) Rodman and chainman. At least one rodman and one chainman, with a minimum of six months prior experience each, shall be

SECTION 01 10 00.10 Page 8 assigned to each survey part.

(4) Surveying technicians shall be familiar with all phases of surveys and the North Carolina State plane coordinate system. Also they shall be well versed in the computation and adjustment of horizontal and vertical control of 2nd and 3rd order survey.

(b) Original and final cross sections. Original ground surveys shall be taken prior to any earth moving operations. Final-in-place cross sections shall be taken after grading has been accomplished to the lines and grades required by the plans and specifications. All original and final cross sections made for payment purposes shall be taken on an interval not to exceed 100 feet. The Contractor shall provide original cross sections to the Contracting Officer a minimum of 7 days prior to commencement of earth moving operations. Final as-built cross sections shall be provided to the Contracting Officer upon completion of work.

(1) Deliverables. The Contractor shall provide ASCII data files containing tab delimited, x,y,z coordinates, point numbers, feature descriptions, etc., for the cross sections, break lines, and spot elevations that were surveyed. Additionally, the Contractor shall provide tab delimited ASCII files of xyz random points data and tab delimited ASCII file of x, y, z, per order breakline point data. The Contractor shall perform adequate quality control to assure there are neither redundant points between the random point file and break line file nor conflicting information between these files. The Contractor shall submit an Autocad Civil 3D (.dwg) file with surveyed topographic surface . The Contractor shall also submit a n Autocad Civil 3D file displaying all planimetric features mapped in Noth Carolina NAD 83 state plane coordinates (feet). Contouring shall be generated from the surface model files with appropriate contour smoothing and shall be included in the Autocad file. The Contractor shall perform adequate quality control to assure contours do not cross. The Autocad file shall be a three dimensional file with contours, elevation shots at the true elevation, spillway structures with description and inverts, control points, vegetation lines and other similar features. A Government supplied seed file will be provided. All work shall conform to the A/E/C Standards.

Files shall be submitted on a compact disc or via electronic mail. Files for the final as-built surveys shall be provided to the Contracting Officer upon completion of work.

(2) Metadata Record. A metadata record for all as-built surveys shall be created using Corpsmet 95. Appropriate information shall be entered in all required fields. The metadata record shall be submitted on compact disc or via electronic mail along with each spatial data deliverable.

(End of Clause)

1.15 WORK IN QUARANTINED AREA

USACE and the U.S. Department of Agriculture (USDA) have a compliance agreement requiring measures to prevent the spread of certain plant pests that may be present in the soil (USACE ER 1110-1-5 ). Major portions of all southeastern states are in a quarantine area for such pests, including the imported fire ant. In addition, adjacent states to the north have introduced infestations resulting from movement of soil from infested southeastern states. The Contractor shall thoroughly clean all

SECTION 01 10 00.10 Page 9 construction equipment and tools at the previous job site in a manner that ensures that these implements are free from residual soil, egg deposits from plant pests, noxious weeds, and plant seeds. Equipment shall be cleaned using water under pressure, and hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, all construction equipment and hand tools used for this USACE contract shall be thoroughly cleaned by the Contractor before they are removed from this job site. The Contractor shall consult with the USDA jurisdictional office for additional cleaning requirements that may be necessary.

(End of Clause)

1.16 FINAL AND CONDITIONAL ACCEPTANCE OF GRASSING

When, upon completion of the final construction inspection, the work is found to comply fully with contract plans, specifications, change orders, and modifications, the Contracting Officer will give final acceptance, provided a satisfactory stand of grass has been obtained. If, due to the season, satisfactory life and growth of grass cannot be determined when all work is completed, the Contracting Officer shall give the Contractor written notice of conditional acceptance. This notice of conditional acceptance will relieve the Contractor of further construction or maintenance work except as noted until the next growing season, at which time he will be required to produce a living and satisfactory stand of grass and apply water and/or fertilizer as required by the Contracting Officer to produce a grass cover in full compliance with the intent of these specifications. The Contractor shall maintain adequate erosion control measures during periods of conditional acceptance of grassing.

The Government shall withhold the greater of $5,000 per disturbed acre or 1% of the contract amount until permanent stabilization measures for disturbed areas is accepted by the Government and, if applicable, all permits acquired by the Contractor regarding the project erosion and sediment control and project storm water quality from any municipality, county, state agency or federal agency have been closed and respective permit closeout documentation submitted to the Government.

(End of Clause)

1.17 NCDOT SPECIFICATIONS

The North Carolina Department of Transportation "Standard Specifications for Roads and Structures English," 2018, (hereinafter referred to as the Standard Specifications) applies to this work when so referenced.

(End of Clause)

1.18 DEFINITIONS FOR NCDOT SPECIFICATIONS

Wherever in the North Carolina Department of Transportation "Standard Specifications for Roads and Structures" or on the drawings the following terms are used, the intent shall be as indicated below unless otherwise modified within the specifications:

State - - - - - - - - - - - - - - - - - U. S. Government Department or Department of Transportation - - - - - - - - - - - Corps of Engineers

SECTION 01 10 00.10 Page 10

Engineer or Chief Engineer- - - - - - - Contracting Officer, Corps of Engineers Materials and Test Unit - - - - - - - - Corps of Engineers Division of Highways- - - - - - - - - - Corps of Engineers Board or Board of Transportation- - - - Corps of Engineers

Where NCDOT Std. Specs. materials and test unit requirements are referenced in these specifications, they shall be taken as such and not Corps of Engineers Standards unless otherwise stated.

(End of Clause)

1.19 PUBLIC CONVENIENCE AND SAFETY

(a) Roads to be closed. No road shall be closed to the public by the Contractor until construction of the new facilities infringe upon the public safety or until construction of the new facilities obliterate the existing facilities. The Contractor shall obtain the Contracting Officer's approval before closing any roads. Barricades, danger, warning and detour signs, as required, shall be erected before closing any roads.

(b) Storage of materials. Materials and equipment shall not be stored within roadway rights-of-way or in such a manner as to pose possible danger or obstruction to the traveling public.

(End of Clause)

1.20 MAINTENANCE DURING CONSTRUCTION

From the first day any work is done, the Contractor shall maintain in an equally satisfactory condition all of the items of work covered by the contract until they are finished, placed in service unfinished, or until all of the work is finally accepted. This maintenance shall be continuous and effective work prosecuted day by day with adequate equipment to the end that roadway and structures are kept in satisfactory and acceptable condition. The Contractor shall be responsible for maintaining all barricades, danger, warning, and detour signs and lights as specified hereinafter. When no pay item for such maintenance is shown in the Bidding Schedule, the cost of maintenance shall be included in the price bid for other pay items, and no separate payment will be made.

(a) Maintenance when work is suspended. If construction is suspended for any reason, the Contractor shall place the work in such condition as the Contracting Officer directs, before suspension, and shall maintain it in a condition satisfactory to the Contracting Officer throughout the period of the suspension.

(b) Final mowing. When the work is otherwise completed, and before it is finally accepted, the Contractor shall give the seeded areas a final mowing, as directed by the Contracting Officer.

(c) Spilled materials. The Contractor shall not allow spilled materials to remain on the highways. Spillage sufficient to create a traffic hazard shall be removed immediately. Other light spillage shall be removed daily.

(d) Fueling, lubrication and general equipment maintenance shall not take place within 50 ft of a waterbody or wetlands.

SECTION 01 10 00.10 Page 11

(End of Clause)

1.21 PARTNERING

In order to most effectively accomplish this contract, the Government proposes to form a cohesive partnership with the Contractor and its subcontractors. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project done right the first time, within budget and on schedule. Integral to the partnership would be a joint Contractor/Government effort to settle any disputes that may arise without costly and time consuming litigation. To that end, a non-binding procedure such as the Alternate Dispute Resolution process could be developed and agreed upon by both parties when it is determined to be necessary. This partnership would be bilateral in make-up and participation will be totally voluntary. Any cost associated with developing this partnership will be agreed to by both parties and will be shared equally with no change in contract price.

(End of Clause)

1.22 LOAD RESTRICTIONS

The Contractor shall comply with all legal load restrictions in the hauling of materials on public roads beyond the limits of the project. A special permit will not relieve the Contractor of liability for damage which may result from such hauling. The Contractor shall not operate equipment of such weight or so loaded as to cause damage to drainage structures or the roadway, or to any other type of improvement, either completed or under construction. Hauling of materials over the existing surface shall be limited as directed, and in no case shall legal load limits be exceeded unless permitted in writing. The Contractor shall repair, at his own expense, all damage to the work caused by his equipment.

(End of Clause)

1.23 PROTECTION OF EXISTING FACILITIES

The Contractor will not be responsible for any alterations to existing structures or utilities except those made by him for his convenience. The Contractor shall protect all existing structures, including bridges, roadway embankments, utilities and improvements from damage, and, in the event of damage as a result of his operations, the Contractor shall be responsible for their repair, restoration, or for all cost of damage resulting therefrom. In addition, the Contractor shall be responsible for any damage to bridge or culvert structures or railway embankments or track caused by the unauthorized excavation or excavation beyond the project dimensions shown on the plans. If the Contractor elects to have alterations made to any existing structure, utility or other improvements for his convenience, he shall make arrangements with the owner of the facility for such alterations and the agreement shall be approved by the Contracting Officer prior to their alteration.

(End of Clause)

1.24 HAUL ROADS

(1985 HQ USACE)

SECTION 01 10 00.10 Page 12

Whenever practical, one-way haul roads shall be used on this contract.

Haul roads built and maintained for this work shall comply with the following:

(a) One-way haul roads for off-the road equipment; e.g., belly bumps, scrapers, and off-the-road trucks shall have a minimum usable width of 25 ft. One-way haul roads for over-the-road haulage equipment only (e.g., dump trucks, etc.) may be reduced to a usable width of 15 ft.

When the Contracting Officer determines that it is impractical to obtain the required width for one-way haul roads (e.g., a road on top of a levee), a usable width of not less than 10 ft. may be approved by the Contracting Officer, provided a positive means of traffic control is implemented. Such positive means shall be signs, signals, and/or signalman and an effective means of speed control.

(b) Two-way haul roads for off-the-road haulage equipment shall have usable width of 60 ft. Two-way haul roads for over-the-road haulage equipment only may be reduced to a usable width of 30 ft.

(c) Haul roads shall be graded and otherwise maintained to keep the surface free from potholes, ruts, and similar conditions that could result in unsafe operation.

(d) Grades and curves shall allow a minimum sight distance of 200

ft. for one-way roads and 300 ft. for two-way roads. Sight distance is defined as the centerline distance an equipment operator (4.5 ft. above the road surface) can see an object 4.5 ft. above the road surface. When conditions make it impractical to obtain the required sight distance (e.g., ramps over levees), a positive means of traffic control shall be implemented.

(e) Dust abatement shall permit observation of objects on the roadway at a minimum distance of 300 ft.

(f) Haul roads shall have the edges of the usable portion marked with posts at intervals of 50 ft. on curves and 200 ft. maximum elsewhere. Such markers shall extend 6 ft. above the road surface and, for nighttime haulage, be provided with reflectors in both directions.

(End of Clause)

1.25 CONTRACT AREA AND TRESPASSING

Property owners have signed easements which will allow the Contractor to enter and perform the work required by these specifications upon all land lying within the right-of-way limits shown on the drawings. The Contractor's operation shall be confined solely to those areas for which permission has been granted by the owners to enter. The Contractor shall cut only such timber as may be necessary for the prosecution of the work.

The Contractor shall not inflict damage upon land outside the contract area by unwarranted entry upon, passage through, or disposal of material on such land. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, lands or facilities outside the contract area. If such an agreement is made, it shall be in writing and a copy shall be furnished the Contracting Officer. The Contractor shall hold and save the Government, its officers, and agents free from liability of any nature or kind arising from any trespassing or damage occasioned by

SECTION 01 10 00.10 Page 13 his operations.

(End of Clause)

1.26 MAR MAC PROPERTY ACCESS AND RESTORATION

The Contractor shall maintain the existing access road to the construction site at all times during the contract. The Contractor shall not interfere with the daily operation of Mar Mac Aggregates or prevent access to Mar Mac Aggregates by the personnel responsible for operations. Upon completion of the contract work, the Contractor shall restore the existing access road and all temporary staging area to its original or better condition.

A staging area and temporary access within the Mar Mac Aggregates property has been identified on the contract plans. The Contractor shall propose and get approval for all staging and temporary access areas to be used outside the direct work areas. The Contractor’s staging areas, stockpile storage, and temporary access areas shall be placed in approved areas as directed by the Contracting Officer or his/her designated representative.

Temporary movement or relocation of contractor facilities shall be made only when approved by the Contracting Officer or his/her designated representative.

1.27 COORDINATION WITH OTHER CONTRACTORS

Other Contractors may be working in the vicinity during the time period of this contract. The Contractor shall coordinate the contract operations with other Contractors in the area as needed to avoid conflicts and delays.

(End of Clause)

1.28 CONTRACT DRAWINGS AND SPECIFICATIONS

(AUG 2000)

(a) The Government will provide to the Contractor, without charge, two cds of award contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic media as chosen by the Contracting Officer.

(b) The Contractor shall—

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

SECTION 01 10 00.10 Page 14

(1) Large-scale drawings shall govern small-scale drawings;

and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified in Section 00 01 15 LIST OF DRAWINGS.

(End of Clause)

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 10 00.10 Page 15

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 ORDER OF WORK

1.4 OCCUPANCY OF PREMISES

1.5 EXISTING WORK

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests

Utility Connection Requests

Borrow Permits

Excavation Permits

Welding Permits

Burning Permits

Salvage Plan ; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes constructing a new sheet pile weir and riprap scour protection. Work also includes cutting the original USACE weir below grade and removing the temporary Section 408 weir and incidental related work as shown on the Contract drawings.

1.2.2 Location

The work is located in the Neuse River cutoff in the City of Goldsboro, Wayne County, North Carolina. The exact location of the improvements is shown on the Contract drawings.

1.3 ORDER OF WORK

Unless otherwise directed by the Contracting Officer or his/her designated representative the general order of work shall be as follows:

1. Clear and grub staging area and construct temporary gravel construction access road, as required.

2. Install erosion and sediment control features.

3. Install control of water measures.

4. Remove existing riprap to natural grade in the location where the new sheet pile weir is to be placed and temporary weir is to be removed, as required.

5. Install the sheet pile weir.

SECTION 01 11 00 Page 2

6. Remove City of Goldsboro's temporary sheet pile weir and cut down existing Federal weir.

7. Regrade side slopes as required and place riprap, bedding stone and geotextile as shown in the drawings.

8. Restore site and private property, demobilize equipment, apply topsoil and seed disturbed areas.

1.4 OCCUPANCY OF PREMISES

Site access will be through the Mar Mac Aggregates property. Temporary access is to be provided by The City of Goldsboro.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.5 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT PROGRESS SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera and/or Microsoft Project Professional 2016

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.2.1 Level of Detail Required

3.2.2 Activity Durations

3.2.3 Procurement Activities

3.2.4 Mandatory Tasks

3.2.5 Government Activities

3.2.6 Standard Activity Coding Dictionary

3.2.6.1 Workers Per Day (WRKP)

3.2.6.2 Area of Work Coding (AREA)

3.2.6.3 Modification Number (MODF)

3.2.6.4 Bid Item Coding (BIDI)

3.2.6.5 Feature of Work Coding (FOW)

3.2.7 Contract Milestones and Constraints

3.2.7.1 Project Start Date Milestone and Constraint

3.2.7.2 End Project Finish Milestone and Constraint

3.2.7.3 Interim Completion Dates and Constraints

3.2.7.3.1 Start Phase

3.2.7.3.2 End Phase

3.2.8 Calendars

3.2.9 Open Ended Logic

3.2.10 Default Progress Data Disallowed

3.2.11 Out-of-Sequence Progress

3.2.12 Added and Deleted Activities

3.2.13 Original Durations

3.2.14 Leads, Lags, and Start to Finish Relationships

3.2.15 Retained Logic

3.2.16 Percent Complete

3.2.17 Remaining Duration

3.2.18 As-Built Drawings

SECTION 01 32 01.00 10 Page 1

3.2.19 Early Completion Schedule and the Right to Finish Early

3.3 PROJECT SCHEDULE SUBMISSIONS

3.3.1 Initial Project Schedule Submission

3.3.2 Periodic Schedule Updates

3.4 SUBMISSION REQUIREMENTS

3.4.1 Data

3.4.2 Network Diagram

3.4.2.1 Continuous Flow

3.4.2.2 Project Milestone Dates

3.4.2.3 Critical Path

3.5 WEEKLY PROGRESS MEETINGS

3.6 REQUESTS FOR TIME EXTENSIONS

3.6.1 Justification of Delay

3.6.2 Time Impact Analysis (Prospective Analysis)

3.6.3 Fragmentary Network (Fragnet)

3.6.4 Time Extension

3.6.5 Impact to Early Completion Schedule

3.7 FAILURE TO ACHIEVE PROGRESS

3.7.1 Artificially Improving Progress

3.7.2 Failure to Perform

3.7.3 Recovery Schedule

3.8 OWNERSHIP OF FLOAT

3.9 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.10 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01.00 10 Page 2

SECTION 01 32 01.00 10

PROJECT PROGRESS SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation .

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications ; G

Initial Project Schedule ; G

Periodic Schedule Updates ; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting requirements of this specification.

SECTION 01 32 01.00 10 Page 3

2.1.1 Government Default Software

The Government intends to use Primavera P6 and/or Microsoft Project Professional 2016 .

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required SDEF file must be created and supported by the software manufacturer.

2.1.2.1 Primavera and/or Microsoft Project Professional 2016

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system. If Microsoft Project Professional 2016 is selected for use, provide the "mpp" file in a version of Microsoft Project Professional 2016 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6 or Microsoft Project Professional 2016 , that is compliant with this specification, the contractor must request permission from the Government to use the software prior to submission of associated submittals.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM)

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made .

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.2.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

SECTION 01 32 01.00 10 Page 4

- Mobilization and demobilization durations

- Minimum of one activity per CLIN

- Coordination with government (local, state, and federal) agencies

- Submitted schedule timeline calendar days for each month matches the calendar days per month for the respective year

3.2.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.2.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.2.4 Mandatory Tasks

Include the following activities/tasks , if applicable, in the initial project schedule and all updates for each work area .

Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each to include but not limited to QCP, APP, and EPP ).

Submission and approval of as-built drawings.

Mobilization(s)

Demobilization(s)

Final Grass / Disturbed Earth Stabilization -

Contractor's pre-final inspection

Correction of Contractor's pre-final inspection.

Government's pre-final inspection.

Correction of punch list from Government's pre-final inspection.

Final inspection.

3.2.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: environmental permit approvals by State regulators, inspections, surveys and Notice to Proceed (NTP) for phasing requirements.

3.2.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange

SECTION 01 32 01.00 10 Page 5

Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 AREA 4 Area of work

3 MODF 6 Modification Number

4 BIDI 6 Bid Item (CLIN)

5 FOW 20

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.2.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.2.6.2 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.2.6.3 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.2.6.4 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .