Sol_A15PS00683.pdf
PDF 336 KB Posted
- Attached to
- z--Roof Replacement Project - RIS Federal contract opportunity
- Solicitation number
- A15PS00683
About this file
A15PS00683
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 20150611132632186.pdf | ||
| 20150611131829188.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040218861
BIA SPRO 00003
100 NORTH RIVERSIDE DRIVE
Contracting Office Anadarko OK 73005-0328
A03
Jocelyn LittleChief, Contracting Officer
BIA SPRO Branch of Acquisitions P.O. Box 368, 1 Mile North of City, Hwy 281 Anadarko, OK 73005
Jocelyn Littlechief 4052471527 x
06/12/2015
A15PS00683
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
PROJECT TITLE: ROOF REPLACEMENT PROJECT FOR FOUR (4) EXISTING BUILDINGS
DESCRIPTION: Contractor to provide all labor, materials and incidental costs associated with the roof replacement for the following four (4) buildings; BLDG 216, BLDG 217, BLDG 218 AND BLDG 220. All work shall be completed in accordance with the
Statement of Work, contract terms and conditions, specifications and the Davis Bacon
Act.
PROJECT LOCATION: Riverside Indian School, Anadarko, Oklahoma, Caddo County. One
(1) Mile North of City, on Highway 281.
ATTACHMENTS:
1. Statement of Work
2. Davis Bacon Wage Rates
MAGNITUDE OF PROJECT: As required unde FAR Part 36.204, Project Magnitude is between $1,000,000 - $5,000,000
SOCIOECONOMIC PROGRAMS: This procurement is being set-aside exclusely for Service
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
7 60 calendar days and complete it within ________________ ________________ calendar days after receiving
07/22/2015
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
BIA SPRO 00003
100 NORTH RIVERSIDE DRIVE
Contracting Office Anadarko OK 73005-0328
A03
Jocelyn Littlechief
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 25
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
A15PS00683
Disabled Veteran Owned Small Businesses. For informational purposes, the North American
Industry Classification Code (NAICS) is 238160 -
Roofing Contractors with a size standard of
$15mil.
SITE VISIT: See FAR Clause 52.236-27 Site Visit
(Construction) on Page 13.
BID: Bid to be submitted as a Lump Sum and entered on Page 2 of the SF-1442, not broken down by building.
Contacting questions can be directed to Jocelyn
LittleChief at jocelyn.littlechief@bia.gov or call 405.247.1527. For technical questions regarding the plans and specifications contact
Frank Tartsah, Facility Manager at frank.tartsah@bia.gov or call 405.247.5059.
Delivery: 11/01/2015
Delivery Location Code: 0009061840
BIE RIVERSIDE INDIAN SCHOOL
101 Riverside Drive
ANADARKO OK 73005 US
FOB: Destination
Period of Performance: 09/01/2015 to 11/01/2015
00010 Roof Replacement, Building 216
00020 Roof Replacement, Building 217
00030 Roof Replacement, Building 218
00040 Roof Replacement, Building 220
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) 52.211-12 Liquidated Damages - Construction. (SEP 2000) 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999) 52.225-9 Buy American Act - Construction Materials. (SEP 2010) 52.225-10 Notice of Buy American Act Requirement - Construction Materials. (FEB 2009) Description/Specifications Deliveries or Performance Contract Administration Data DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (APR 2013) Contractor Performance Assessment Rating System (CPARS) Contract Clauses 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) 52.228-15 Performance and Payment Bonds - Construction. (OCT 2010) 52.236-26 Preconstruction Conference. (FEB 1995) 52.252-2 Clauses Incorporated by Reference. (FEB 1998) 52.252-5 Authorized Deviations in Provisions. (APR 1984) 52.252-6 Authorized Deviations in Clauses. (APR 1984) 1452.203-70 Restriction on Endorsements (JUL 1996) 1452.226-70 Indian Preference
INDIAN PREFERENCE—DEPARTMENT OF THE INTERIOR (APR 1984)
1452.226-71 Indian Preference Program
INDIAN PREFERENCE PROGRAM— DEPARTMENT OF THE INTERIOR (APR 1984)
1452.233-2 Service of Protest Department of Interior (JUL 1996)(Deviation) List of Documents, Exhibits and Other Attachments Instructions, Conditions, and Notices to Bidders
Solicitation/Contract Form
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than Sixty (60) days from Notice to Proceed. The time stated for completion shall include final cleanup of the premises. (End of clause)
52.211-12 Liquidated Damages - Construction. (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $150.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (End of clause)
52.211-13 Time Extensions. (SEP 2000)
52.211-18 Variation in Estimated Quantity. (APR 1984)
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade 9.0%
Goals for Female Participation for Each Trade 6.9%
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.
Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled Affirmative Action Compliance Requirements for Construction, and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the -
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the covered area is Caddo County, Anadarko, Oklahoma. (End of provision)
52.222-27 Affirmative Action Compliance Requirements for Construction. (FEB 1999)
52.225-9 Buy American Act - Construction Materials. (SEP 2010)
(a) Definitions. As used in this clause -
"Commercially available off-the-shelf (COTS) item"--
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
"Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means -
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph
(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Domestic construction material" means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
"Foreign construction material" means a construction material other than a domestic construction material.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that -
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including -
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph
(d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure QuantityPrice (Dollars)* Item 1:
Foreign construction material _____________________ Domestic construction material _____________________
Item 2: _____________________ Foreign construction material _____________________ Domestic construction material
52.225-10 Notice of Buy American Act Requirement - Construction Materials. (FEB 2009)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American Act--Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9, does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested -
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of provision)
52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)
52.232-5 Payments under Fixed-Price Construction Contracts. (SEP 2002)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if -
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that -
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the unearned amount), the Contractor shall -
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until -
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as -
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after -
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C. 15).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A contract action is any action resulting in a contract, as defined in FAR Subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under subparagraph (d)(2) of this clause shall be -
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
(End of clause)
52.236-2 Differing Site Conditions. (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)
52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984)
52.236-7 Permits and Responsibilities. (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
(APR 1984)
52.236-10 Operations and Storage Areas. (APR 1984)
52.236-11 Use and Possession Prior to Completion. (APR 1984)
52.236-12 Cleaning Up. (APR 1984)
52.236-13 Accident Prevention. (NOV 1991)
52.236-15 Schedules for Construction Contracts. (APR 1984)
52.236-17 Layout of Work. (APR 1984)
52.236-21 Specifications and Drawings for Construction. (FEB 1997)
52.236-26 Preconstruction Conference. (FEB 1995)
52.236-27 Site Visit (Construction). (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for June 30, 2015 at 1000 CT. Participants will meet at the Riverside Indian School, Facility Management Building, 101 Riverside Drive, Anadarko, OK 73005.
(End of provision)
52.242-14 Suspension of Work. (APR 1984)
52.248-3 Value Engineering - Construction. (OCT 2010)
52.249-10 Default (Fixed-Price Construction). (APR 1984)
Description/Specifications
Statement of Work Specifications
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform all work as outlined in the Statement of Work that is included in the solicitation at Section J, List of Documents, Exhibits and other attachments.
Deliveries or Performance
Material Approval Submittals
SUBMITTALS
The submittals in accordance with the clause entitled, "Materials and Workmanship" shall be submitted on the ENG FORM 4025, Transmittal of Shop Drawings, Equipment Data, Material Samples, or Manufacturer's Certificates of Compliance Form for Approval, unless a different form has been reviewed and approved by the COR. Any requirement for the contractor to submit certificates, manufacturing brochures, etc. shall be submitted in three (3) copies. Submittals shall be made at least ten (10) days before items are incorporated in the work and in all instances within 30 days of award. Submittals will normally be approved or disapproved within seven (7) calendar days after submission. Incorporation of materials in a project prior to receipt of approved submittals shall be solely at the risk of the contractor.
https://www.acquisition.gov/sites/default/files/current/far/html/52_233_240.html#wp1113365 https://www.acquisition.gov/sites/default/files/current/far/html/52_233_240.html#wp1113375
Contract Administration Data
DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (APR 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Internet Payment Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor.
To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is:
https://www.ipp.gov. Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
Internally Generated Invoice
Updated Progress Schedules and Payrolls should be submitted directly to the Contracting Officer's Representative (COR).
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation. (End of Template)
Contractor Performance Assessment Rating System (CPARS)
(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts.
The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
(c) We request that you furnish the Contracting Officer with the name, position, title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official.
The report information must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions.
https://www.ipp.gov/
Further details, system requirements, and training information for CPARS is available at http://www.cpars.csd.disa.mil/. The CPARS User Manual, registration for On Line Training for Contractor Representatives, and a practice application may be found at this site.
(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation and the report will be accessible at http://www.cpars.csd.disa.mil/. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official’s narrative and should provide your views on the causes and ramification of the assessed performance. In addition to the ratings and supporting narratives, blocks 1-17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating “No comment” in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: “The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment.” Your response is due within 30 calendar days after receipt of the
CPAR.
(f) The following guidelines apply concerning your use of the past performance evaluation:
(1) Protect the evaluation s “source selection information.” After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.
(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30-day review period.
(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of clause)
Contract Clauses
52.202-1 Definitions. (NOV 2013)
52.203-3 Gratuities. (APR 1984)
52.203-5 Covenant Against Contingent Fees. (APR 1984)
52.203-7 Anti-Kickback Procedures. (OCT 2010) http://www.cpars.csd.disa.mil/ http://www.cpars.csd.disa.mil/
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (JAN 1997)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (JAN 1997)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (OCT 2010)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (May 2011)
52.204-7 System for Award Management. (JUL 2013)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUL 2013)
52.204-13 System for Award Management Maintenance. (JUL 2013)
52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (AUG 2013)
52.211-6 Brand Name or Equal (AUG 1999)
52.214-26 Audit and Records - Sealed Bidding. (OCT 2010)
52.219-8 Utilization of Small Business Concerns. (JUL 2013)
52.219-14 Limitations on Subcontracting. (NOV 2011)
52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-Aside. (NOV 2011)
52.219-28 Post-Award Small Business Program Representation (JUL 2013)
52.222-3 Convict Labor. (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation. (JUL 2005)
52.222-6 Davis-Bacon Act. (JUL 2005)
52.222-7 Withholding of Funds. (FEB 1988)
52.222-8 Payrolls and Basic Records. (JUN 2010)
52.222-9 Apprentices and Trainees. (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)
52.222-11 Subcontracts (Labor Standards). (JUL 2005)
52.222-12 Contract Termination - Debarment. (FEB 1988)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations. (FEB 1988)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
52.222-15 Certification of Eligibility. (FEB 1988)
52.222-21 Prohibition of Segregated Facilities. (FEB 1999)
52.222-26 Equal Opportunity. (MAR 2007)
52.222-27 Affirmative Action Compliance Requirements for Construction. (FEB 1999)
52.222-35 Equal Opportunity for Veterans. (SEP 2010)
52.222-36 Affirmative Action for Workers with Disabilities. (OCT 2010)
52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans. (SEP 2006)
52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010)
52.222-50 Combating Trafficking in Persons. (FEB 2009)
52.222-54 Employment Eligibility Verification. (AUG 2013)
52.223-2 Affirmative Procurement of Biobased Products Under Service And Construction Contracts.
(JUL 2012)
52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997) - Alternate I
(JUL 1995)
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)
52.223-6 Drug-Free Workplace. (MAY 2001)
52.223-15 Energy Efficiency in Energy-Consuming Products. (DEC 2007)
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts.
(MAY 2008)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)
52.227-1 Authorization and Consent. (DEC 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (DEC 2007)
52.227-4 Patent Indemnity -- Construction Contracts. (DEC 2007)
52.228-1 Bid Guarantee. (SEPT 1996)
52.228-2 Additional Bond Security. (OCT 1997)
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective -
(1) For such period as the laws of the State in which this contract is to be performed prescribe; or
(2) Until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request. (End of clause)
52.228-11 Pledges of Assets. (JAN 2012)
52.228-12 Prospective Subcontractor Requests for Bonds. (OCT 1995)
52.228-15 Performance and Payment Bonds - Construction. (OCT 2010)
(a) Definitions. As used in this clause -
"Original contract price" means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection. (i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, 3700 East West Highway, Room 6F01, Hyattsville, MD 20782. Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract. (End of clause)
52.229-3 Federal, State, and Local Taxes. (APR 2003)
52.232-17 Interest. (OCT 2010)
52.232-23 Assignment of Claims. (JAN 1986)
52.232-27 Prompt Payment For Construction Contracts. (JUL 2013)
52.232-33 Payment by Electronic Funds Transfer – System for Award Management. (JUL 2013)
52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)
52.233-1 Disputes. (JUL 2002) - Alternate I (DEC 1991)
52.233-3 Protest after Award. (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)
52.236-8 Other Contracts. (APR 1984)
52.236-26 Preconstruction Conference. (FEB 1995)
52.242-13 Bankruptcy. (JUL 1995)
52.243-4 Changes. (JUN 2007)
52.244-6 Subcontracts for Commercial Items. (DEC 2013)
52.245-1 Government Property. (AUG 2010)
52.246-12 Inspection of Construction (AUG 1996)
52.246-21 Warranty of Construction (MAR 1994)
52.249-2 Termination for Convenience of the Government (Fixed-Price). (MAY 2004) - Alternate I
(SEP 1996)
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://acquisition.gov/far/. (End of clause)
52.252-5 Authorized Deviations in Provisions. (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of (DEVIATION) after the date http://acquisition.gov/far/ of the provision.
(b) The use in this solicitation of any DIAPR (48 CFR Chapter DIAPR) provision with an authorized deviation is indicated by the addition of (DEVIATION) after the name of the regulation. (End of provision)
52.252-6 Authorized Deviations in Clauses. (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter
1) clause with an authorized deviation is indicated by the addition of (DEVIATION) after the date of the clause.
(b) The use in this solicitation or contract of any DIAPR (48 CFR DIAPR) clause with an authorized deviation is indicated by the addition of (DEVIATION) after the name of the regulation. (End of clause)
52.253-1 Computer Generated Forms. (JAN 1991)
1452.201-70 Authorities and Delegations Notice to Contractors (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award.
The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor.
Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
Waive or agree to modification of the delivery schedule;
Make any final decision on any contract matter…