A1 SOW Rev1 PMC REFERB 2022.doc
DOC document 44 KB Posted
- Attached to
- PMC Valve Replacement Federal contract opportunity
- Solicitation number
- N3220522Q2118
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A7 Use of Other than Full and Openredacted signed .pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MSC N7 SERVICE ORDER REQUEST
| Vessel: |
| USNS CATAWBA |
| TASK: |
Authorizing Official
Port Engineer:
Phone:
L Abrams
(757) 374-3099
| REQN: |
| NXXXXX-XXXX-XXX |
| Type Desk: Pete Desimone |
| Date: |
| 3 May 2022 |
| Refurbish PMC VALVES. |
| MSC NORFOLK (>150K): |
1. Statement of Work:
1.1.1 Provide the services of Propulsion system Inc. (OEM), an ABS recognized Marine Propulsion shafting repair facility to refurbish two PMC Valves back to OEM Specification PMC Valve currently located at MSC warehouse Norfolk Virginia and will be shipped at government expense from warehouse to PSI facility. PSI to package crate and ship the newly refurbish PMC valves back to MSC warehouse Norfolk Virginia.
1.1.2 Contractor shall open inspect and refurbish the two propeller hubs using only OEM procedures and supported technical manual with contractor provided OEM parts. Note: PMC valves are critical item and are needed to support the USNS Catawba upcoming dry-docking. Refurbishment shall include the machining, honing, polishing, boring, skin cutting and the replacement of all associated internal soft components to return the PMC valve to OEM specification.
1.1.3 Contractor shall, conduct all required in shop test and operational of the two PMC Valves and verify each valves meets OEM Specification. A written report shall be provided at the completion of the refurbishment process to the port engineer specifying the valves meets OEM requirements.
1.1.4 Contractor shall, following satisfactory in shop testing of the two PMC Valves, prepare the Valves in accordance with OEM Procedure, crate the valves in separate crate and ship to the designated MSC Norfolk warehouse as directed by the port engineer.
2. Work Schedule POP:
23 June, 2022- 30 September, 2022
3. Vessel Location: NA Valve Location: PMC Valve currently located at MSC warehouse Norfolk Virginia
4. Recommended Sources:
Propulsion System Inc 8009 7th Street Suite 1
Seattle Washington 98108 Phone: 206-789-0944
POC: Leon Abrams N7