A06_BlackRock_PV_SpecBinder_100.pdf
PDF 1 MB Posted
- Attached to
- BLACK ROCK SOLAR POWER SYSTEM Federal contract opportunity
- Solicitation number
- 140L6424Q0035
About this file
This document is a set of specifications related to a federal contract opportunity for the Black Rock Solar Power System project located in Arizona. The key details are:
The project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, and other items necessary to remove an existing building and photovoltaic system, abandon underground utilities, and install an off-grid, photovoltaic power system, associated shed, equipment, and electrical components at the Black Rock Lookout site. Specifications cover general requirements, quality control, demolition, concrete work, and other construction details. The project is being solicited by the Department of the Interior Bureau of Land Management Arizona Region under Solicitation Number 140L6424Q0035.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A06_BlackRock_PV_DWGBinder_100.pdf | ||
| B03_DB_Building_Wage_Determination.pdf | ||
| Sol_140L6424Q0035.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLACK ROCK SOLAR
ARIZONA STRIP DISTRICT
BUREAU OF LAND MANAGEMENT
PROJECT SPECIFICATIONS
U.S. DEPARTMENT OF THE INTERIOR
3 May 2024
BUREAU OF LAND MANAGEMENT (BLM) 001500 – 1
BLACK ROCK SOLAR LIST OF DRAWINGS AND SPECIFICATIONS
SECTION 001500
BLACK ROCK SOLAR
LIST OF DRAWINGS AND SPECIFICATIONS
PART 1 – GENERAL
1.1 DESCRIPTION
A. List of Contract Drawings:
1. Index of Sheets:
T1 Title Sheet G1 General Specifications C1 Existing Conditions C2 Lookout Site Plan C3 RV Site Plan C4 RV Site Array C5 Shed Site Plan C6 Shed Details C7 Lookout Details C8 One Line Diagram D1 Details D2 Details
12 Total Plan Sheets in this Contract
B. List of Contract Specifications
1. Index of Specifications
DIVISION 1 - GENERAL REQUIREMENTS
Section 001500 List of Drawings and Specifications Section 010150 General Requirements Section 010250 Definition of Items and Measurement and
Payment
Section 014000 Quality Requirements
DIVISION 2 – EXISTING CONDITIONS
Section 024116 Structural Demolition
DIVISION 3 – CONCRETE
Section 033000 Cast-In-Place Concrete
BUREAU OF LAND MANAGEMENT (BLM) 001500 – 2
BLACK ROCK SOLAR LIST OF DRAWINGS AND SPECIFICATIONS
DIVISION 6 – WOOD AND PLASTICS
Section 061000 Rough Carpentry Section 061600 Sheathing Section 061753 Shop-Fabricated Wood Trusses
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
Section 074113 Metal Roof Panels Section 074646 Fiber Cement Siding Section 076200 Sheet Metal Flashing and Trim Section 079200 Joint Sealants
DIVISION 8 – DOORS AND WINDOWS
Section 081113 Steel Doors and Frames Section 087110 Door Hardware
DIVISION 23 - MECHANICAL
Section 231120 Liquefied-Petroleum Gas Tank and Piping
DIVISION 26 - ELECTRICAL
Section 260500 Electrical Materials and Methods Section 267000 Off-Grid Power System
DIVISION 31 - EARTHWORK
Section 311100 Clearing and Grubbing Section 312250 Earthwork Section 312317 Trenching, Bedding, and Backfill for Utilities Section 312500 Temporary Erosion and Sedimentation Control
END OF SECTION 001500
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 1
BLACK ROCK SOLAR GENERAL REQUIREMENTS
SECTION 010150
GENERAL REQUIREMENTS
PART 1 – SUMMARY OF WORK
1.1 DESCRIPTION
A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery for removal of existing building and photovoltaic system, abandonment of underground utilities, and installation of off grid, photovoltaic power systems, associated shed, equipment, and electrical components.
1.2 LOCATION
A. This project is located at the Black Rock Lookout: 36.792838’ latitude, -113.751826' longitude, 7,330 feet elevation.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The project site is typically accessible April through October.
1.4 USE OF PREMISES
A. Use of Site: Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.
C. Driveways and Entrances: Keep driveways, parking areas, loading areas and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.5 WORK RESTRICTIONS
A. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.
B. Do not schedule work during holidays, BUREAU OF LAND MANAGEMENT (BLM) 010150 – 2
C. Work can be scheduled during weekends or between 6:00 PM to 7:00 AM with written approval from the Contracting Officer (CO).
D. Project Scheduling: Schedule work to minimize impacts to government.
1.6 CONTRACTOR’S RESPONSIBILITIES
A. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.
B. Protect trees and vegetation within project area from damage
1.7 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.8 PERMITS
A. Obtain permits for work required by County, State, or Federal laws or regulations.
B. State electrical inspection is required for this project. Obtain permits for electrical work if the State Electrical Inspector requires a permit to perform the inspection.
PART 2 – ACCIDENT PREVENTION
2.1 DESCRIPTION
A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.
2.2 SUBMITTALS
A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to proceed will not be made until the plan is received. As a minimum the plan shall include:
1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.
2. Name and contact information of supervisor responsible to carry out the plan.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 3
4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a brief report of safety meetings and of inspections within 7 days of the meeting or inspection. Include a list of attendees.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
2.3 ACCIDENT REPORTING
A. Accidents: Report accidents immediately to the Government and assist the Government and other officials as required in the investigation and documentation of the accident.
2.4 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
2.5 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
2.6 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
2.7 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
2.8 SAFETY MEETINGS
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 4
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
2.9 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. Designate and post a hard hat area.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.
2.10 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
PART 3 – SUBMITTAL PROCEDURES
3.1 DESCRIPTION
A. This section includes administrative, procedural, and construction schedule requirements for submittals.
3.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer’s (CO's) responsive action.
B. Informational Submittals: Written information that does not require CO's approval.
3.3 PROCEDURES
A. General: The following procedure requirements pertain to all submittals regardless of the method utilized for submission.
1. Contractor shall review each submittal and check for compliance with the Contract Documents as well as certify to its accuracy. Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
2. The Government Officer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
3. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 5
4. Use only final submittals with mark indicating action taken by CO in connection with construction.
5. The Contractor shall develop a submittal log and track each submittal. The submittal log shall be submitted on a weekly basis to the Contracting Officer (CO).
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Government's receipt of submittal.
1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. The Government will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 10 working days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Stamp each submittal with a uniform approval stamp. Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 2 by 3 inches on label or beside title block to record
Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
D. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
E. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
F. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 6
reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
G. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
H. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
3.4 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections. Submit Action Submittals, except for Application for Payment, electronically via email to the Government.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale in electronic format. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams: Differentiate between manufacturer installed and field installed wiring. Show field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 7
D. Requests for Information (RFI’s): Immediately on discovery of the need for additional information or interpretation of the Contract Documents, prepare and submit an RFI in electronic form.
1. RFI’s submitted by entities other than the Contractor shall not be accepted.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in
Contractor's work or work of subcontractors.
3. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
a. Project name.
b. Project number.
c. Date.
d. Name of Contractor.
e. Name of Contracting Officer.
f. RFI number, numbered sequentially.
g. RFI subject.
h. Specification Section number and title and related paragraphs, as appropriate.
i. Drawing number and detail references, as appropriate.
j. Field dimensions and conditions, as appropriate.
k. Contractor's suggested resolution. If Contractor's solution(s) impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
l. Contractor's signature.
m. Attachments: Include sketches, descriptions, measurements, photos, Product
Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
1) Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
4. CO's Action: The Government will review each RFI, determine action required, and respond. Allow seven (7) working days for the Government’s response for each RFI. RFIs received by the Government after 1:00 p.m. will be considered as received the following working day.
5. On receipt of the Government's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify the Government within seven days if Contractor disagrees with response.
6. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:
a. Project name.
b. Name and address of Contractor.
c. Name and address of Contracting Officer.
d. RFI number including RFIs that were dropped and not submitted.
e. RFI description.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 8
f. Date the RFI was submitted.
g. Date CO's response was received.
h. Identification of related Minor Change in the Work, Construction Change
Directive, and Proposal Request, as appropriate.
i. Identification of related Field Order, Work Change Directive, and Proposal
Request, as appropriate.
E. Contractor Quality Control Submittals: Provide electronic Quality Control submittals, including design data, certifications, manufacturer's instructions, manufacturer's field reports, and other quality-control submittals as required under other Sections of the Specifications.
1. Certifications: Where other Sections of the Specifications require certification that a product, material or installation complies with specified requirements, submit a notarized certification from the manufacturer certifying compliance with specified requirements.
a. Signature: Signed by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.
2. Inspection and Test Reports: Requirements for submittal of inspection and test reports from independent testing agencies are specified in Division 01 Section “Quality Requirements."
F. Contractor Quality Control Plan: Comply with requirements specified in Division 01 Section “Quality Requirements.” Provide in electronic format.
G. Application for Payment: Comply with requirements specified in the Contract Clauses and Division 01 Section “Definition of Items & Measurement and Payment”. Provide in electronic format.
3.5 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections. Submit Informational Submittals electronically via email to Contracting Officer.
1. Number of Copies: Submit two paper copies or one electronic pdf of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
B. Contractor’s Quality Control Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at the site, and submit in electronic format to the CO at weekly intervals:
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 9
1. List of subcontractors at the site.
2. Approximate count of personnel at the site.
3. High and low temperatures, general weather conditions.
4. Accidents and unusual events.
5. Meetings and significant decisions.
6. Stoppages, delays, shortages, and losses.
7. Meter readings and similar recordings.
8. Emergency procedures.
9. Orders and requests of governing authorities.
10. Change Orders received, implemented.
11. Services connected, disconnected.
12. Equipment or system tests and startups.
13. Partial Completions, occupancies.
14. Substantial Completions authorized.
C. Cost Breakdown: Following award, provide a cost breakdown schedule listing main types of work with associated costs. Provide in electronic format.
D. Schedule of Values: Comply with requirements specified in the Contract Clauses.
Provide in electronic format.
E. Accident Prevention Plan: Comply with requirements specified in Division 1 Section “Accident Prevention.” Provide in electronic format.
F. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements. Provide in electronic format.
G. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements. Provide in electronic format.
H. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturers. Provide in electronic format.
3.6 CONSTRUCTION SCHEDULE
A. General: This section includes preparation and submittal of Construction Schedules.
Submit Construction Schedules electronically utilizing email to the Government.
B. Procedures:
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 10
1. Within ten calendar days after date of Notice to Proceed, submit a detailed Construction Schedule setting forth requirements for complete execution of the work. Provide schedules in electronic format.
2. With each Progress Payment Request, submit an Updated Construction Schedule reflecting work progress to the end of the Progress Payment Request period. On each Updated Construction Schedule indicate:
a. Actual start dates for work items started during the report period.
b. The percent complete on activities that have actual start dates.
c. Actual completion dates for work items completed during report period.
d. Estimated remaining duration for work items in progress.
e. Estimated start dates for work items scheduled to start during month following report period.
f. Changes in duration of work items.
C. Schedule Requirements:
1. Schedule contract work and monitor progress using a Critical Path Method (CPM) or similar type scheduling system. Break the schedule into sub-activities to include as a minimum major suppliers, submittal approvals, and major trades.
2. Clearly indicate sequence of construction activities, grouped by base and optional items.
a. For each awarded item show the start and completion of work items, their major components, and interim milestones.
b. Identify and show activities for procurement, delivery, and installation of equipment and materials.
c. Identify interdependence of procurement and construction activities.
d. Identify dates for testing and inspections.
3. Prepare construction Schedule to complete the Work within the contract time requirement.
D. Reviews: The government will review and return the initial Construction Schedule submittal and subsequent schedules with comments. If revisions are noted or required, make revisions based upon comments and resubmit the Schedule.
PART 4 – TEMPORARY FACILITIES AND CONTROLS
4.1 DESCRIPTION
A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.
4.2 UTILITIES
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 11
A. Water Service: Limited water service is available for use at the site upon approval from the Government.
B. Sanitary Facilities: A vault toilet is available for use at the RV site.
C. Electric Power and Lighting Service: Utility power is not available at the site. The Contractor is responsible for providing electrical service deemed necessary for the duration of the construction.
D. Telephone Service: Cell service and telephone service is not available at the site.
4.3 CONSTRUCTION WASTE DISPOSAL
A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.
B. Cleanup construction debris at the completion of each day’s work. Do not use existing on-site trash receptacles for disposal or interim storage of construction debris.
C. Burning of construction debris is not allowed on lands administered by the BLM.
D. Dispose construction debris at an established Sanitary Landfill. Schedule disposal frequency to ensure waste containers are not overflowing.
4.4 STAGING AND SUPPORT FACILITIES INSTALLATION
A. Staging: An area at the project site will be made available for use as a staging area.
Coordinate size and location of staging area with Contracting Officer prior to storing materials. Security and clean-up of staging and support facilities is the responsibility of the Contractor.
B. Storage: Confine storage of materials to storage areas. Coordinate on-site storage requirements with the Contracting Officer.
C. Field offices, recreational vehicle, and storage sheds: An area at the project site can be made available for locating a temporary field office, recreational vehicle parking, and storage sheds. The temporary facilities can remain on site during construction.
Coordinate size and location of area with the Government prior to bringing in temporary facilities. Security and clean-up of temporary facility location is the responsibility of the Contractor.
4.5 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 12
B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights.
C. Fire Protection:
1. Store combustible materials in containers in fire-safe locations.
2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.
3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.
PART 5 – EXECUTION REQUIREMENTS
5.1 DESCRIPTION
A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:
1. General installation of products.
2. Progress cleaning.
3. Protection of installed construction.
4. Inspection and training reports.
5. Correction of the Work.
5.2 EXAMINATION
A. Existing Conditions: Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.
B. Acceptance of Conditions: Examine areas, and conditions, with Installer. Record observations.
1. Examine roughing-in for electrical systems to verify actual locations of connections before equipment and fixture installation.
2. Proceed with installation only after unsatisfactory conditions have been corrected.
Proceeding with the Work indicates acceptance of surfaces and conditions.
5.3 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly.
B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 13
Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.
5.4 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
B. Comply with manufacturer's written instructions and recommendations for installing products.
C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
5.5 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
D. Waste Disposal: Burying or burning waste materials on-site will not be permitted.
Washing waste materials down sewers or into waterways will not be permitted.
5.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
5.7 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 14
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
PART 6 – OPERATIONS AND MAINTENANCE MANUALS
6.1 DESCRIPTION
A. This Section consists of administrative and procedural requirements for operation and maintenance manuals.
6.2 SUBMITTALS
A. Submit two paper copy manuals in final form at least 15 working days before final inspection.
6.3 OPERATION AND MAINTENANCE MANUALS
A. Assemble a complete set of operation and maintenance data indicating the operation and maintenance of each system, subsystem, and piece of equipment not part of a system.
Include operation and maintenance data required in individual Specification Sections and as follows:
1. Operation Data: Include emergency instructions and procedures, system and equipment descriptions, operating procedures, and sequence of operations.
2. Maintenance Data: Include manufacturer's information, list of spare parts, maintenance procedures, maintenance and service schedules for preventive and routine maintenance, and copies of warranties and bonds.
B. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain a title page, table of contents, and manual contents.
C. Title Page: Enclose title page in transparent plastic sleeve. Include the following information:
1. Subject matter included in manual.
2. Name and address of Project.
3. Name and address of Forest.
4. Date of submittal.
5. Name, address, and telephone number of Contractor.
6. Cross-reference to related systems in other operation and maintenance manuals.
D. Table of Contents: List each product included in manual, identified by product name, indexed to content of volume, and cross-referenced to Specification Section.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 15
E. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.
1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.
a. Identify each binder on front and spine, with printed title "OPERATION
AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.
2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.
3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software diskettes for computerized electronic equipment.
4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.
a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.
b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.
F. Content: Include operation and maintenance data required in individual Specification Sections and equipment descriptions, operating standards, operating procedures, operating logs, wiring and control diagrams, and license requirements.
G. Descriptions: Include the following:
1. Product name and model number.
2. Manufacturer's name.
3. Equipment identification with serial number of each component.
4. Equipment function.
5. Operating characteristics.
6. Performance curves.
7. Engineering data and tests.
8. Complete nomenclature and number of replacement parts.
H. Source Information: For each product, list name, address, and telephone number of Installer or supplier.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 16
I. Operating Procedures: Include startup, break-in, and control procedures; stopping and normal shutdown instructions; routine, normal, seasonal, and weekend operating instructions; and required sequences for electric or electronic systems.
J. Systems and Equipment Controls: Describe sequence of operation, and diagram controls as installed.
K. Maintenance Procedures: For each system, subsystem, and piece of equipment not part of a system, include manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, drawings and diagrams for maintenance, nomenclature of parts and components, and recommended spare parts for each component part or piece of equipment.
L. Maintenance and Service Schedules: Include schedules for preventive and routine maintenance and service with standard time allotment.
M. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.
1. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.
Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.
PART 7 – CLOSEOUT PROCEDURES
7.1 DESCRIPTION
A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Inspection procedures.
2. Final completion.
3. Project Record Documents.
4. Final cleaning.
7.2 SUBSTANTIAL COMPLETION
A. Definition of Substantial Completion: The Date certified by the Contracting Officer when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 17
1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.
2. Advise the Government of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.
4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.
5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs, and similar final record information.
6. Deliver tools, spare parts, extra materials, and similar items to location designated by Government. Label with manufacturer's name and model number where applicable.
7. Complete startup testing of systems.
8. Complete final cleaning requirements, including touchup painting.
9. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, the Government will either proceed with inspection or notify the Government of unfulfilled requirements. The Government will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by the Government, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for Final Completion.
7.3 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:
1. Submit certified copy of the Government’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
2. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.
B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, the Government will either proceed with inspection or notify Contractor of unfulfilled requirements. The Government will prepare a final Certificate for Payment
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 18
after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
7.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
7.5 PROJECT RECORD DOCUMENTS
A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.
B. Submit record documents for review prior to request for final inspection.
C. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.
1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.
a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.
b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.
2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.
3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.
4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;
bind each set with durable paper cover sheets. Include identification on cover sheets.
7.6 FINAL CLEANING
A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 19
B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:
1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.
2. Remove tools, construction equipment, machinery, and surplus material from Project site.
3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.
Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.
D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.
END OF SECTION 010150
BUREAU OF LAND MANAGEMENT (BLM) 010150 – 20
This page intentionally left blank.
BUREAU OF LAND MANAGEMENT (BLM) 010250 – 1
BLACK ROCK SOLAR DEFINITION OF ITEMS AND MEASUREMENT
AND PAYMENT
SECTION 010250
DEFINITION OF ITEMS
AND
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends, and another begins; and method of measurements and basis of payment for work items listed in the Schedule of Items.
B. Work: Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it and carrying out all duties and obligations imposed by the contract on the Contractor.
C. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the item in accordance with these specifications and as shown on the drawings.
D. Measurement and payment for contract work shall be made only for and under those items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
B. Lump Sum: Do not measure directly. The amount is complete payment for all work described in the contract and necessary to complete the work for that item.
PART 2 - METHOD OF MEASUREMENT
2.1 GENERAL
A. Methods of measurement for determining final payment is designated on the Schedule of Items for each pay item based upon the following:
1. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall be measured complete and in-place.
BUREAU OF LAND MANAGEMENT (BLM) 010250 – 2
BLACK ROCK SOLAR DEFINITION OF ITEMS AND MEASUREMENT
AND PAYMENT
PART 3 – DEFINITION OF CONTRACT ITEMS
3.1 SCHEDULE OF ITEMS
A. The project Schedule of Items includes several sections to organize the contract items.
Provide item pricing for all items listed in the Schedule of Items. Contract award will be made for all Base Items.
3.2 BASE ITEMS
A. Base Item No. 1 – Mobilization
1. Payment: The contract lump sum price as shown in the Schedule of Items includes materials, equipment, labor and incidentals required to perform all operations necessary for the movement of personnel, equipment, supplies and incidentals to the project site, and other work that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
B. Base Item No. 2 – RV Photovoltaic System
1. Payment: The contract lump sum price as shown in the Schedule of Items includes materials, equipment, labor and incidentals to remove and disposal of existing shed, RV pedestal, concrete pad and other identified items, and install complete renewable power system, shed and concrete pad, electrical, propane tank, gas piping, trenching and backfilling for the RV site.
C. Base Item No. 3 – Lookout Photovoltaic System
1. Payment: The contract lump sum price as shown in the Schedule of Items includes materials, equipment, labor and incidentals to remove and disposal of existing building and photovoltaic system, abandonment of underground utilities, and install complete renewable power system, electrical, trenching and backfilling for the Lookout site.
END OF SECTION 010250
BUREAU OF LAND MANAGEMENT (BLM) 014000-1
BLACK ROCK SOLAR QUALITY REQUIREMENTS
SECTION 014000
QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality assur-ance and quality control including preparing and executing a quality control program.
1.2 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements. Services do not include contract enforcement activities performed by
CO.
1.3 CONFLICTING REQUIREMENTS
A. General: If compliance with two or more standards is specified and the standards es-tablish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to CO for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or speci-fied shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum with reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer un-certainties to CO for a decision before proceeding.
1.4 SUBMITTALS
A. As specified in “Submittal Procedures” in Division 1 Section “General Requirements.”
B. Testing Agencies Qualification Data: Submit proof of qualifications and experience in the form of a recent report on the inspection of the testing agency by a recognized au-thority.
C. Quality Control Plan: At the time of the preconstruction conference, submit for ap-proval a written Contractor Quality Control (CQC) plan.
1. The plan shall include:
a. A list of personnel responsible for quality control and assigned duties.
BUREAU OF LAND MANAGEMENT (BLM) 014000-2
b. A copy of a letter of direction to the Contractor's Quality Control Supervi-sor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sam-pling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and con-tamination as required by regulations and laws.
2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
3. The Government reserves the right to require changes in the plan during the con-tract period as necessary to obtain the quality specified.
4. No change in the approved plan may be made without written concurrence by the Government.
D. Contractor's Quality Control Daily Reports:
1. Provide daily reports for each day of the period of performance, starting with Notice to Proceed. Date and sign all reports by the project manager.
a. Submit a daily report stating “No Work Preformed” if no work was per-formed on a given day.
2. The Quality Control Supervisor shall complete daily reports.
3. Daily reports shall be a comprehensive report of the days activities. Describe in detail work performed by the prime and each subcontractor.
4. Include all three phase control activities in the report.
5. Use the provided template for daily reports at the end of this specification. Re-quest template if not provided with contract documents. Fill out all sections of the template.
6. Include all inspections performed in daily reports. Include how the work was inspected, the results of the inspections, and what corrective action is required, if any, and when it will or did occur.
7. Submit showing all inspections and tests on the first workday following the date covered by the report. Include results of these inspections and tests in the daily report, including if they are in compliance with contract requirements, and if not, corrective action plan.
8. If the CQC plan and Quality Control Daily Reports are not submitted as speci-fied, the Contracting Officer may retain all payments until such time a plan is approved and implemented.
9. Submit weekly certified payrolls no later than on the first workday following the date covered by the report to both the Contracting Officer Representative and Contracting Officer.
E. Test Reports:
1. Submit Daily Test Information Sheets with Quality Control Daily Reports.
2. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
BUREAU OF LAND MANAGEMENT (BLM) 014000-3
3. Submit three copies of complete test results not later than three calendar days af-ter the test was performed.
4. Test Reports shall be certified and include the following:
a. Date of issue.
b. Project title and number.
c. Name, address, and telephone number of testing agency.
d. Dates and locations of samples and tests or inspections.
e. Names of individuals making tests and inspections.
f. Description…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .