A04_SOW.docx

DOCX document 6 MB Posted

Attached to
OVERLAND PASS CHAINING Federal contract opportunity
Solicitation number
140L3922R0025
Issued by
Department of the Interior Bureau of Land Management Nevada Region

About this file

This statement of work describes a federal contract opportunity for chaining treatment services on Bureau of Land Management land in Nevada. The contractor will be required to chain treat approximately 1,667 acres across three units to reduce pinyon pine and juniper coverage. Work will include a double pass chaining treatment with the application of bitterbrush seed during the second pass. The contractor must provide two dozers capable of pulling an Ely anchor chain and seed dribblers. The government will provide the chain assembly, seed, and dribblers. Work must be completed between September 15 and March 15, 2023. The contractor will be evaluated on technical approach, past performance on similar projects, and price per acre for chaining treatment.

View the file

Other files for this federal contract opportunity

Other files attached to OVERLAND PASS CHAINING, newest first.
File Type Posted
Bid_Schedule.docx DOCX document
A06_Map_3.pdf PDF
A06_Map_1.pdf PDF
Sol_140L3922R0025.pdf PDF
B03_Wage_Determination.pdf PDF
A06_Map_2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overland Pass Restoration 2022 Chaining Treatment Statement of Work

General Information and Requirements Description of Work The work required under this contract is to furnish all labor, equipment, supplies and materials, except for specified Government-furnished materials and property (Section III A and B), to chain 1,666 acres (Table 1) of pinyon pine and juniper in two units at Overland Pass in far northwest White Pine County, Nevada. The Big Wash Unit is an option year unit of 996 acres and may be awarded at some time during the 2023 fiscal year (10/1/2022 through 9/30/2023) funding dependent. Awarding of the option year unit will not be contingent upon the completion of other two units. The maps and acreage associated with the chaining units are attached to this statement of work. There is potential for acreage reduction depending on need to avoid sensitive resources. Work required will be a double pass chaining with the second pass conducted in the opposite direction as the first pass. Seeding bitterbrush seed using government provided dribblers mounted to the dozers will be required on the second pass. The Government will apply other seed to the site after the first pass is completed, and prior to the second pass. The chaining units intersect open roads and trails. It will be the contractor’s responsibility to clear vegetation from the roads and trails following the completion of the chaining.

Table 1 – Table of treatment units by line item, treatment and size.

Line Item
Unit Name
Description
Total Acres
010
Overland Pass
2-Way Ely Chaining
975
020
Cracker Johnson
2-Way Ely Chaining
692
030
Big Wash - Option Year
2-Way Ely Chaining
996

The treatment area boundaries will be outlined on a map provided by the Government. The Contractor will be responsible for following the treatment boundaries with a Global Positioning System (GPS) or similar navigation device. The contractor may flag the boundaries of the unit at their discretion however, the contractor will be responsible for the removal of all flagging prior to the final inspection.

The terrain is typically gently to moderately rolling hills; mostly with drainages and flat-top plateau/mesas. Two dozers capable of towing an Ely anchor chain (battleship anchor chain with rail welded perpendicular to the links) will be required to complete the work. Contractors shall submit a bid on a per acre basis for each treatment unit in the format provided in Attachment 1.

Work Layout The work units are depicted on the attached maps. The Government will provide a map to the Contractor with the treatment area boundaries (outside perimeter, islands, etc.) necessary for the work executed under the Contract. The Government will provide a shapefile or map (for upload on GPS unit) of the project area boundary to the Contractor. A map with avoidance areas (archaeological sites; springs; structural range improvements; survey markers such as sections corners, quarter corners, mining claims, etc.) will be provided to the contractor. Survey markers or mining claim markers disturbed or removed during chaining operations shall be reset at the Contractor’s expense. Range improvements or other physical structures damaged or removed during chaining operations shall be repaired or replaced at the Contractor’s expense.

Location and Access to Work Sites The project is located in far northwest White Pine County, Nevada, approximately 80 miles northwest of Ely, Nevada. The project lies along the south end of the Ruby Mountains, near Bald Mountain in Northern Newark Valley (See location map attached).

Access to the treatment area is along the Long Valley/Ruby Marshes Road that leads north from US Highway 50, approximately 30 miles west of Ely Nevada. Overlan travel may be permitted on a case-by-case basis and shall be coordinated with the BLM during the pre-work meeting and as the need arises during implementation. Some of the access roads are unimproved two-track roads that may require four-wheel drive vehicles with good clearance.

The following legal land descriptions apply for the project area:

· Township 25 North; Range 56 East; Sections 25-27, and 35-36; MDM

· Township 25 North; Range 57 East; Sections 22, and 26-28; MDM

· Township 24 North; Range 56 East; Sections 1-2; MDM Environmental Considerations The project site shall be cleaned up, and all refuse removed to an approved landfill at the Contractor’s expense. The Contractor shall not disturb lands adjacent to the project site. Existing access roads and trails within the project area that are damaged by the Contractor shall be restored at the Contractor’s expense to the same condition they were at the commencement of work. Stream channels, springs and other wet areas will be avoided by vehicles and heavy equipment. No new roads shall be constructed during project implementation. Cross-country travel shall be limited and discussed and approved by the BLM. Any heavily travelled areas shall be closed and rehabilitated prior to contract completion. Specifications for closure will be determined on a case-by-case basis in consultation with the BLM.

Any staging areas for fueling or maintenance of equipment shall be approved by the BLM. Any on-site fuel storage tanks shall have a catchment barrier placed underneath the tank to prevent fuel from entering the soil. To prevent excess ground disturbance and potential access roads, the chain shall be disconnected from the dozers prior to moving them to a fueling or maintenance staging area (i.e., do not drag the chain to the same location day after day to fuel dozers).

Vehicles and other equipment used for implementation of the project shall be washed to remove any vegetation and potential noxious weed and invasive species parts prior to beginning the work and following completion of the work.

The dozers shall be configured in a “J” or “U” formation to prevent excessive dragging of the chain. The operators shall be configure the dozers in a fashion so the chain is rolling as much as possible to prevent excessive soil disturbance. See the attached informational document on proper chaining techniques to consider.

Chaining shall not occur when the soil is saturated or where there is sufficient soil moisture that the equipment is leaving substantial ruts as determined by the Contracting Officer or representative. If and when these conditions are encountered, the Contractor shall stop work and notify the Contracting Officer or designated representative.

Identified cultural sites, cadastral survey markers and other leave areas shall not be disturbed by equipment or the chaining operation. Execution of the work shall be planned in a manner to reduce multiple passes on the same piece of ground with the chain.

Work Schedule The work schedule shall be submitted at the pre-work conference. The work schedule may be modified if inclement weather conditions occur. The Contractor shall notify the Contracting Officer’s Representative immediately of any changes in the original work schedule.

The Contractor shall notify the Contracting Officer’s Representative at least ten (10) days prior to finishing the first pass, so seeding can be scheduled. Every effort will be made to prevent delay of the second pass from the seeding operation. However, the Contractor shall be prepared to accommodate seeding operations for at least two days between the first and second pass.

Work Camp Camping will be allowed during project implementation only at sites that have been approved in advance by BLM. Grey and black water will be properly disposed of. All fire regulations and permits shall be followed. All garbage and refuse shall be removed from the camp site by the contractor at the time of project completion. Final payment will be reserved subject to inspection of these sites by BLM and approval of site cleanup.

PROJECT MEETINGS

Pre-Work Conference A pre-work conference will be held prior to the start of work, and within 15 days of Contract award. The Contractor and Contracting Officer’s Representative will schedule a time for the meeting location, date and time. The purpose of the meeting will be to review the required work, the project locations, project specifications, the work schedule, payroll and payments and administrative provisions of the Contract. The Contractor and the persons responsible for coordination of the work shall be present at the meeting. The Contractor shall be prepared to summarize and explain procedures planned for the project.

Progress Meetings Meetings may be called by either the Contracting Officer’s Representative or the Contractor. Meetings shall be held at the project site, or as determined by the Contracting Officer’s Representative.

Final Inspection The final inspection meeting shall be held at the project site, or as determined by the Contracting Officer’s Representative. The Contractor shall notify the Contracting Officer’s Representative at least four (4) working days before the completion date, so the Government can schedule a final inspection. Final payment of the contract will be held pending the completion of a satisfactory final inspection of all associated areas.

Government Furnished and Contractor Furnished Property Materials Furnished by the Government The Government will provide paper and electronic copies of maps with the project area boundaries, and a shapefile of the project area boundaries (for GPS upload). The Government will also provide antelope bitterbrush seed to be applied through government provided dribblers mounted to the dozers on the second pass of the chaining. Seed rate for the bitterbrush shall be approximately 1 pound per acre. Contractor provided dribblers will not be accepted.

Equipment Furnished by the Government Ely Anchor Chain The Government will provide an Ely anchor chain, pigtail chains, swivels, clevises and associated pins, seed dribblers, and repair parts for the above mentioned equipment.

The Ely anchor chain and pigtail chains weigh an estimated 22,000 to 28,500. The overall length of the Ely anchor chain and pigtail chains will be approximately 180 to 200 feet in length.

The Government-furnished materials and equipment will be provided by the Bureau of Land Management located at 702 North Industrial Way in Ely, Nevada. The materials and equipment will be available for pick-up Monday through Friday, 8:00 a.m. to 4:00 p.m., except on holidays. Cody Coombs shall be contacted at least 48 hours in advance for materials and equipment information. He can be reached at (775) 289-1854.

Equipment Furnished by the Contractor 2 Dozers The Contractor will be responsible for furnishing two dozers capable of pulling an Ely anchor chain assembly which is approximately 180 to 200 feet in overall length and weighs an estimated 22,000 to 28,500 pounds and capable of mounting seed dribblers. The dozers must be furnished with skilled and experienced operators and the necessary support. Equipment shall be clean and in good working order and free of fluid leaks. Spills of any fluids will be the contractor’s responsibility to properly mitigate and clean. All spills shall be reported to the BLM representative.

It is the contractor’s responsibility to ensure that the dozer is capable of attaching the government provided dribbler to an appropriate location on the dozer (see attached photos). The dribbler must be mounted so that the tire rests on the track and seed is distributed onto the track during movement of the dozer. If there is a way to attach the dribbler to the dozer it is the contractor’s responsibility to manufacture a suitable way (brackets) to do so.

GPS or Navigation Units The Contractor shall, at a minimum, provide one functioning GPS or tablet unit capable of uploading shapefiles or georeferenced maps and displaying them in a manner that can be followed by the contractor’s personnel. It is expected that the individual assigned by the Contractor who is responsible for using the navigational device to follow and/or mark project area boundaries will be able to operate and trouble shoot the device.

Communication

Dozer operators shall be able to reasonably communicate to one another while chaining to ensure proper alignment and deployment of the chain and to avoid restricted chaining areas. The Contractor is responsible for establishing a communication protocol with the dozer operators.

Measurement and Payment Measurement of Payment Work will be measured and paid for by the number of acres that are fully treated (double chained). The total will be rounded up to the nearest whole acre. Billing may occur once the first pass has been completed for an entire treatment unit. Once the first pass is completed for a treatment unit, the acreage of that treatment unit may be billed at a rate equal to half of the per acre bid price. Area measurements required under this Contract will be measured on a horizontal plane. The determination of the total acreage of completed work will be made by the use of a GPS unit and/or geographic information system (GIS).

The contractor is responsible for reviewing the units sufficiently to determine if they have the technical capacity to complete the project in the terrain.

Basis of Payment Prices and payment will be full compensation for the work described in this section. Payment will be made under the following:

Pay Item
Pay Unit
2-Way Chaining
Acre

The Contracting Officer or representative will make periodic inspections as a basis for progress payments and recommendations for adjustments in work quality. The Contractor or representative is encouraged to observe inspections at the time they are being made. Work performed according to the specifications will be considered acceptable for payment purposes.

Chaining Specifications The following is a detailed summary of the work required to complete the chaining treatment for all units.

Type of Work The project involves the double chaining of pinyon and juniper, and applying bitterbrush seed on the second pass. The area is dominated by pinyon and juniper with declining amounts of native shrubs and perennial, herbaceous species.

A double pass (twice over) chaining shall be conducted. The first pass of all units will be conducted prior to aerial seeding and initiation of the second pass. Once the first pass is completed, aerial seeding will immediately follow. It is anticipated that the dozers and chain may be moved between units without transportation but it is not a guarantee. The aerial seeding will be conducted and administered by the Government. Once the aerial seeding is completed, chaining will immediately follow a second time in the opposite direction. The second pass will occur in the opposite direction of the first pass to assist in further removing targeted vegetation and assist in imbedding the seed mixture into the soil. The Contractor shall notify the Contracting Officer’s Representative at least seven (7) days prior to finishing the first pass so aerial seeding can be scheduled.

Seed dribblers (two on each dozer) shall be attached to the dozers on the second pass to disperse bitterbrush seed at a rate of approximately 1 pound per acre. The contractor shall ensure the dribblers are working and maintain seed in the dribblers.

Treatment Acreage and Areas Current acreage of the project area is 2,663 acres. A minimum of 1,667 acres will be chained, and a maximum of 2,663 acres could be chained. The attached maps delineate the project area boundaries with tentative islands and leave areas. Leave areas and boundaries may be altered prior to implementation of the project to mitigate sensitive resource concerns and may result in further acreage reduction, but reduction will be less than 5% acreage.

The area for chaining occurs on a bench considered to be moderate terrain with some rocks. Tree cover in the area is moderately to extremely dense with size ranging from 4-20+ inch diameter at root collar.

Treatment The chaining shall be conducted based on a double pass. The first pass will be conducted prior to aerial seeding. All units must be completed with the first pass prior to beginning the second pass on any of the units. The Contractor will notify the BLM seven (7) days in advance of when they intend to complete the first pass of the chaining. Once the first pass is completed, aerial seeding will immediately follow. The aerial seeding will be conducted and administered by the BLM under separate contract. Once the aerial seeding is completed, chaining will immediately follow a second time in the opposite direction of the first pass to assist in further removing targeted vegetation and assist in embedding the seed mixture into the soil. The dozers will pull the Ely anchor chain in a “J” or “U” formation with the horizontal dozer spacing at approximately 90 feet and the vertical dozer spacing at approximately 50 feet (“J” formation). The contractor shall adjust dozer spacing or chain length to ensure the chain is “rolling” along the ground as much as possible to prevent dragging and piling of trees. See attached literature on proper chaining technique to follow.

Seed dribblers (provided by the Government) shall be mounted to the dozers on the second pass to disperse bitterbrush seed at approximately 1 pound per acre.

Chaining shall not occur when the soil is saturated or where there is sufficient soil moisture that the equipment is leaving substantial ruts as determined by the Contracting Officer or representative. If and when these conditions are encountered, the Contractor shall stop work and notify the Contracting Officer or designated representative.

Within the project area the units, there are areas that must be completely avoided. Dozers or chain are not allowed to traverse the units, even when just being “walked” to another unit. Those areas will be provided to the contractor. Contractor must coordinate with the government representative regarding movement from one unit to another. In most areas, the chain can be drug between units, but certain areas must be avoided.

Chaining of the second pass shall not occur under conditions when the seed cannot be properly covered by soil. These conditions include deep snow, saturated conditions or frozen ground. If and when these conditions are encountered, the Contractor shall stop work and notify the Contracting Officer or designated representative.

The Contractor is required to protect and avoid archaeological sites, survey markers, existing physical structures and springs located within the project area from damage or removal. In case of destruction or removal by the Contractor, they will be replaced or repaired by the Contractor at the Contractor’s expense. These special areas will be delineated within the avoidance areas and identified within the project area as identified on maps to be uploaded on the navigational device and map provided.

The Government Projector Inspector will conduct periodic inspections to ensure compliance with the contract procedures and specifications.

Loading, Unloading and Transporting Property The Contractor shall be responsible for providing the necessary handling equipment to load and unload materials and equipment. Transportation of all Government furnished items to and from the project sites must be arranged and supplied by the Contractor. The Contractor is responsible for any damages incurred to the materials and equipment, incorporated into the work, while loading, unloading and transporting to and from the project sites. The Contractor is responsible for loading all of the equipment (Ely anchor chain, pigtail chains, swivels, clevises, seed dribblers and other necessary parts) at the BLM ware-yard, transporting all of the equipment to the project site, unloading and assembling all of the equipment at the project site. Once the work is completed, the Contractor is responsible for loading all of the equipment at the project site, transporting it to the BLM ware-yard and unloading the equipment at the BLM ware-yard.

Loading and unloading of equipment should occur on established roads or within the treatment units as much as possible. The Contractor shall coordinate and gain approval of the Contracting Officer’s Representative for mobilizing the equipment to the project site.

The Government will be responsible for transporting the bitterbrush seed to the project work site. The contractor will be responsible for loading and maintaining bitterbrush seed within the seed dribblers.

Equipment Maintenance and Repairs The Contractor is responsible for all maintenance and repairs of Contractor furnished equipment. The Contractor shall complete sufficient maintenance of the equipment to prevent down-time on the project sites. The Contractor shall furnish all necessary lubricating equipment, proper lubricants and service tools to conduct minor maintenance to the dozers at the work site. The Contractor is responsible for checking bolts, nuts and other parts on dozers and Ely anchor chain periodically to ensure tightness and operating efficiency. The Contractor is responsible for all maintenance measures to ensure proper functionality and for safety precautions.

The Contractor shall be equipped with the proper tools to conduct minor repairs to the dozers and the Ely anchor chain assembly at the work site.

The Government will supply parts for the Ely anchor chain, pigtail chains, swivels, clevises and pins that fail due to normal wear. The Contractor will be responsible for parts to the Ely anchor chain, pigtail chains, swivels, clevises and pins if damage occurs due to negligence by the Contractor. The Contractor will be responsible for the installation or repair of all parts, necessitated by normal wear or breakage or due to the fault or negligence of the Contractor.

Under no circumstances will the Contractor make any modifications to the Ely anchor chain assembly without prior approval from the Contracting Officer or Contracting Officer’s Representative. The Contractor is responsible for returning the Ely anchor chain without damage and in good working condition. The Contractor is responsible for returning the swivels cleaned (free of rocks, wood, dirt and other debris) and lubricated.

Areas needed to work and maintain equipment within the treatment unit may be cleared of vegetation while minimizing soil disturbance. These work areas are to be kept to the minimum amount of area required and will not exceed 1/10th of an acre. The BLM will be notified of all of these locations. Upon completion of the work, the contractor may be responsible for hand seeding (the BLM will provide seed) these sites and scattering removed vegetation back on the sites.

Performance Schedule Period of performance for this work shall be as soon as possible following the initial award of the contract, and within the following timeframe: September 15 to March 15. The end of the performance period will be March 15, 2023, barring no unusual delays for weather. The performance period for all option year line items beyond the base year will be one calendar year from the award of the line item, but must be performed during the fall and winter months (September to March).

The Contractor shall be required to start and complete the treatment area within the performance time identified above or as otherwise negotiated during the pre-work conference, provided weather conditions permit. If inclement weather conditions should occur prior to the Contractor completing the project, the Contractor shall be issued a stop work order and the project shall be completed as soon as weather conditions permit.

No extensions will be granted due to these timing restrictions (except as mentioned under I.D.).

If inclement weather conditions should occur prior to the Contractor completing the project, the Contractor shall be issued a stop work order and the project shall be completed as soon as weather conditions permit. If weather prevents the project from being completed within the timeframe above, arrangements shall be made with the Contracting Officer to finish the project the following year.

Evaluation Criteria Offerors will be rated and selected based on the following criteria:

Technical Proposal Vendors are requested to submit a Technical Proposal. Technical proposals should include, at a minimum:

· The suggested technical approach to accomplish the tasks in the Performance Work Statement.

· Type of equipment to be utilized.

· Describe equipment to be used to accomplish the tasks described in the Work Statement.

· Quality control plan

· Describe methods to be utilized to ensure work is being completed as required in the Performance Work Statement (e.g., self-monitoring techniques)

· Describe methods to minimize disturbance and reduce Government oversight

· Key personnel for the project and their relevant experience

· A proposed timeline for project (to be completed no later than dates indicated in Performance Work Statement) Include only information relevant to this project and the Contractor's proposal. Address each item described above.

Past Performance Sufficient information must be presented to enable the Government to evaluate the Contractor's past performance and determine relevancy to this project. It is the quoter’s responsibility to ensure contact references are provided with current and accurate contact information.

Provide a list of at least three projects similar in type and magnitude completed within the last five years. Include a brief narrative of the projects to show relevancy to the work as described in the Performance Work Statement. It is desirable, but not required, that references be other Federal Agencies.

Provide past performance references including, at a minimum, the following information:

1. Name of Project
2. Location of Project
3. Contract Number
4. Total cost for Project
5. Name of Agency/Entity
6. Point of Contact (including Phone & Fax Numbers)
7. Description of services performed (to show relevancy to this project)

Offerors WITHOUT RECENT OR RELEVANT REFERENCES shall submit a statement to such effect in order to be considered as having "Neutral" Past Performance history. All others will be rated deficient in the past performance category.

Past Performance Evaluation: The following factors shall be used in the evaluation of past performance:

· Relevancy of past performance provided (unless a neutral rating is requested per instructions). Relevancy should include projects similar in size and complexity.

· References and past performance of the company to show quality of work necessary to successfully provide these services.

· How quality control was monitored to ensure compliance with specifications.

· Timely completion of projects.

· Ability to manage employees and/or subcontractors to complete the project within schedule.

· Ability to manage project and complete within budget.

Price Offeror are to provide bids on a per acre basis for 2-way chaining on the attached table format, including the per acre cost for base areas and the option area. The price should include all costs associated with the completion of the project. Award of the contract will be completed by awarding the base year line items (Unit 1-3) and funding the option line item as an option year as funding becomes available.

Technical and Past performance, when combined, are significantly more important than price.

Overland Pass, 2022 Chaining Treatment, Statement of Work

Attachment 1 Standard Bid Table

Contract Line Item
Corresponding Treatment Name
Treatment Method
Total Acres
Bid Price ($/acre)
010
Overland Pass
2-Way Ely Chaining
975
020
Cracker Johnson
2-Way Ely Chaining
692
030
Big Wash –Option Year
2-Way Ely Chaining
996

Attachment 1 – Photos

Photo of Government Provided Dribbler

Photo of government provided dribbler attachment bracket.

Attachment 2-Maps image1.jpeg image2.jpeg image3.jpg image4.jpg image5.jpg

File details come from the government source that posted it. Updated .