This service contract requirements document specifies the scope of work for a project to replace carpeting in the second floor offices of the Brown v. Board of Education National Historical Park in Topeka, Kansas. The project involves removing approximately 3,300 square feet of existing commercial-grade sheet carpeting across multiple offices and installing new commercial-grade carpet tiles using a monolithic pattern to appear as sheet carpeting. The scope of work includes subfloor repair, furniture moving, and compliance with all applicable regulations. The selected contractor must complete the work within 30 calendar days. The document provides specifications for the new carpet tiles, underlayment, adhesives and installation accessories. It also outlines submittal requirements, temporary services, project closeout procedures, and warranties required of the contractor.

View the file

Other files for this federal contract opportunity

Other files attached to BRVB Replace Carpet in 2nd Floor Offices, newest first.
File Type Posted
Sol_140P6023Q0051.pdf PDF
B03_DOL_Wage_Determination_(Attachment_2).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Service Contract Requirements V. 2021-10-18 Page | 1

BROWN V. BOARD of EDUCATION

NATIONAL HISTORICAL PARK

REPLACE CARPETING SECOND FLOOR OFFICES

244934

PROJECT STATEMENT OF WORK or

PERFORMANCE WORK STATEMENT

NATIONAL PARK SERVICE

May 2, 2023

Page | 2

TABLE OF CONTENTS

Service General Requirements

Division 9 Finishes

Section 09 68 13 – Tile Carpeting

Drawings and Photographs

Attachment A: Floor Plan

Attachment B: Approximate Room Dimensions

Attachment C: Building Exterior

Attachment D: Room Photographs

Page | 3

SERVICE GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 – LOCATION AND DESCRIPTION OF WORK

1.1 Background: The building was constructed in 1927. During the Rehabilitation project in 2003 carpeting was installed in the 2nd floor offices. The carpet is showing signs of deterioration due to the age of the carpeting and usage.

1.2 Work Covered by the Contract Documents:

A. Project Location: Brown v. Board of Education National Historical Park, 1515 SE Monroe St, Topeka, Ks. 66612

Work consists of:

1. This project will remove approximately 3300 SF of commercial grade high traffic glued down sheet carpeting and install approximately 3300 SF of commercial grade carpet tiles.

2. This Contractor shall verify total square foot area as all sf information in this scope is approximate. This project will include offices 208, 209, 212, 216, Connecting Hall, 219, 220, 226, 227, 228, 229 and 230 designated in the floor plan in attachment A below.

There is an opening between rooms 226 and 230 not shown on plan view. Approximate room dimensions are listed below in attachment B.

3. The new carpet will be laid in monolithic pattern to appear as sheet carpeting.

4. The scope of this project will include the removal of the current sheet carpet and rubber transition strips. Offices have original wood baseboards will not be removed these will stay in place, if shoe molding needs to be removed in these areas for carpet installation these must be replaced after carpet installation. The contractor will replace any damaged shoe moldings with same size and the NPS will paint the new moldings and any areas where the paint is damaged during removal and reinstallation.

5. Room 216 has a concrete floor; all other rooms have a ¼” plywood underlayment. If there is any underlayment damage it must be repaired by installing self-leveling compound or replacement of the subfloor area. Contractor should plan on 10% replacement and 50% of the area needing to be leveled with self-leveling compound.

6. NPS staff will remove IT equipment as needed as well as personal items that are in the office spaces. Contractor will be required to move furniture as needed, such as desks and file cabinets to complete carpet and cove base installation. The cubes in room 216 are attached to the floor and cannot move.

7. There are approximately 12 power and IT boxes in the floor that will remain and there are some piping and compressor penetrations that will have to be worked around. (See photos below)

Page | 4

8. Contractor shall provide carpet tiles and install according to industry standards using premium acrylic-based pressure sensitive adhesive specifically designed for carpet tile installation. Construction adhesive will not be approved as an adhesive for this project.

9. Contractor shall reuse transitions at all door entrances excluding replacing the existing rubber transitions.

10. Removal and proper disposal of existing carpet and cove base.

11. Recycling of old carpet should be arranged by contractor; contractor shall provide documentation of recycling or disposal, if recycling is not possible.

12. Project will be phased based on NPS schedule requirements.

a. Office installation schedule shall be coordinated with NPS Contracting Officer’s

Representative (COR). The contractor can plan on 3 rooms a day at minimum depending on how much sub-floor and leveling is needed.

13. Contractor shall provide all OEM Manuals and Warranty documentation for all products use in this project.

14. The work of this contract shall be performed to meet all federal, state, and local rules and regulations.

B. All work will be performed under a single contract.

Period of performance: Work shall be completed within 30 calendar days. The period of performance is inclusive of zero weather days.

ITEM 2 - EXISTING UTILITIES: N/A This section is not applicable to this contract

2.1 Existing Utilities: The contractor will have to work around existing floor boxes and piping and will notify Contracting Officer (CO), Contracting Officer’s Representative (COR) if any service interruptions are needed for this project.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If contractor damage occurs, alert Contracting Officer (CO) and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. BRVB Superintendent

Compendium - Brown v. Board of Education National Historical Park (U.S. National Park

Service) (nps.gov)

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

https://www.nps.gov/brvb/learn/management/brvb-superintendent-compendium.htm

Page | 5

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;

holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays

(opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site. Limit use of premises to area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Limits: Contractor will be limited to the rooms assigned for each day as agreed upon between the contractor and the COR. The contractor will have on site secure storage for all of their materials.

COR will designate space at preconstruction meeting.

C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

D. Limit site disturbance to rooms working in only. Contractor cannot work in halls or other rooms.

E. Utilities

a. General: Cost or use charges for temporary facilities shall be included in the Contract

Sum as required.

b. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Use resources wisely and minimize waste of water.

Contractor will not put any hazardous waste down the NPS drains or clean tools in bathrooms or other sinks. A janitor sink is available for contractors use in the building.

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

Page | 6

c. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Power may or may not meet your power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

a. Toilets: Restroom are available on the second floor for contractor use.

F. Security and Protection facilities: This section is not applicable.

1 Environmental Protection: Provide protection, operate temporary facilities, and conduct work in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2 Cleaning of Equipment: This section is not applicable.

3 Tree and Plant Protection: This section is not applicable.

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the agreed upon location between the contractor and COR. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3.5 Preservation of Natural Features: This section is not applicable.

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

a. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

b. Address Recycling: Government goal is to salvage and recycle as much nonhazardous waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Photo Documentation:

Contractor must provide existing condition, progress and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email within 7 days from time of taken or as approved by COR.

Page | 7

3.9 Fire and Life Safety:

4 Comply with the requirements of NFPA.

5 Store and handle hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov).

Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

i. Immediately report all spills of hazardous materials to the CO, COR and park.

ii. Maintain a spill emergency response kit.

iii. Train employees how to respond to a spill and use an emergency response kit.

3.10 Noise and Acoustics Management: No radios will be allowed to be played during this project.

ITEM 4 - EXAMINATION OF THE SITE

4.1 All interested contractors are urged to visit the job site and examine existing conditions before submitting quotes. Contractors will be expected to complete the work as quoted.

ITEM 5 – SUBMITTALS

5.1 General Submittal Procedures:

A. General: Prepare and submit submittals for approved equipment as specified

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer.

5.2 Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet.

A. Product Data: Provide component and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.

B. Samples: Submit 2 color samples 24” x 24” minimum in size for all color and product selection.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

C. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

D. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor.

If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons https://www.osha.gov/laws-regs/regulations/standardnumber/1926

Page | 8 for rejection. Resubmit, identifying changes. Any work done before approval shall be at

Contractor's own risk.

ITEM 6 – TEMPORARY SERVICES

6.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.

ITEM 7 - PROJECT CLOSEOUT

7.1 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for intended use.

7.2 Completion: Contractor shall request a final inspection to the Contracting Officer and COR.

7.3 Warranties

A. Workmanship Warranty will be based on project acceptance and will remain in effect for 1 year following acceptance. The contractor will also support manufacturer warrantied items and repair work during this period.

B. Provide all manufacturer warranty information of products installed. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

END OF SECTION

Page | 9

Attachment A: Floor Plan

Page | 10

Attachment B: Approximate Room Dimensions

ROOM APPROXIMATE

DIMENSION

SUBFLOOR FLOOR PENETRATIONS

208 5’ X 17’ PLYWOOD COMPRESSOR etc.

209 32’ X 25’ PLYWOOD NONE

212 24’ X 22’ PLYWOOD NONE

216 29’ X 24’ CONCRETE 10

CONNECTING

HALL

8’ X 4’ CONCRETE NONE

219 6’ X 10’ PLYWOOD NONE

220 6’ X 10’ PLYWOOD NONE

226 8’ X 12’ PLYWOOD NONE

227 17’ X 11’ PLYWOOD NONE

228 17’ X 16’ PLYWOOD 2

229 8’ X 6’ PLYWOOD NONE

230 8’ X 10’ PLYWOOD NONE

Attachment C: Building Exterior

Page | 11

Attachment D: Room Photographs

208 209

212 216

Page | 12

Connecting Hall 219

220 226 & 230

Page | 13

227 228

Floor Penetration Examples

Page | 14

SECTION 096813

TILE CARPETING

PART 1 - GENERAL

1.1 SCOPE OF WORK

A. Project Location: Brown v. Board of Education National Historical Park, 1515 SE Monroe St, Topeka, Ks 66612

B. Building(s) Name/Identifier: Monroe School Building

1.2 SUMMARY

A. Section Includes:

1. Modular carpet tile.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For carpet tile installation, plans showing the following:

1. Columns, doorways, enclosing walls or partitions, built-in cabinets, and locations where cutouts are required in carpet tiles.

2. Carpet tile type, color, and dye lot.

3. Type of installation.

4. Pattern of installation.

5. Type, color, and location of edge, transition, and other accessory strips.

6. Transition details to other flooring materials.

C. Samples: For each exposed product and for each color and texture required.

1.5 INFORMATIONAL SUBMITTALS

A. Product test reports.

B. Sample warranty.

C. Product Data: For adhesives, indicating VOC content of 50 g/L or less.

Page | 15

1.6 CLOSEOUT SUBMITTALS

A. Maintenance data.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: Certified by the International Certified Floorcovering Installers

Association at the Commercial II certification level.

1.8 WARRANTY

A. Special Warranty for Carpet Tiles: Manufacturer agrees to repair or replace components of carpet tile installation that fail in materials or workmanship within specified warranty period.

1. Warranty Period: 10 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 CARPET TILE .GENERAL

A. Basis of Design: Tarkett Aftermath II

1. Products of other manufacturers in compliance with criteria are acceptable based on prior approval by Contracting Officer’s Representative (COR).

a. Acceptable Manufacturers:

1) J&J Industries

2) Interface

3) Mohawk

4) Tarkett (formerly Tandus-Centiva)

5) Other approved equals

B. Construction: Patterned Loop

C. Color: As selected by Contracting Officer’s Representative (COR) from manufacturer’s full range.

D. Fiber Type: Dynex SD Nylon.

E. Density: 7,556 oz./cu. yd.

F. Total Thickness: 0.280 inches

G. Dye Method: 90% Solution Dyed / 10% Yarn Dyed

H. Stitches: 8.5 per inch.

I. Gauge: 5/64

J. Tuft Density: 108.8 tufts/ sq. in.

Page | 16

K. Face Weight: 17.0 oz/sq. yd.

L. Backing System: Modular ethos with Omnicoat Technology with synthetic non-woven primary backing.

1. Total Weight: 94.9 oz./sq. yd. +/- 5%

2. Delamination: No delamination per ASTM D3936

M. Size: 24 by 24 inches.

N. Applied Treatments:

1. Soil Release Treatment: Sentry Soil Protector

2. Stain Release Rating: GSA pass.

O. Sustainable Design Requirements:

1. Sustainable Product Certification: Gold level certification according to ANSI/NSF 140.

P. Performance Characteristics:

1. Appearance Retention Rating: Severe traffic, 3.5 minimum according to ASTM D5252.

2. Flammability (Flooring Radiant Panel: ASTM E 648 Class I (glue down)

3. Smoke Density: ASTM E 662 less than 450.

2.2 INSTALLATION ACCESSORIES

A. Trowelable Leveling and Patching Compounds: Latex-modified, hydraulic-cement-based formulation provided or recommended by carpet tile manufacturer.

B. Adhesives: Water-resistant, mildew-resistant, nonstaining, pressure-sensitive type to suit products and subfloor conditions indicated, that comply with flammability requirements for installed carpet tile, and are recommended by carpet tile manufacturer for releasable installation.

1. Adhesives shall have a VOC content of 50 g/L or less.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Concrete Slabs:

1. Moisture Testing: Perform tests so that each test area does not exceed 1000 sq. ft. (304.8

sq. m), and perform no fewer than three tests in each installation area and with test areas evenly spaced in installation areas.

Page | 17

a. Relative Humidity Test: Using in situ probes, ASTM F2170. Proceed with installation only after substrates have a maximum 75 percent relative humidity level measurement.

b. Perform additional moisture tests recommended in writing by adhesive and carpet tile manufacturers. Proceed with installation only after substrates pass testing.

B. Wood Subfloors: Verify that underlayment surface is free of irregularities and substances that may interfere with adhesive bond or show through surface.

3.2 PREPARATION

A. General: Comply with the Carpet and Rug Institute's CRI 104 and with carpet tile manufacturer's written installation instructions for preparing substrates indicated to receive carpet tile.

B. Use trowelable leveling and patching compounds, according to manufacturer's written instructions, to fill cracks, holes, depressions, and protrusions in substrates. Fill or level cracks, holes and depressions 1/8 inch (3 mm) wide or wider, and protrusions more than 1/32 inch (0.8

mm) unless more stringent requirements are required by manufacturer's written instructions.

C. Concrete Substrates: Remove coatings, including curing compounds, and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, without using solvents. Use mechanical methods recommended in writing by adhesive and carpet tile manufacturers.

D. Broom and vacuum clean substrates to be covered immediately before installing carpet tile.

3.3 INSTALLATION

A. General: Comply with the Carpet and Rug Institute's CRI 104, Section 10, "Carpet Tile," and with carpet tile manufacturer's written installation instructions.

B. Installation Method: Carpet tiles installed in a monolithic method and as recommended in writing by carpet tile manufacturer.

C. Maintain dye-lot integrity. Do not mix dye lots in same area.

D. Cut and fit carpet tile to butt tightly to vertical surfaces, permanent fixtures, and built-in furniture including cabinets, pipes, outlets, edgings, thresholds, and nosings. Bind or seal cut edges as recommended by carpet tile manufacturer.

E. Extend carpet tile into toe spaces, door reveals, closets, open-bottomed obstructions, removable flanges, alcoves, and similar openings.

F. Maintain reference markers, holes, and openings that are in place or marked for future cutting by repeating on carpet tile as marked on subfloor. Use nonpermanent, nonstaining marking device.

G. Install pattern parallel to walls and borders.

Page | 18

H. Protect carpet tile against damage from construction operations and placement of equipment and fixtures during the remainder of construction period. Use protection methods indicated or recommended in writing by carpet tile manufacturer.

END OF SECTION

Page | 19

SUBMITTAL LIST

Note: See tab below for Samples and Instructions. Attach to end of Specification Section 01 33 23 when complete.

Park/PMIS/Project Title

SUBMITTAL REQUIREMENTS (indicate with an "X")

Spec.

Sec.

Par.

No.

Description

INFORMATIONAL ACTION

C E

R T

L

A B

T E

S T

R E

P O

R T

/C A

L C

O R

P L

A N

M fg

D

A

I N

S T

R U

C T

IO

Q U

A L

IF

IC

A T

IO

H

O P

D R

A W

IN

G

M P

L E

M fg

D

A

I N

S T

R U

C T

IO

P ro d u c t

D a ta

096813 1.4A Carpet Tile X

96813 1.4A Transition Strip X

096813 1.4A Leveling Compound X

096813 1.4A Adhesives X

96813 1.4B Carpet Tile Installation X

096813 1.4C Carpet Tile X

096813 1.5A Product Test Reports X

096813 1.5B Sample warranty X

096813 1.5C Product Data, adhesives VOC content, Safety Data Sheets for all chemicals

X

096813 1.6A Maintenance Data X

096813 1.7A Installer Qualifications X

096813 1.8A Warranty X