A.02.10 TECHSPECS_Granite FGW Cable Supply_22Q0120.pdf
PDF 823 KB Posted
- Attached to
- LGA - FGW Rope Chain Supply Federal contract opportunity
- Solicitation number
- W912EF22Q0120
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B.08.03 Solicitation Amendment W912EF-22-Q-0120 0001.pdf | ||
| A.03.09 PLANS (22Q0120).pdf | ||
| B.08.02 Solicitation (W912EF22Q0120).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lower Granite Floating Guide Wall Cable (Supply) W912EF22Q0120
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 78 00.00 28 CLOSEOUT SUBMITTALS
DI VI SI ON 05 - METALS
05 50 13 CABLES ASSEMBLIES AND CONNECTING HARDWARE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
This page intentionally left blank
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 00 00.00 28 Page 1
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran Employment Information http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wct.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material http://www.ebenefits.va.gov/ebenefits-portal/downloads/veterans-hiring-guide-2014.pdf
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
SECTION 01 00 00.00 28 Page 2
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Reviewing Authority
1.2.2.1 Action Elements for Submittal Review
1.2.3 Work
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2 Information Only (I)
1.4 CAD FILE REQUIREMENTS
1.4.1 [CAD File Requirements for Design Drawings Created After Award.
1.4.2 USACE CAD/BIM Technology Center
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Identifying Submittals
1.5.3 Format For Electronic Submittals
1.5.4 Format for SD-02 Shop Drawings
1.5.4.1 Shop Drawing Submittals
1.5.5 Format of SD-03 Product Data and SD-08 Manufacturer's
Instructions
1.5.6 Format of SD-04 Samples
1.5.7 Format of SD-05 Design Data and SD-07 Certificates
1.5.8 Format of SD-06 Test Reports and SD-09 Manufacturer's Field
Reports
1.5.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout
Submittals
1.6 QUANTITY OF SUBMITTALS
1.6.1 Electronic Copies
1.6.2 Hard Copies (HC)
1.6.2.1 Hard Copy Submittals
1.6.3 Official Receipt of Transmittals
1.6.4 Number of Samples SD-04 Samples
1.6.5 Number of Copies of SD-10 Operation and Maintenance Data
1.7 INFORMATION ONLY SUBMITTALS
1.8 SUBMITTAL REGISTER
1.8.1 Use Of Submittal Register
1.8.2 Contractor Use of Submittal Register
1.8.3 Approving Authority Use of Submittal Register
1.8.4 Contractor Action Code and Action Code
1.8.5 Copies Delivered to the Government
1.9 SCHEDULING
1.10 GOVERNMENT APPROVING AUTHORITY
1.10.1 Review Notations
1.11 DISAPPROVED OR REJECTED SUBMITTALS
SECTION 01 33 00 Page 1
1.12 APPROVED/ACCEPTED SUBMITTALS
1.13 APPROVED SAMPLES
1.14 WITHHOLDING OF PAYMENT
1.15 STAMPS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
ATTACHMENTS:
ENG Form 4025
Submittal Register
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
The Contracting Officer (KO) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Make certain that each submittal is complete and in sufficient detail to easily determine contract compliance.
a. Use the same units of weights and measures as the contract drawings.
b. Contractor's Quality Control (CQC) System Manager shall check and approve all items prior to submittal and stamp, sign, and date indicating action taken.
c. Clearly identify any proposed variations from the contract requirements.
d. Include drawings; literature (catalog cuts, diagrams, operating charts or curves); test reports; samples; O&M manuals (including parts list); certifications; warranties; and other necessary information.
e. Obtain submittal approval prior to acquiring the covered material or equipment.
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ERDC/ITL TR-19-6 (Aug 2019) A/E/C Graphics Standard, Release 2.1
ERDC/ITL TR-19-7 (Aug 2019) A/E/C CAD Standard - Release 6.1
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required to be approved prior to commencing work on site. Submittals required prior to the start of the next major phase of the construction on a multi-phase contract. Schedules or tabular list of data or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
SECTION 01 33 00 Page 3
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Unless otherwise specified testing must have been completed within three (3) years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
SECTION 01 33 00 Page 4
Confined space entry permits.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Reviewing Authority
Office or designated person to review submittal.
1.2.2.1 Action Elements for Submittal Review
AE Architect/Engineer C Engineering & Construction Division, Construction Branch CS Cybersecurity, Electrical Design Lead DDC Walla Walla District Dive Coordinator, Safety Office A Engineering & Construction Division, Structural Design
"Architectural" ECC Operation's Division, Environmental Compliance Coordinator ECCS Operation's Division, Environmental Compliance Coordinator and
Safety Officer OPC Operation's Division, Pesticide Coordinator EL Engineering & Construction Division, Electrical Design GT Engineering & Construction Division, Geotechnical Design H Engineering & Construction Division, Hydraulic Design ME Engineering & Construction Division, Mechanical Design ST Engineering & Construction Division, Structural Design TL Engineering & Construction Division, Technical Lead HDC Hydroelectric Design Center GE Engineering & Construction Division, General Engineering GS Engineering & Construction Division, Geospatial PMP Project Management Division, Planning SO Safety Office SLE Security Law Enforcement Officer EOC Engineering Design, Project Operations and Construction CERL Construction Engineering Research Laboratory EC Engineering and Construction
1.2.3 Work
As used in this SECTION, on- and off-site construction [fabrication] required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
G - This code is for submittals requiring government approval that
SECTION 01 33 00 Page 5 were listed in the original government-generated specs.
I - This code is used for both Government-generated submittals and Contractor-generated submittals. This code is reserved for submittals that don't require approval, e.g. test reports.
1.3.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the KO.
Government approval is required for any variations from the Solicitation or Accepted Proposal and other items as designated by the KO. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.3.2 Information Only (I)
Submittals not requiring Government approval will be for information only
(FIO).
1.4 CAD FI LE REQUI REMENTS
The following applies to all CAD File submittals for this Contract, unless otherwise noted:
a. Furnish CAD files in the latest version of Bentley DGN format, for all CAD Files submitted by the Contractor in performance of this contract.
b. Unless otherwise noted, all CAD Files shall meet A/E/C CAD and Graphic Standards, as follows:
1. Compliant with the A/E/C CAD Standard ERDC/ITL TR-19-7 , A/E/C Graphics Standard ERDC/ITL TR-19-6 .
c. CAD Files shall have presentation graphics which can be edited by Bentley software (with the exception of photographs). Presentation graphics typically consist of drawing elements such as lines, arcs, shapes, text, and their attributes (e.g., color, width, line style).
d. If CAD files are developed in a format other than the specified Bentley software, furnish the following:
1. The converted CAD files in Bentley DGN format, in compliance with all specified CAD file requirements.
2. The original CAD files in their native file format.
e. In addition to CAD files, submit an ADOBE .pdf of each CAD File.
The pdfs and the CAD files shall be identical.
f. Submit files using the DoD SAFE (Secure Access File Exchange) website as directed by the Contracting Officer.
SECTION 01 33 00 Page 6
1.4.1 [CAD File Requirements for Design Drawings Created After Award.
In addition to the requirements listed above, when the Contractor prepares design drawings for requirements stated in the contract, for a modification, or as part of a Value Engineering Change Proposal, the following requirements apply:
a. Electronic files shall be .dgn format with element types that can be edited (i.e. no attached raster files, .dxf, or .dwg file formats will be accepted). The Contractor shall use the furnished Walla Walla District title block border and seed files to match AEC CAD standard for all drawings with the appropriate firm name included within the title block.
b. Each drawing file shall be completely independent of any data in any other file, including fonts and shapes not included with the basic CAD software program utilized. Drawing files with external references or special fonts are not acceptable. All displayed graphic elements on all levels of the drawing file shall be part of the project drawing image. The drawing file shall not contain any graphic element that is not part of the drawing image.
c. Provide an index of drawings sheet in CAD as part of the drawing set, and an electronic list in Microsoft Excel of all drawings.
Include the electronic file name, the sheet reference number, the sheet number, and the sheet title, containing the data for each drawing.
d. Design drawings may be prepared more like shop drawings to minimize construction submittals after final designs are approved. Therefore, the Contractor is encouraged to prepare and submit with the design drawings, appropriate connection, fabrication, layout, and product specific drawings.
e. The Contractor-originated drawings will be used as the basis for the record drawings. Shop drawings included as design documents shall comply with the same drawing requirements such as drawing form, sheet size, layering, lettering, and title block used in design drawings.
f. All final Contractor-originated design drawings shall be signed, dated, and bear the seal of the registered architect or the registered engineer of the respective discipline. This seal shall be the seal of the Designer of Record for that drawing, and who is professionally registered for work in that discipline. Application of the electronic seal and signature accepts responsibility for the work shown thereon.
1.4.2 USACE CAD/BIM Technology Center
The USACE CAD/BIM Technology Center hosts all standard content for USACE.
This content can be accessed through the CAD/BIM Technology Center website, https://cadbimcenter.erdc.dren.mil .
1.5 PREPARATION
1.5.1 Transmittal Form
The attached sample transmittal form (ENG Form 4025) shall be used to
SECTION 01 33 00 Page 7 submit both Government approved and information only submittals in accordance with the instructions on the reverse side of the form.
Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Identifying Submittals
When submittals are provided by either the Prime Contractor or subcontractor, the Prime Contractor is responsible to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title, location, and date.
b. Contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier Contractor associated with submittal.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add a number suffix on submittal description, for example, submittal 18 would become 18.1, to indicate the resubmission.
h. Product identification and location in project.
The sequence of submission of drawings shall be such that all information is available for checking each drawing when it is received. Contract number and project shall be shown directly above the revision space on all drawings submitted. Drawing details and notes shall be of such quality and clarity and of sufficient definition and line weight as to permit sharp and totally legible scanning. All items shall be adequately identified to show where they will be used, and shall be referenced to applicable contract drawings and specification section.
All shop drawings submitted on a single transmittal (ENG form 4025) shall pertain to only one (1) specification section. Computed weights of all items shall be indicated on the shop drawings. Where drawings are submitted for either one (1) assemblies consisting of more than one (1) piece of equipment, or two (2) systems consisting of numerous components dependent one on the other for matching or compatible characteristics, complete information shall be submitted on all such related components at the same time.
SECTION 01 33 00 Page 8
1.5.3 Format For Electronic Submittals
The PDF file name of all submittals shall include the contract and transmittal number.
a. example: 19C0005 01 35 29.10 28-1 Item 1, 5
b. re-submittal example: 19C0005 01 35 29.10 28-1.1 Item 1, 5
All electronic submittals shall be in color and digitally searchable. All pages in the file shall be oriented so that no rotation or manipulation to view is needed.
1.5.4 Format for SD-02 Shop Drawings
All shop drawings prepared by the Contractor for this contract shall be formatted to American National Standards Institute (ANSI D).
a. All shop drawings shall have a title block prepared by the Contractor independent of any Contract Drawing. Include a revision block.
b. Title block shall include project title, sheet description, sheet number, contract number and issue date.
c. Revision block shall contain revision mark, revision description, date of revision.
d. Each Sheet shall have a unique number.
e. Each sheet shall have the Contractor Firm name on it.
f. CAD requirements for Shop Drawings include the following:
1. CAD file(s) meeting requirements of paragraph "CAD File Requirements" in this SECTION.
2. An Adobe .pdf copy of the corresponding CAD file(s). The pdfs and CAD files shall be identical.
3. Shop drawing format does not need to comply with A/E/C CAD and Graphic Standards.
1.5.4.1 Shop Drawing Submittals
Shop Drawing Submittals are required as follows:
1. As shown and specified in the plans and specifications during design and Construction.
2. As specified in SECTION 01 78 00.00 28 CLOSEOUT SUBMITTALS, paragraph FINAL SHOP DRAWINGS.
1.5.5 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions
a. Present product data submittals for each section as required.
Include table of contents, listing page and catalog item numbers for product data.
SECTION 01 33 00 Page 9
b. Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains. Mark out all product data not pertaining to the product being submitted.
c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist.
Identify this material as developed specifically for project, with information and format as required for submission of SD-07 Certificates.
d. Provide all software code, user interfaces, logic and graphic information, manuals, documentation, etc. in English, only.
e. Provide product data in English dimensions. Where product data are included in preprinted catalogs with Metric units only, submit English dimensions on separate sheet.
f. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, submit as specified for SD-07 Certificates.
g. Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the KO. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
h. Collect required data submittals for each specific material, product, unit of work, or system into a single submittal. Mark the submittal to clearly indicate what choices, options, and portions of the product offering will be incorporated into the work. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of construction effort.
i. Submit manufacturer's instructions prior to installation.
1.5.6 Format of SD-04 Samples
a. Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:
(1) Sample of Equipment or Device: Full size.
(2) Sample of Materials Less Than 2 by 3 inches built up to 8-1/2 by 11 inches.
SECTION 01 33 00 Page 10
(3) Sample of Materials Exceeding 8-1/2 by 11 inches: Cut down to 8-1/2 by 11 inches and adequate to indicate color, texture, and material variations.
(4) Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
(5) Sample of Non-Solid Materials: Pint. Examples of non-solid materials are sand and paint.
(6) Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
(7) Sample Panel: 4 by 4 feet.
(8) Sample Installation: 100 square feet.
b. Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three (3) units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
c. Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at time of use.
d. Recording of Sample Installation: Note and preserve the notation of area constituting sample installation but remove notation at final clean up of project.
e. When color, texture or pattern is specified by naming a particular manufacturer and style, include one (1) sample of that manufacturer and style, for comparison.
1.5.7 Format of SD-05 Design Data and SD-07 Certificates
Provide design data and certificates formatted for 8-1/2 by 11 inches paper. Provide a bound volume for submittals containing numerous pages.
1.5.8 Format of SD-06 Test Reports and SD-09 Manufacturer's Field Reports
a. Provide reports formatted for 8-1/2 by 11 inches paper in one complete file.
b. Indicate by prominent notation, each report in the submittal.
Indicate specification number and paragraph number to which it pertains.
1.5.9 Format of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
When the submittal includes a document which is to be used in the project or become part of the project record, other than as a submittal, do not apply Contractor's approval stamp to the document, but to a separate sheet
SECTION 01 33 00 Page 11 accompanying the document.
1.6 QUANTITY OF SUBMITTALS
The quantities listed below are for all submittals except for the closeout quantities of submittals required in SECTION 01 78 00.00 28
CLOSEOUT SUBMITTALS.
1.6.1 Electronic Copies
Each submi t t al shal l be submi t t ed i n PDF f or mat , unl ess ot her wi se not ed, t o t he Lower Gr ani t e COR. The COR emai l wi l l be pr ovi ded af t er awar d.
Submittal files too large to send via e-mail shall be submitted using the DoD SAFE (Secure Access File Exchange) website as directed by the Contracting Officer.
1.6.2 Har d Copi es ( HC)
In addition to the electronic submission required for all submittals, hard copies shall also be submitted for submittals designated with a (HC) in the submittal title or as specifically designated by type of submittal or as stated in the technical specification for that given submittal.
submittal title example: Draft O&M Manuals and Parts Catalogs (HC)
1.6.2.1 Hard Copy Submittals
SUBMI TTALS WI TH AN HC DESI GNATED REQUI RE A HARD COPY SUBMI SSI ON I N THE
QUANTI TI ES DI SCUSSED BELOW:
Submit two (2) paper copies of all (HC) designated submittals to the address below, unless otherwise noted. Each copy shall be sent with the ENG Form 4025.
District Commander
ATTN: CENWW-EC-C
Walla Walla District Corps of Engineers 201 North Third Avenue Walla Walla, WA 99362-1876
1.6.3 Official Receipt of Transmittals
Official receipt of a transmittal that is sent electronically begins the business day after the Government receives that transmission by e-mail or through the Safe Access File Exchange website as directed by the Contracting Officer.
Official receipt of the transmittal that also requires a hard copy submission only begins when the Government receives the hard copy and not the electronic submission.
1.6.4 Number of Samples SD-04 Samples
ALL SD- 04 SUBMI TTALS REQUI RE A HARD COPY SUBMI SSI ON I N THE QUANTI TI ES
DI SCUSSED BELOW:
a. Submit two (2) samples, or two (2) sets of samples showing range of variation, of each required item. One approved sample or set of
SECTION 01 33 00 Page 12 samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one (1) sample panel. Include components listed in technical section or as directed.
c. Submit one (1) sample installation.
d. Submit one (1) sample of non-solid materials, for example paint.
e. Submit to address shown in paragraph "Hard Copy Submittals" above.
1.6.5 Number of Copies of SD-10 Operation and Maintenance Data
SD- 10 SUBMI TTALS WI TH AN HC DESI GNATED REQUI RE A HARD COPY SUBMI SSI ON I N
THE QUANTI TI ES DI SCUSSED BELOW:
Submit in compliance with SECTION 01 78 00.00 28 CLOSEOUT SUBMITTALS.
Submit one (1) copy each to the following addresses with remainder sent to the District office address. See paragraph "Hard Copy Submittals":
Operations Project Manager Lower Granite Project Office 885 Almota Ferry Road Pomeroy, WA 99347-9758
1.7 INFORMATION ONLY SUBMITTALS
Approval of the KO is not required on information only submittals. The following list applies to all for information only submittals:
a. The Contractor is not relieved from the obligation to furnish material conforming to the plans and specifications.
b. The KO reserves the right to require the Contractor to resubmit any item found not to comply with the contract, and is not prevented from requiring removal and replacement of nonconforming material incorporated in the work.
c. Does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 SUBMITTAL REGISTER
The Submittal Register will be loaded into RMS by the Government. A copy of the Submittal Register is attached to the end of this SECTION with the following fields filled in:
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g.
SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section
SECTION 01 33 00 Page 13 where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Column (f): Indicate approving authority for each submittal.
An excel copy of t he submi t t al r egi st er wi l l be pr ovi ded once t he t ask or der i s awar ded.
1.8.1 Use Of Submittal Register
Submit submittal register with QC plan and project schedule. Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.8.2 Contractor Use of Submittal Register
Update the following fields with each submittal throughout contract:
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.8.3 Approving Authority Use of Submittal Register
Update the following fields in the Government-furnished submittal register program:
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.8.4 Contractor Action Code and Action Code
Entries for columns (j) and (o), are to be used as follows (others may be prescribed by Transmittal Form):
SECTION 01 33 00 Page 14
NR - Not Received
AN - Approved as noted
A - Approved
RR - Disapproved, Revise, and Resubmit
1.8.5 Copies Delivered to the Government
Deliver a PDF copy of the submittal register, updated by Contractor, to Government with each invoice request.
1.9 SCHEDULING
Schedule, and submit concurrently, submittals covering component items forming a system or items that are interrelated. Submit all related certifications along with the pertinent drawings. No delay, damages, or time extensions will be allowed for time lost due to late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed in the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the KO does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register, and update monthly, with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
e. Allow the Government Thi r t y [ ( 30) ] calendar days to review submittals and for each resubmittal. The 30-day period shall commence at date of receipt of transmittals from the Contractor by the Government and the period shall end at date of signature of Approving Authority on the ENG Form 4025.
1.10 GOVERNMENT APPROVING AUTHORITY
When the approving authority is the Government, the KO will:
a. Note date on which submittal was received from QC system Manager.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
SECTION 01 33 00 Page 15
c. Identify returned submittals with one of the actions defined in paragraph "Review Notations" along with markings appropriate for action indicated.
The Government will provide the appropriate review notation for submittals, upon completion of review. The official response will only be through RMS.
1.10.1 Review Notations
KO review will be completed within Thi r t y ( 30) calendar days after date of receipt of submittal and resubmittals. Submittals will be returned to the Contractor with the following notations:
a. Submittals marked with an action code of "A" are "approved" or "accepted" and authorize the Contractor to proceed with the work covered.
b. Submittals marked with an action code of "B" are "accepted as noted on drawing", "accepted except as noted on drawing", and authorize the Contractor to proceed with the work covered once they make the changes to the submittal provided they take no exception to the corrections.
c. Submittals marked with an action code of "C" are "accepted as noted, resubmission required", and authorize the Contractor to proceed with the work covered provided they take no exception to the corrections. The Contractor shall resubmit with appropriate changes to address the Government notations.
d. Submittals marked with an action code of "E" are "disapproved", "not accepted", and indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete.
Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved or accepted.
e. Submittals marked with an action code of "F" are Submittals marked "receipt acknowledge" and will indicate submittal has been received but not necessarily reviewed by the Government. Comments to these submittals may or may not be provided; however the Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.
f. FIO submittals marked with an action code of "FX" are Submittals marked as "does not comply as noted with contract requirements" and indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes for Government approval or acceptance. No work shall proceed for this item until resubmittal is received.
1.11 DISAPPROVED OR REJECTED SUBMITTALS
Make corrections required by the KO. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.
SECTION 01 33 00 Page 16
If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12 APPROVED/ACCEPTED SUBMITTALS
The KO's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist. The Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work .
After submittals have been approved or accepted by the KO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not to be construed to change or modify any contract requirements. Before submitting samples, assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved. Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at their expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at their expense, if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service. Samples of various materials or equipment delivered on-site or in place may be taken by the KO for testing. Samples failing to meet contract requirements will automatically void previous approvals. Replace such materials or equipment to meet contract requirements. Approval of the Contractor's samples by the KO does not relieve the Contractor of their responsibilities under the contract.
1.14 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
1.15 STAMPS
Stamps used by the CQC system manager on the submittal data to certify that the submittal meets contract requirements is to be similar to the following:
SECTION 01 33 00 Page 17
| CONTRACT NUMBER |
| CONTRACTOR |
| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal | | data and/or attach sheets(s) |
| SIGNATURE: _____________________________________________|
| TITLE: CQC SYSTEM MANAGER |
| DATE: _______________ |
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
SECTION 01 33 00 Page 18
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 1 PAGES
W912EF22Q0120
Lower Granite Floating Guide Wall Cable (Supply)
01 78 00.00 28 SD-11 Closeout Submittals
3.1 G CFinal Shop Drawings
05 50 13 SD-01 Preconstruction Submittals
1.3 I MEQualification Of Welders
2.2.2 I MECertification Of Welding Inspector
SD-02 Shop Drawings
2.3 G MEPlates, Angles And Weldements
SD-03 Product Data
2.4 G MECable Assemblies
2.5 I MEHDPE Pipe
SD-06 Test Reports
3.3 I MEWeld Inspection
SD-07 Certificates
3.6 G MEMeasurement Certificate
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 ORDERING INFORMATION
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 42 00 Page 1
SECTION 01 42 00
SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
One East Wacker Drive, Suite 700 Chicago, IL 60601-1802 Ph: 312-670-2400 Fax: 312-670-5403 Bookstore: 800-644-2400 E-mail: aisc@ware-pak.com Internet: http://www.aisc.org
AMERICAN WELDING SOCIETY (AWS)
13301 NW 47 Ave Miami, FL 33054 Ph: 888-WELDING, 305-824-1177, 305-826-6192 Fax: 305-826-6195 E-mail: customer.service@awspubs.com Internet: http://www.aws.org
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 877-909-2786 Internet: http://www.astm.org
SECTION 01 42 00 Page 2
U.S. ARMY CORPS OF ENGINEERS (USACE)
CRD-C DOCUMENTS available on Internet:
http://www.wbdg.org/ccb/browse_cat.php?c=68 Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
PART 2 PRODUCTS
Not used
PART 3 EXECUTION
Not used
SECTION 01 42 00 Page 3
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 78 00.00 28
CLOSEOUT SUBMITTALS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 DEFINITIONS
1.2.1 Contract Drawings
1.2.2 Shop Drawings
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 FINAL SHOP DRAWINGS
SECTION 01 78 00.00 28 Page 1
SECTION 01 78 00.00 28
CLOSEOUT SUBMITTALS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. A designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-11 Closeout Submittals
Final Shop Drawings; G C
1.2 DEFINITIONS
1.2.1 Contract Drawings
Contract drawings are the set of Design Drawings furnished by the Government for this contract. Contract Drawings form a part of the legal contract between the Contractor and Government, and do NOT include FIO's or Resource Drawings.
1.2.2 Shop Drawings
a. Shop drawings are a drawing or set of drawings produced by the contractor, supplier, manufacturer, subcontractor, or fabricator for the following purposes:
1. Manufacturer's or Contractor's drawn version of information shown in the construction documents.
2. Drawn to explain the fabrication and/or installation of the items, in the construction documents, to the Manufacturer's production crew or Contractor's installation crews.
b. See SECTION 01 33 00 SUBMITTAL PROCEDURES, paragraph "Format for SD-02 Shop Drawings", for Shop Drawing requirements.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 FINAL SHOP DRAWINGS
a. Upon completion of the work under this contract, submit for review and approval by the Contracting Officer, a copy, in ADOBE .pdf, of the final SHOP DRAWINGS. All drawings submitted to the Contracting Officer shall be in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES, paragraph "Format for SD-02 Shop Drawings". The drawings shall show all changes and revisions, including any field changes, SECTION 01 78 00.00 28 Page 2 made up to the time that the work is completed and accepted.
b. Submit Final Shop Drawings, meeting requirements of SECTION 01 33 00 SUBMITTAL PROCEDURES, paragraph "CAD File Requirements".
c. The shop drawings are not required to comply with A/E/C CAD and Graphic Standards.
d. Furnish a complete set of Shop Drawings in Bentley DGN format for all Shop drawings produced by the Contractor in performance of this contract. Submittal of concrete placement drawings, concrete reinforcement drawings, and concrete formwork drawings are not required.
e. Furnish an index drawing for all Shop drawing submittal sets.
Index shall include the following for each Shop drawing:
1. Sheet Number.
2. File Number.
3. Drawing Title.
4. CAD File Name.
f. Furnish an electronic spread sheet of the index to include all information specified in SECTION 01 33 00 SUBMITTAL PROCEDURES paragraph "Format for SD-02 Shop Drawings". Spread sheet shall be compatible with Microsoft Excel.
SECTION 01 78 00.00 28 Page 3
DIVISION 05 - METALS
SECTION 05 50 13
CABLES ASSEMBLIES AND CONNECTING HARDWARE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALIFICATION OF WELDERS
1.4 DELIVERY, STORAGE, AND PROTECTION
1.5 MISCELLANEOUS REQUIREMENTS
1.5.1 Fabrication Drawings
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Structural Carbon Steel
2.1.2 Structural Tubing
2.2 FABRICATION FINISHES
2.2.1 Dimensional Tolerances
2.2.2 Certification Of Welding Inspector
2.2.3 Welding Procedure Specifications (WPS)
2.2.4 Structural Steel Fabrication
2.2.5 Galvanizing
2.2.6 Repair of Zinc-Coated Surfaces
2.3 CONNECTING HARDWARE
2.4 CABLE ASSEMBLIES
2.5 HDPE PIPE
PART 3 EXECUTION
3.1 WORKMANSHIP
3.2 WELDING
3.3 WELD INSPECTION
3.4 PREPARATION
3.4.1 Material Coatings and Surfaces
3.4.2 Environmental Conditions
3.5 CABLE ASSEMBLIES
3.6 SHIPPING AND PACKAGING
SECTION 05 50 13 Page 1
SECTION 05 50 13
CABLES ASSEMBLIES AND CONNECTING HARDWARE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 303 (2016) Code of Standard Practice for Steel Buildings and Bridges
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A500/A500M (2021) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
ASTM A586 (2018) Standard Specification for Metallic-Coated Parallel and Helical Steel Wire Structural Strand
ASTM A653/A653M (2020) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM A780/A780M (2020) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A924/A924M (2020) Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process
SECTION 05 50 13 Page 2
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only.
Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURE
SD-01 Preconstruction Submittals
Qualification Of Welders; I, ME
Certification Of Welding Inspector; I, ME
SD-02 Shop Drawings
Plates, Angles And Weldements; G, ME
SD-03 Product Data
Cable Assemblies; G, ME
HDPE Pipe; I, ME
SD-06 Test Reports
Weld Inspection; I ME
SD-07 Certificates
Measurement Certificate; G, ME
1.3 QUALIFICATION OF WELDERS
Prior to commencing fabrication, submit Qualifications of Welders and Welding Operators for approval. Each welder, welding operator, and tacker assigned to work on this contract shall be qualified in accordance with the applicable requirements of AWS D1.1/D1.1M . Welders and welding operators shall pass the qualification tests prescribed by AWS D1.1/D1.1M within 12 months prior to performing work on this contract and as specified in this SECTION. Welders, welding operators, and tackers who make acceptable procedure qualification test welds will be considered qualified for the welding procedure used
1.4 DELIVERY, STORAGE, AND PROTECTION
Protect from corrosion, deformation, and other types of damage. Store items in an enclosed area free from contact with soil and weather. Remove and replace damaged items with new items.
SECTION 05 50 13 Page 3
1.5 MISCELLANEOUS REQUIREMENTS
1.5.1 Fabrication Drawings
Submit fabrication drawings showing layout(s), connections to structural system, and anchoring details as specified in AISC 303 .
PART 2 PRODUCTS
2.1 MATERIALS
Provide exposed fastenings of compatible materials (avoid contact of dissimilar metals). Coordinate color and finish with the material to which fastenings are applied.
2.1.1 Structural Carbon Steel
Provide in accordance with ASTM A36/A36M.
2.1.2 Structural Tubing
Provide in accordance with ASTM A500/A500M .
2.2 FABRICATION FINISHES
2.2.1 Dimensional Tolerances
Dimensions shall be measured by a calibrated steel tape of approximately the same temperature as the material being measured. The overall dimensions of an assembled structural unit shall be within the tolerances indicated on the contract drawings or as specified. An allowable variation of 1/32 inch is permissible in the overall length of component members with both ends milled, and component members without milled ends shall not deviate from the dimensions shown by not more than 1/16 inch for members 30 feet or less in length and by not more than 1/8 inch for members over 30 feet in length.
This is the start of the file's text. The full file is on GovTribe.