About this file

This document is a justification and approval for a brand name sole source procurement. The U.S. Army Corps of Engineers, Walla Walla District requires Schweitzer Engineering Laboratories protective relays, revenue meters, auxiliary controllers, computers, and networking equipment totaling $820,661 to upgrade the protection, control, and annunciation systems at the McNary Powerhouse. This equipment will replace end of life components and be compatible with the existing SEL equipment integrated throughout the powerhouse. Using another manufacturer's products would reduce system compatibility and increase costs, complexity, risk, and schedule delays. The requirement will be publicly noticed on beta.sam.gov with the brand name requirement. All responses able to meet the brand name requirement will be considered.

The district has previously procured this SEL equipment on small business set aside contracts and supply blanket purchase agreements awarded from 2017 to 2020 totaling over $87,000. This upcoming procurement will be competed with the brand name requirement and all compliant offers received will be evaluated for best value.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Control No. 20-0052

BRAND NAME DETERMINATION

FOR OTHER THAN FULL AND OPEN COMPETITION

Schweitzer Engineering Laboratories (SEL) EQUIPMENT

1. DESCRIPTION OF THE LOCATION: The U.S. Army Corps of Engineers, Walla Walla District

(CENWW-CT) 201 North 3rd, Walla Walla, WA 99362

2. DESCRIPTION OF ACTION: Approval is being requested to procure Schweitzer Engineering Laboratories (SEL) brand name products under a firm fixed price contract. McNary Powerhouse is requesting to procure SEL protective relays, watt hour meters, and network switches for generators, transformers, bus, and switchgear.

Action will be funded by Large Cap (Bonneville Power Administraction(BPA)-Power Marketing Aministration) funds. Schweitzer Engineering Laboratories (SEL) equipment estimated value $820,661.

3. DESCRIPTION OF SUPPLIES/SERVICES: The U.S. Army Corps of Engineers, Walla Walla District, McNary Powerhouse has a requirement for the purchase of SEL protective relays, revenue meters, auxiliary & automation controllers, computer and network equipment for the protection, control & annunciation systems upgrades. The SEL (P&C) equipment will be used for upgrading main unit generator and GSU transformer protection and control systems at McNary Powerhouse. The SEL equipment will replace the existing SEL equipment and be installed into new S boards under a separate construction contract. The S boards are being replaced, so new protective relaying equipment is required. The SEL real time automation controller (RTAC) and SEL Axion (auxiliary controller) will be used for collecting alarms for the new annunciation/SER system and are compatible with new human machine interfaces (HMI) and networking equipment for the Generic Data Acquisition System (GDACS). A separate annunciation panel is needed in the control room to provide hardwired door security switches to the control room for S boards and related equipment. Below is a list of all the required items:

Manufacturer Part Number Description Qty Total

SEL 0700G11ACA2X7685A630

SEL 700G1 Generator Relay with 5 inch Touchscreen 32

SEL 0735LX20944GFXDXXX16201XX

SEL 735 Revenue Meter with 5-inch touchscreen option if available 17

SEL 2242S1X0 SEL 2242 Chassis/Backplane 25 SEL 2241X0X323X05SXXXX Sel 2241 25 SEL 224311X0 SEL 2243 Power Coupler 48 SEL 22442424X0 SEL 2244-2 DI Module 97 SEL 22443131X0 SEL 2244-3 DO Module 25

SEL 22445151X0

SEL 2244-5 FHC DO Module (10 Form A Contacts) 17

SEL 22445152X0

SEL 2244-5 FHC DO Module (5 Form A, 5 Form B Contacts) 10

SEL 22452121XX0 SEL 2245-2 DC AI Module 25

SEL 07873EE1ACA2A7685A630

SEL 7873E with 5 inch touchscreen 17

SEL 3555#H6NK

SEL 3555 RTAC with HMI runtime License; 8GB, 256GB SSD, 3 expansion PCIe Serial, Cards 2 RJ45 Ethernet ports, DVI- D, DVI-I & Display port video ports 10

SEL 3355#BKHC

Rugged Computer; Windows Server; 4GB, 32GB SSD, Expansion PCIe Ethernet Card, 2 RJ45 Ethernet ports, DVI-D & DisplayPort video ports 3

SEL 252301313A0A0XX SEL-2523 Annunciator Panel 2 SEL 2488PRAA1181BX2XX SEL-2488 Satellite Clock 2 SEL 2488PRAX1181BX23X SEL-2488 Satellite Clock 1 SEL 3401#0201 Digital IRIG-B Clock for S-Boards 8 SEL 5045#0101 SEL TEAM Software 2

SEL 3620X3A0XXX0

SEL-3620 Ethernet security Gateway and Password Manager 3

4. AUTHORITY CITED:

10 U.S.C.2304(c)(1) as implemented by FAR 6.302-1 (c) Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements. Per FAR 13.501(a) this Justification is for the use of a brand name description under FAR 6.302-1(c).

FAR 11.105(a)(1), Items Particular to One Manufacturer. The particular brand name, product, or feature is essential to the Government 's requirements, and market research indicates other companies' similar products, are lacking particular features, and do not meet, or cannot be modified to meet, the agency' s needs.

5. REASON FOR AUTHORITY CITED:

a. Background: The equipment requested will be used for replacing End Of Life components (MTL IO) at McNary Dam for the Powerhouse Control System Upgrade as part of the McNary Digital Governors, Exciters, and Powerhouse Controls Upgrade project for Walla Walla District. McNary Project presently has a main unit annunciation, Sequence of Event Recording (SER), and protection system under development by the Hydroelectric Design Center (HDC) in support of the Construction Contract for McNary Power House Control upgrade. The parts listed above are required to fulfill control, relaying protection, communications, and indication of the system. All the components needed must be replaced in kind, as other manufacturers cannot provide compatible components. If another manufacuter’s products were used to replace these End of Life components, it would create Operations and Maintenance (O&M) compatability issues and increase cost and risk to other sytems within the Dam.

Benefits for the use of the existing brand of SEL will result in simplified training requirements for Government personnel, interoperability requirements within the existing systems, reduction of spare parts inventory required for system maintenance, and will allow parts to be exchanged between the new and existing systems.

b. Justification: SEL is an industry leader in power system protection, technology, service and value. Due to the reputation, reliability and outstanding service record of SEL, McNary Dam has integrated SEL protective relays throughout its powerhouse. Currently at McNary all 14 generators and 7 main transformers are protected by SEL es protective relay devices and metered by SEL metering devices.

Other locations in the plant use various SEL feeder protective relays.

Substitution of another’s component for SEL components would:

i. Increase the initial and recurring costs of spare parts inventory

ii. Increase labor time, travel, and expense to train Government personnel who will support the system

iii. Decrease compatibility with existing systems and thus decrease the amount of information that can be conveyed throughout the system

iv. Increase the complexity of the facility and thus decrease maintainability and reliability

v. Increase the chance of discovering incompatibilities which require re-procurement and schedule delays beyond funding availability

c. Impact: Operating a powerhouse under emergency conditions is largely instinctive due to a powerhouse operator’s continuous training and repetition. The success of returning a plant to normal operating conditions after an emergency is largely based on the simplicity of the system. With the Main Unit and Transformer protective system currently being SEL equipment, installing non-SEL equipment would add complexity, significant costs and delay in schedule. Added complexity correlates directly with increased risk.

d. Alternatives:

The Government could not purchase the product and leave the end of life components in place; this alternative is not feasible because we need to ensure the availability of a working and usable sequence of SEL products at the projects where GDACS is installed.

The Government could purchase a different product; this alternative is not in the best interest Government..

The SEL protective relays will be used for main unit generator protection and transformer protection. All of the protective relays in the powerhouse are currently SEL equipment, which has allowed maintenance practices have become more efficient due to redundancy. Reliability of the system as a whole has increased due to more effective maintenance practices. The proposed SEL devices have similar maintenance requirements as existing SEL protective relays and would require even less time to install and maintain.

6. EFFORTS TO OBTAIN COMPETITION: competition between firms that sell the required brand name SEL is expected. The requirement will be advertised on Beta.Sam with the brand name only requirement in that solicitation. The McNary Powerhouse configuration requires use of these specified items. Due to the need for compatibility and interoperability of existing equipment we are requesting a brand name determination approval.. All sources responding that can provide name brand items will be considered.

7. ACTIONS TO INCREASE COMPETITION: This action will be competed. The supply contract will be posted to Beta.Sam in a ccordance with the FAR. All sources responding that can provide name brand items will be considered.

8. MARKET RESEARCH: Research shows SEL brand name products is the only identified product compatible with the existing system for this installation phase. Other sources have been vetted to meet current needs, but there is no alternative available without complete system replacement with an equivalent product.

9. INTERESTED SOURCES: This requirement will be synopsized in accordance with FAR 5.201 and any offers received will be considered. The justification will be made publically available in accordance with

FAR 6.305.

10. OTHER FACTORS:

a. Procurement History: The Government has previously purchased this product as a total small business set aside and as a BPA supply contract. Awards were based off of Best Value based on Price and were Brand Name requirements. See below for list of prior contract numbers awarded for SEL Relays

W912EF18F0095 LLA Relay; B&P Consort, Inc; $6,350.00; awarded 21 March 2018; GPC Purchase;

Brand Name W912EF19F0106 HLD Protection Relay; B&P Consort, Ince; $12,500.00; awarded 20 June 2019; GPC Purchase; Brand Name W912EF17F0059 LLA Relays; Aponte Power Services LLC; $23,280.00; awarded 27 July 2017; Brand Name W912EF20F0044 LGO Sel Relay; B&P Consort, Inc; $45,105.36; awarded 9 April 2020; Brand Name

b. Other Facts: None

11. TECHNICAL CERTIFICATION: I certify that the supporting data under my cognizance of which are included in this Justification and Approval are accurate and complete to the best of my knowledge and belief.

Prepared by: Kortney Siracusa Signature: ____________________________ Title: Electrical Engineer

12. REQUIREMENTS CERTIFICATION: I certify that the supporting data under my cognizance of which are included in this Justification and Approval are accurate and complete to the best of my knowledge and belief.

Prepared by: Jason Buchanan Signature: ____________________________ Title: Project Manager

13. Fair and Reasonable Cost Determination:

I hereby determine that the anticipated cost to the Government for this contract action will be fair and reasonable based on price analysis and independent Government cost estimate. Certified cost or pricing data was not required because the prohibition at FAR 15.403-1(b)(3).

Approved by: Sara Edwards Signature: ____________________________ Title: Contracting Officer

14. CONTRACTING OFFICER CERTIFICATION:

In accordance with the authority of 10 U.S.C. 2304(c)(1), as implemented by FAR 13.106-1(b)(1) and based upon the foregoing, I hereby determine that a brand name procurement is authorized and is in the best interest of the Government. I certify that this Determination is accurate and complete to the best of my knowledge and belief.

Approved by: Sara Edwards Signature: ____________________________ Title: Contracting Officer

SIRACUSA.KORTNEY.M

ICHAEL.1514272030

Digitally signed by

SIRACUSA.KORTNEY.MICHAEL.1514272030

Date: 2020.07.20 14:28:47 -07'00'

Digitally signed by

BUCHANAN.JASON.W.1144982700

Date: 2020.07.20 16:51:24 -07'00'

EDWARDS.SARA.JAN

E.1245134009

Digitally signed by

EDWARDS.SARA.JANE.1245134009

Date: 2020.07.21 06:24:25 -07'00'

EDWARDS.SARA.J

ANE.1245134009

Digitally signed by

EDWARDS.SARA.JANE.12451340

Date: 2020.07.21 06:24:52 -07'00'

File details come from the government source that posted it. Updated .