STATEMENT OF WORK
Water Treatment Services for Cooling Towers/Closed Loops
A.1.1 INTRODUCTION
The Federal Bureau of Prisons, Federal Correctional Complex, Coleman, Florida, intends to make a best value, single award for the provision of Cooling Tower/Closed Loop water chemistry control. This contract will be for the next 5 fiscal years running from October 1, 2018 thru September 30, 2023. There will be a base year, fiscal year 2019, and 4 option years, FY2020, FY2021, FY2022, and FY2023.
A.1.2 PLACE OF PERFORMANCE
Cooling tower systems and closed chill water loop treatment services will be performed at the Federal Correctional Complex (FCC), 846 NE 54th Terrace, Coleman, FL 33521.
A.1.3 COOLING TOWER AND CLOSED CHILL WATER LOOP DATA
There are a total of eleven (11) cooling tower systems and five (5) closed chill water loops.
These systems are spread out between five different remote utility buildings (RUB’s).
A.1.4 GENERAL REQUIREMENT
The contractor shall provide for FCC Coleman RUB’s all of the following services in association with, and support of, our water treatment needs concerning all eleven (11) cooling tower systems and five (5) closed chill water loops.
A.1.5 WATER TREATMENT SPECIFIC REQUIREMENT
1. A detailed treatment proposal outlining:
a. effectiveness criteria
b. control limits
c. list of all products to be used in the program
d. estimated chemical usage based on target control levels for cycles and product concentration
e. all other requirements involved in the service/treatment
2. The treatment program will address the interconnected aspects of preventative maintenance of corrosion control, scale and suspended solids control and bio fouling control, prevent buildup of material on heat exchanger surfaces to maintain fouling factor less then heat exchangers’ design limits.
3. Documentation shall be provided for:
a. the indication of compatibility of all dual product combination treatment
b. product bulletins
c. SDS’ on all proposed products
4. Pricing will be based on all factors and shall include:
a. all chemicals and equipment
b. tech services and laboratory services
c. primary stainless steel tanks for each chemical with a level indicator Feed tank measuring no bigger than 24”Wx24”Lx26”H Biocide tanks measuring no bigger than 24”Wx24”Lx13”H each
d. stainless steel secondary containments with a minimum of 110% spill volume capacity, or primary stainless steel tanks with a double wall specifically for leaks and spills
e. primary tanks must have latching/locking device to prevent unauthorized personnel from gaining access to chemicals
f. all testing equipment/kits for operators at FCC Coleman, testing done daily
g. delivery to point of use / FOB destination
5. Chill water loops must be treated to meet the following specifications: mild steel corrosion rates below .2 mils per year, copper corrosion rates below .1 mil per year, bacteria = sterile
6. Cooling tower must be controlled to minimize corrosion and fouling according to the following criteria: mild steel corrosion rates below 2.0 mil per year; copper corrosion rates below .1 mil per year; bacterial levels below 10-4 CFU/ml as per easicult method; maintain chiller manufacturers design efficiency and approach temperature.
7. Cooling tower water limits shall be: Azole 1-2ppm min; Alkalinity 1100ppm max; 6 cycles max; magnesium based cycle balance; phosphonate range of 2-6ppm.
8. Inhibitor must be the following: all organic, environmentally safe; multi metal corrosion inhibiting; non chromate, zinc, or molybdenum containing; it must be a phosphonate, polymeric dispersant and contain other corrosion inhibitors such as tolytriazole.
9. Provide alternating biocide program that will control micro organisms such as bacteria, algae, and fungi to prevent the formation of biofilms. Primary biocide shall be oxidizing and secondary biocide shall be non-oxidizing. Primary and secondary biocides shall be fed into the system using a metered/timed pump system.
10. Provide CTI recommended control for bacteria and legionella in cooling towers.
11. No acid is to be used in scale inhibiting.
12. Provide chemical delivery to the point of use, being FCC Coleman RUB’s, by:
a. utilizing the contractors own fleet vehicle
b. delivery driver must be haz mat qualified
c. delivery records shall be provided upon the products arrival at FCC Coleman
d. chemical transfer will be done by the contractor to prevent FCC Coleman personnel from handling the chemicals
13. Contractor will provide the service pertaining to the handling, transferring, disposal of and inventorying all chemicals.
14. Contractor must have laboratories capable of performing basic water analysis per standard methods.
15. Contractor shall make monthly service visits to each RUB to:
a. perform basic water testing analysis
b. provide a service report for each RUB that details the test results, control ranges, water characteristics, treatment residuals, and suggested corrective actions
c. provide ongoing training to personnel.
d. ensure controls are working properly
e. inventory on chemicals
16. Provide annual inspections of water side of chiller heat exchangers on occasions when equipment is opened for cleaning.
17. Contractor will maintain full responsibility of guarding against damage or loss to FCC Coleman property. In the event of property loss or damage by the Contractor, the Contractor agrees to replace or repair such loss or damage.
18. Contractor agrees to repair any damaged or scaled components/equipment that occurred during the contract period and is found to be at their fault. These repairs, cleaning, descaling, etc., shall be at the Contractors expense and will be done at the earliest opportunity in order to prevent further damage to the system.
A.1.6 RESIDENCY REQUIREMENTS
The residency requirement applies to both individuals and employees of companies providing services to the Federal Bureau of Prisons. For three of the five years immediately prior to submission of your offer/bid/quote, individuals or contractor employees providing services in any Federal Bureau of Prisons facility must have:
1. resided in the United States (U.S.);
2. worked for the U.S. overseas in a Federal or military capacity; or
3. been a dependent of a Federal or military employee serving overseas
A.1.7 EVALUATION METHODOLOGY
The Government intends to evaluate quotes considering proposed service details, price and past performance. Award will be made to the contractor that represents the best value to the government for this requirement. All quotes received will be considered.
Section 3 - Contract Clauses
52.212-4 Contract Terms and Conditions--Commercial Items (Jan 2017)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this con-tract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Gov-ernment may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exer-cise its post-acceptance rights--
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agree-ment on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reason-able control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include--
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this con-tract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer--System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer--Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, includ-ing costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.--
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall--
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the--
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109 , which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if--
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the de-mand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on--
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisi-tion Regulation in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon ac-ceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particu-lar purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regu-lations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limita-tions on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following or-der:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) System for Award Management (SAM).
(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Govern-ment's reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(2)(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the SAM database; (B) comply with the requirements of subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Of-ficer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM in-formation that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect inform-ation within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see subpart 32.8, Assignment of Claims). Assignees shall be separately re-gistered in the SAM database. Information provided to the Contractor's SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Sus-pension of payment" paragraph of the EFT clause of this contract.
(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via SAM accessed through https://www.acquisition.gov.
(u) Unauthorized Obligations
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requir-ing the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it ap-pearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of clause)
A.1 ADDENDUM TO FAR 52.212-4, Contract Terms and Conditions--Commercial Items (Jan 2017)
The terms and conditions for the following clauses are hereby incorporated into this solicitation and resulting contract as an addendum to FAR clause 52.212-4.
Clauses By Reference
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text.
Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov
Clause Title Fill-ins (if applicable)
52.246-11 Higher-Level Contract Quality Requirement (Dec 2014)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (Jan 2017)
52.204-2 Security Requirements (Aug 1996)
52.204-12 Unique Entity Identifier Maintenance (Oct 2016)
52.204-13 System for Award Management Maintenance (Oct 2016)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services
Developed or Provided by Kaspersky Lab and Other Covered Entities
(Jul 2018)
52.208-9 Contractor Use of Mandatory Sources of Supply or Services (May
2014)
52.216-11 Cost Contract - No Fee (Apr 1984)
52.222-1 Notice to the Government of Labor Disputes (Feb 1997)
52.222-21 Prohibition of Segregated Facilities (Apr 2015)
52.222-26 Equal Opportunity (Sept 2016)
52.222-50 Combating Trafficking in Persons (Mar 2015)
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
Clause Title Fill-ins (if applicable)
(Aug 2011)
52.224-3 Privacy Training (Jan 2017)
52.224-3 Alt I Privacy Training (Jan 2017) - Alternate I (Jan 2017)
52.225-13 Restrictions on Certain Foreign Purchases (June 2008)
52.228-4 Workers' Compensation and War-Hazard Insurance Overseas (Apr
1984)
52.228-7 Insurance - Liability to Third Persons (Mar 1996)
52.229-8 Taxes - Foreign Cost-Reimbursement Contracts (Mar 1990)
52.232-17 Interest (May 2014)
52.232-20 Limitation Of Cost (Apr 1984)
52.232-25 Prompt Payment (Jan 2017)
52.232-30 Installment Payments for Commercial Items (Jan 2017)
52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors
(Dec 2013)
52.233-1 Disputes (May 2014)
52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)
52.233-3 Protest after Award (Aug 1996)
52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)
52.242-1 Notice of Intent to Disallow Costs (Apr 1984)
52.242-4 Certification of Final Indirect Costs (Jan 1997)
52.242-13 Bankruptcy (July 1995)
52.244-6 Subcontracts for Commercial Items (Jul 2018)
52.246-23 Limitation of Liability (Feb 1997)
52.247-68 Report of Shipment (RESHIP) (Feb 2006)
52.249-6 Termination (Cost Reimbursement) (May 2004)
52.250-5 SAFETY Act - Equitable Adjustment (Feb 2009)
52.251-2 Interagency Fleet Management System Vehicles And Related
Services (Jan 1991)
52.253-1 Computer Generated Forms (Jan 1991)
Clauses By Full Text
2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (June 1996)
(a) "Unsafe condition" as used in this clause means the actual or potential exposure of contractor or Government employees to a haz-ardous material as defined in Federal Standard No. 313, and any revisions thereto during the term of this contract, or any other materi-al or working condition designated by the Contracting Officer's Technical Representative (COTR) as potentially hazardous and requir-ing safety controls.
(b) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require contractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.
(c) Prior to commencement of work, contractors are required to inspect for and report to the contracting officer or designee the pres-ence of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.
(d) If during the performance of the work under this contract, the contractor or any of its employees, or subcontractor employees, dis-covers the existence of an unsafe condition, the contractor shall immediately notify the contracting officer, or designee, (with written notice provided not later than three (3) working days thereafter) of the existence of an unsafe condition. Such notice shall include the contractor's recommendations for the protection and the safety of Government, contractor and subcontractor personnel and property that may be exposed to the unsafe condition.
(e) When the Government receives notice of an unsafe condition from the contractor, the parties will agree on a course of action to mitigate the effects of that condition and, if necessary, the contract will be amended. Failure to agree on a course of action will consti-tute a dispute under the Disputes clause of this contract.
(f) Nothing contained in this clause shall relieve the contractor or subcontractors from complying with applicable Federal, State, and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with hazardous material including but not limited to the use, disturbance, or disposal of such material.
(End of Clause)
52.252-2 Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon re-quest, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this / these address(es):
[Insert one or more Internet addresses]
(End of clause)
52.222-50 Alt I Combating Trafficking in Persons (Mar 2015) - Alternate I (Mar 2015)
(a) Definitions. As used in this clause--
Agent means any individual, including a director, an officer, an employee, or an independent contractor, authorized to act on behalf of the organization.
"Coercion" means--
(1) Threats of serious harm to or physical restraint against any person;
(2) Any scheme, plan, or pattern intended to cause a person to believe that failure to perform an act would result in serious harm to or physical restraint against any person; or
(3) The abuse or threatened abuse of the legal process.
"Commercial sex act" means any sex act on account of which anything of value is given to or received by any person.
Commercially available off-the-shelf (COTS) item means--
(1) Any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Debt bondage" means the status or condition of a debtor arising from a pledge by the debtor of his or her personal services or of those of a person under his or her control as a security for debt, if the value of those services as reasonably assessed is not applied toward the liquidation of the debt or the length and nature of those services are not respectively limited and defined.
"Employee" means an employee of the Contractor directly engaged in the performance of work under the contract who has other than a minimal impact or involvement in contract performance.
"Forced Labor" means knowingly providing or obtaining the labor or services of a person--
(1) By threats of serious harm to, or physical restraint against, that person or another person;
(2) By means of any scheme, plan, or pattern intended to cause the person to believe that, if the person did not perform such labor or services, that person or another person would suffer serious harm or physical restraint; or
(3) By means of the abuse or threatened abuse of law or the legal process.
"Involuntary servitude" includes a condition of servitude induced by means of--
(1) Any scheme, plan, or pattern intended to cause a person to believe that, if the person did not enter into or continue in such condi-tions, that person or another person would suffer serious harm or physical restraint; or
(2) The abuse or threatened abuse of the legal process.
"Severe forms of trafficking in persons" means--
(1) Sex trafficking in which a commercial sex act is induced by force, fraud, or coercion, or in which the person induced to perform such act has not attained 18 years of age; or
(2) The recruitment, harboring, transportation, provision, or obtaining of a person for labor or services, through the use of force, fraud, or coercion for the purpose of subjection to involuntary servitude, peonage, debt bondage, or slavery.
"Sex trafficking" means the recruitment, harboring, transportation, provision, or obtaining of a person for the purpose of a commercial sex act.
Subcontract means any contract entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract.
Subcontractor means any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime contractor or anoth-er subcontractor.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Policy. The United States Government has adopted a policy prohibiting trafficking in persons including the trafficking-related activities of this clause. Contractors, contractor employees, and their agents shall not--
(1) Engage in severe forms of trafficking in persons during the period of performance of the contract;
(2) Procure commercial sex acts during the period of performance of the contract;
(3) Use forced labor in the performance of the contract;
(4) Destroy, conceal, confiscate, or otherwise deny access by an employee to the employee’s identity or immigration documents, such as passports or drivers’ licenses, regardless of issuing authority;
(5)(i) Use misleading or fraudulent practices during the recruitment of employees or offering of employment, such as failing to dis-close, in a format and language accessible to the worker, basic information or making material misrepresentations during the recruit-ment of employees regarding the key terms and conditions of employment, including wages and fringe benefits, the location of work, the living conditions, housing and associated costs (if employer or agent provided or arranged), any significant cost to be charged to the employee, and, if applicable, the hazardous nature of the work;
(ii) Use recruiters that do not comply with local labor laws of the country in which the recruiting takes place;
(6) Charge employees recruitment fees;
(7)(i) Fail to provide return transportation or pay for the cost of return transportation upon the end of employment--
(A) For an employee who is not a national of the country in which the work is taking place and who was brought into that country for the purpose of working on a U.S. Government contract or subcontract (for portions of contracts performed outside the United States);
or
(B) For an employee who is not a United States national and who was brought into the United States for the purpose of working on a U.S. Government contract or subcontract, if the payment of such costs is required under existing temporary worker programs or pursu-ant to a written agreement with the employee (for portions of contracts performed inside the United States); except that--
(ii) The requirements of paragraphs (b)(7)(i) of this clause shall not apply to an employee who is--
(A) Legally permitted to remain in the country of employment and who chooses to do so; or
(B) Exempted by an authorized official of the contracting agency from the requirement to provide return transportation or pay for the cost of return transportation;
(iii) The requirements of paragraph (b)(7)(i) of this clause are modified for a victim of trafficking in persons who is seeking victim services or legal redress in the country of employment, or for a witness in an enforcement action related to trafficking in persons. The contractor shall provide the return transportation or pay the cost of return transportation in a way that does not obstruct the victim ser-vices, legal redress, or witness activity. For example, the contractor shall not only offer return transportation to a witness at a time when the witness is still needed to testify. This paragraph does not apply when the exemptions at paragraph (b)(7)(ii) of this clause ap-ply.
(8) Provide or arrange housing that fails to meet the host country housing and safety standards; or
(9) If required by law or contract, fail to provide an employment contract, recruitment agreement, or other required work document in writing. Such written work document shall be in a language the employee understands. If the employee must relocate to perform the work, the work document shall be provided to the employee at least five days prior to the employee relocating. The employee’s work document shall include, but is not limited to, details about work description, wages, prohibition on charging recruitment fees, work location(s), living accommodations and associated costs, time off, roundtrip transportation arrangements, grievance process, and the content of applicable laws and regulations that prohibit trafficking in persons.
(c) Contractor requirements. The Contractor shall--
(1) Notify its employees and agents of--
(i)(A) The United States Government’s policy prohibiting trafficking in persons described in paragraph (b) of this clause; and
(B) The following directive(s) or notice(s) applicable to employees performing work at the contract place(s) of performance as indic-ated below:
Document Title Document may be obtained from: Applies to performance in/at:
[Contracting Officer shall insert title of directive/notice; indicate the document is attached or provide source (such as website link) for obtaining document; and, indicate the contract performance location outside the United States to which the document applies.]
(ii) The actions that will be taken against employees or agents for violations of this policy. Such actions for employees may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment; and
(2) Take appropriate action, up to and including termination, against employees, agents, or subcontractors that violate the policy in paragraph (b) of this clause.
(d) Notification. (1) The Contractor shall inform the Contracting Officer and the agency Inspector General immediately of--
(i) Any credible information it receives from any source (including host country law enforcement) that alleges a Contractor employee, subcontractor, subcontractor employee, or their agent has engaged in conduct that violates the policy in paragraph (b) of this clause (see also 18 U.S.C. 1351, Fraud in Foreign Labor Contracting, and 52.203-13(b)(3)(i)(A), if that clause is included in the solicitation or contract, which requires disclosure to the agency Office of the Inspector General when the Contractor has credible evidence of fraud); and
(ii) Any actions taken against a Contractor employee, subcontractor, subcontractor employee, or their agent pursuant to this clause.
(2) If the allegation may be associated with more than one contract, the Contractor shall inform the contracting officer for the contract with the highest dollar value.
(e) Remedies. In addition to other remedies available to the Government, the Contractor’s failure to comply with the requirements of paragraphs (c), (d), (g), (h), or (i) of this clause may result in--
(1) Requiring the Contractor to remove a Contractor employee or employees from the performance of the contract;
(2) Requiring the Contractor to terminate a subcontract;
(3) Suspension of contract payments until the Contractor has taken appropriate remedial action;
(4) Loss of award fee, consistent with the award fee plan, for the performance period in which the Government determined Contractor non-compliance;
(5) Declining to exercise available options under the contract;
(6) Termination of the contract for default or cause, in accordance with the termination clause of this contract; or
(7) Suspension or debarment.
(f) Mitigating and aggravating factors. When determining remedies, the Contracting Officer may consider the following:
(1) Mitigating factors. The Contractor had a Trafficking in Persons compliance plan or an awareness program at the time of the viola-tion, was in compliance with the plan, and has taken appropriate remedial actions for the violation, that may include reparation to vic-tims for such violations.
(2) Aggravating factors. The Contractor failed to abate an alleged violation or enforce the requirements of a compliance plan, when directed by the Contracting Officer to do so.
(g) Full cooperation. (1) The Contractor shall, at a minimum--
(i) Disclose to the agency Inspector General information sufficient to identify the nature and extent of an offense and the individuals responsible for the conduct;
(ii) Provide timely and complete responses to Government auditors’ and investigators’ requests for documents;
(iii) Cooperate fully in providing reasonable access to its facilities and staff (both inside and outside the U.S.) to allow contracting agencies and other responsible Federal agencies to conduct audits, investigations, or other actions to ascertain compliance with the Trafficking Victims Protection Act of 2000 (22 U.S.C. chapter 78), E.O. 13627, or any other applicable law or regulation establishing restrictions on trafficking in persons, the procurement of commercial sex acts, or the use of forced labor; and
(iv) Protect all employees suspected of being victims of or witnesses to prohibited activities, prior to returning to the country from which the employee was recruited, and shall not prevent or hinder the ability of these employees from cooperating fully with Govern-ment authorities.
(2) The requirement for full cooperation does not foreclose any Contractor rights arising in law, the FAR, or the terms of the contract.
It does not--
(i) Require the Contractor to waive its attorney-client privilege or the protections afforded by the attorney work product doctrine;
(ii) Require any officer, director, owner, employee, or agent of the Contractor, including a sole proprietor, to waive his or her attorney client privilege or Fifth Amendment rights; or
(iii) Restrict the Contractor from--
(A) Conducting an internal investigation; or
(B) Defending a proceeding or dispute arising under the contract or related to a potential or disclosed violation.
(h) Compliance plan. (1) This paragraph (h) applies to any portion of the contract that--
(i) Is for supplies, other than commercially available off-the-shelf items, acquired outside the United States, or services to be per-formed outside the United States; and
(ii) Has an estimated value that exceeds $500,000.
(2) The Contractor shall maintain a compliance plan during the performance of the contract that is appropriate—
(i) To the size and complexity of the contract; and
(ii) To the nature and scope of the activities to be performed for the Government, including the number of non-United States citizens expected to be employed and the risk that the contract or subcontract will involve services or supplies susceptible to trafficking in per-sons.
(3) Minimum requirements. The compliance plan must include, at a minimum, the following:
(i) An awareness program to inform contractor employees about the Government’s policy prohibiting trafficking- related activities de-scribed in paragraph (b) of this clause, the activities prohibited, and the actions that will be taken against the employee for violations.
Additional information about Trafficking in Persons and examples of awareness programs can be found at the Web site for the Depart-ment of State’s Office to Monitor and Combat Trafficking in Persons at http://www.state.gov/j/tip/.
(ii) A process for employees to report, without fear of retaliation, activity inconsistent with the policy prohibiting trafficking in per-sons, including a means to make available to all employees the hotline phone number of the Global Human Trafficking Hotline at 1–844–888–FREE and its email address at help@befree.org.
(iii) A recruitment and wage plan that only permits the use of recruitment companies with trained employees, prohibits charging re-cruitment fees to the employee, and ensures that wages meet applicable host-country legal requirements or explains any variance.
(iv) A housing plan, if the Contractor or subcontractor intends to provide or arrange housing, that ensures that the housing meets host-country housing and safety standards.
(v) Procedures to prevent agents and subcontractors at any tier and at any dollar value from engaging in trafficking in persons (including activities in paragraph (b) of this clause) and to monitor, detect, and terminate any agents, subcontracts, or subcontractor employees that have engaged in such activities.
(4) Posting. (i) The Contractor shall post the relevant contents of the compliance plan, no later than the initiation of contract perform-ance, at the workplace (unless the work is to be performed in the field or not in a fixed location) and on the Contractor’s Web site (if one is maintained). If posting at the workplace or on the Web site is impracticable, the Contractor shall provide the relevant contents of the compliance plan to each worker in writing.
(ii) The Contractor shall provide the compliance plan to the Contracting Officer upon request.
(5) Certification. Annually after receiving an award, the Contractor shall submit a certification to the Contracting Officer that—
(i) It has implemented a compliance plan to prevent any prohibited activities identified at paragraph (b) of this clause and to monitor, detect, and terminate any agent, subcontract or subcontractor employee engaging in prohibited activities; and
(ii) After having conducted due diligence, either--
(A) To the best of the Contractor’s knowledge and belief, neither it nor any of its agents, subcontractors, or their agents is engaged in any such activities; or
(B) If abuses relating to any of the prohibited activities identified in paragraph (b) of this clause have been found, the Contractor or subcontractor has taken the appropriate remedial and referral actions.
(i) Subcontracts. (1) The Contractor shall include the substance of this clause, including this paragraph (i), in all subcontracts and in all contracts with agents. The requirements in paragraph (h) of this clause apply only to any portion of the subcontract that--
(A) Is for supplies, other than commercially available off-the-shelf items, acquired outside the United States, or services to be per-formed outside the United States; and
(B) Has an estimated value that exceeds $500,000.
(2) If any subcontractor is required by this clause to submit a certification, the Contractor shall require submission prior to the award of the subcontract and annually thereafter. The certification shall cover the items in paragraph (h)(5) of this clause.
(End of clause)
52.232-29 Terms for Financing of Purchases of Commercial Items (Feb 2002)
(a) Contractor entitlement to financing payments. The Contractor may request, and the Government shall pay, a contract financing payment as specified elsewhere in this contract when: the payment requested is properly due in accordance with this contract; the sup-plies deliverable or services due under the contract will be delivered or performed in accordance with the contract; and there has been no impairment or diminution of the Government's security under this contract.
(b) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated contract financing payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at 52.212-4, Contract Terms and Conditions Commercial Items.
(c) Security for Government financing. In the event the Contractor fails to provide adequate security, as required in this contract, no financing payment shall be made under this contract. Upon receipt of adequate security, financing payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the provisions for contract financing. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such ad-ditional security, the Contracting Officer may collect or liquidate such security that has been provided and suspend further payments to the Contractor; and the Contractor shall repay to the Government the amount of unliquidated financing payments as the Contracting Officer at his sole discretion deems repayable.
(d) Reservation of rights.
(1) No payment or other action by the Government under this clause shall-
(i) Excuse the Contractor from performance of obligations under this contract; or
(ii) Constitute a waiver of any of the…