About this file

This Statement of Work (SOW) details requirements for a manual lathe and additional accessories for use at NASA Armstrong Flight Research Center. Key specifications for the lathe include a 11" swing x 18"cc capacity, 5HP spindle motor, digital spindle speed selector, and LED work light. Required accessories include an Acurite 203 DRO, various chucks and collets, a steady rest, taper attachment, and Aloris AXA#1 toolset. The lathe must be reliable and sturdy to handle regular operations, and fit within the fabrication shop space and floor loading limits. Delivery is required within 90 days of contract award under Solicitation Number 80NSSC23846739Q issued by the National Aeronautics and Space Administration Shared Services Center.

View the file

Other files for this federal contract opportunity

Other files attached to CNC Manual Lathe and additional features/kits plus shipping, newest first.
File Type Posted
RFQ 80NSSC23846739Q.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement Of Work (SOW)

1. Objective & Requirements:

2. Characteristics, Scopes, and Specs:

1 Tool room lathe with the following:

o Key Specs

LED work light

Inch‐metric dual dials

Inch‐metric gearbox

Capacity of 11” swing x 18”cc Hardened and Ground Dovetail bed plate 5HP spindle motor and VFD drive Digital spindle speed selector 4‐degree taper nose o Additional Options Acu‐rite 203 DRO 6” 3‐jaw chuck with backplate, buck chuck adjust‐tru style Albrecht keyless precision drill chuck with 2MT Aloris AXA#1 toolset with 6 various holders and standard AXA toolpost HARDINGE 5C collet set, 1/32” (33 pieces) Steady rest Taper attachment o Characteristics Reliable and maintainable Fit into fabrication shop

Meet floor loading limit of fabrication shop Sturdy frame to handle forces of regular lathe operation Standard mode of operation for a tool room lathe

3. Place of Performance:

NASA Armstrong Flight Research Center at Edwards Air Force Base

4. Period of Performance:

90 days lead time after contract award

File details come from the government source that posted it. Updated .