Questions and Answers 2.pdf

PDF 160 KB Posted

Attached to
GrCop 42 Additive Manufacturing Powder Federal contract opportunity
Solicitation number
80NSSC23842451Q
Issued by
National Aeronautics and Space Administration Shared Services Center

About this file

This document contains questions and answers regarding National Aeronautics and Space Administration solicitation number 80NSSC23842451Q for GrCop 42 additive manufacturing powder. The solicitation seeks 500 kilograms of chromium, niobium, and copper alloy powder within specified composition ranges for delivery within eight weeks of award. The procurement is only for the specified quantity and type of materials, with no drawings or 3D models provided.

View the file

Other files for this federal contract opportunity

Other files attached to GrCop 42 Additive Manufacturing Powder, newest first.
File Type Posted
Questions and Answers.pdf PDF
RFQ80NSSC23842451Q.pdf PDF
SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. Can you provide me with step file and drawing in order to quote solicitation 80NSSC23842451Q for GrCop 42 Additive Manufacturing Powder?

A step file is for a 3D model, this is powder, there is no step file or drawing.

2. What is the composition of the CrNbCu powder? Is it Cr3.27/Nb2.92/Cu93.81w%?

This chart shows the composition in weight percent, there is a range for each element shown with the target being in the middle of that range. The Cu is the balance to make up 100% after the other element target weights are taken out.

3. We are a manufacturer of custom parts for both metals and plastics. I might be confused but this looks like a request to order material request for NASA which we do not do.

The procurement is for materials so there are no drawings

4. The quote is for 500kgs, however we note that this was presented as a “minimum” amount. Is there a maximum or desired amount above 500kgs? Is there a required delivery date?

The procurement is for 500 Kgs of material, no more, no less. Product also must be delivered within 8 weeks after award.