2018_02_13_MAIA_Hosting_PreSol_Conference.pdf

PDF 3 MB Posted

Attached to
Multi-Angle Imager for Aerosols (MAIA) Hosting Services Amendment 1 Federal contract opportunity
Solicitation number
80LARC18R0004
Issued by
National Aeronautics and Space Administration Langley Research Center

About this file

Presolicitation Conference Slides

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PreSolicitation Conference NASA Langley Research Center

February 13, 2018

Multi-Angle Imager for Aerosols (MAIA) Hosting Services

Solicitation 80LARC18R0004

Agenda 8:00am Registration

8:15am NASA Science and Hosting Services Greg Stover

9:00am MAIA Science Overview Dave Diner

9:30am MAIA Instrument Overview Kevin Burke

10:00am Procurement Information/Other Michael Kaszyca

10:30am Break

11:00am One-on-One Sessions

Conference Guidelines

• All questions/communications pertaining to the Draft RFP (DRFP) and proposal preparation instructions shall be submitted in writing to Karen Dempster at larc-maia@mail.nasa.gov in accordance with the DRFP instructions.

• We will attempt to answer questions during the conference today, but some will likely require some research and/or an official decision, and those will be answered in writing at a later.

• All questions submitted by the February 7, 2018 initial deadline have been addressed and will be posted on the FedBizOps website.

• List of participants and conference presentation will be posted on the FedBizOps website.

• Nothing stated at this conference should be construed as a revision unless subsequently issued in an amendment or incorporated in the Final RFP.

• Communications blackout will be invoked once the Final RFP is issued.

NASA Science and Hosting Services Greg Stover Program Manager

Earth System Science Pathfinder Program

February 13, 2018

Guiding Recommendation Documents for NASA Earth Science Program of Record

2007 DECADAL SURVEY

• Research/Applications priorities

• No realistic budget constraint

• Shopping list of missions & activities

• Assumed Legacy missions completed

2010 NASA RESPONSE TO

CLIMATE PLAN

• Identified new Climate Measurements

• Matched against President’s budget

• Vetted w/OSTP, OMB & Admin

2012 NRC MIDTERM REPORT

• Endorsed NASA’s implementation

• “Encouraged” more rigorous cost control

• Endorsed additional Venture calls

In addition to these documents, we are responsive to Executive and Congressional direction

2017 Decadal Survey Snapshot for NASA Earth Science

2017 DECADAL SURVEY • Publicly released January 5, 2018

• Supports the NASA Earth Science Division Program of Record through 2023

• Prioritized observations rather than specific missions

• Emphasis on competition

• Provide NASA ESD with implementation flexibility

(Pre)Formulation

Implementation

Primary Ops

Extended Ops

ISS Instruments

LIS (2020), SAGE III (2020)

TSIS-1 (2018), ECOSTRESS

(2018), GEDI (2018)

EMIT (TBD)

NASA Earth Science Missions: Present through 2023

Landsat 9 (2020)

NI-SAR (2021)

SWOT (2021)

TEMPO (2018)

GRACE-FO (2) (2018)

ICESat-2 (2018)

CYGNSS (8) (2019)

NISTAR, EPIC

(DSCOVR / NOAA)

(2019)

QuikSCA T (2017)

Landsat 7

(USGS)

(~2022)Terra

(>2021)

Aqua (>2022)

CloudSat (~2018)

CALIPSO

(>2022)

Aura (>2022)

SMAP

(>2022)

Suomi NPP

(NOAA)

(>2022)

Landsat 8

(USGS)

(>2022)

GPM

(>2022)

OCO-2

(>2022)

Sentinel-6A/B (2020, 2025)

MAIA (~2021)

GeoCARB (~2021)

TROPICS (6) (~2021)

SORCE,

TCTE (NOAA)

(2017)

OSTM/Jason-2 (NOAA) (>2022)

JPSS-2 Instruments OMPS-Limb (2019)

02.06.18

PREFIRE (2) (TBD)

SAGE III (2020)

GEDI (2018)

ECOSTRESS (2018) LIS (2020)

TSIS-1 (2018)

Formulation

Implementation

Primary Ops

Extended Ops

International Space Station Earth Science Operating Missions

ELC-2

AMS

ESP-3 ELC-4

Columbus

EF JEMEF

ELC-1

ELC-3

External Logistics Carriers: ELC-1, ELC-2, ELC-3 External Stowage Platforms: ESP-3 Alpha Magnetic Spectrometer Columbus External Payload Facility Kibo External Payload Facility

02.06.18

EMIT (TBD)

• Addresses unique highly focused requirements in Earth system science research

• Complementary to the Facility‐class Earth Systematic missions

• Program consists of legacy missions and Venture Class

• Venture Class

• Science‐driven, PI‐led, competitively selected, cost‐ and schedule‐constrained, regularly solicited, orbital and suborbital

• Low‐to‐moderate cost ($30M‐$170M), small‐to‐medium sized orbital (class C/D) and sub‐orbital projects

– Cost capped for entire project life‐cycle

ESSP Program Characteristics Guiding

Open solicitation - In Review Completed solicitation

EVS

Sustained Sub-Orbital

Investigations (~4 years)

EVM

Complete, self-contained, small missions (~4 years)

EVI

Full function, facility-class instruments Missions of

Opportunity (MoO) (~18 months)

Earth Science Venture Opportunities

Mission Mission Type Release Date

Selection Date

Major Milestone

EV-1, aka EVS-1 5 Suborbital Airborne Campaigns 2009 2010 N/A

EVM-1, CYGNSS Smallsat constellation 2011 2012 Launched Dec 2016

EVI-1, TEMPO Geosynchronous hosted payload 2011 2012 Delivery NLT 2017

EVI-2, ECOSTRESS

& GEDI

Class C & Class D ISS-hosted

Instruments 2013 2014 Delivery NLT 2019

EVS-2 6 Suborbital Airborne Campaigns 2013 2014 N/A

EVI-3, MAIA &

TROPICS

Class C LEO Instrument & Class D

Cubesat Constellation 2015 2016 Delivery NLT 2021

EVM-2, GeoCarb Geostationary hosted payload 2015 2016 Launch ~2021

EVI-4, EMIT &

PREFIRE

CLASS C ISS-hosted payload & Class

D twin CubeSats 2016 2018 Delivery NLT 2021

EVS-3 Suborbital Airborne Campaigns 2017 2018 N/A

EVI-5 Instrument Only 2018 2019 Delivery NLT 2024

EVM-3 Full Orbital 2019 2020 Launch ~2025

EVI-6 Instrument Only 2020 2021 Delivery NLT 2025

EVS-4 Suborbital Airborne Campaigns 2021 2022 N/A

EVI-7 Instrument Only 2021 2022 Delivery NLT 2026 10

ESSP Portfolio

NASA Approach to Hosted Payloads

• Venture Class enabled an avenue that facilitates hosting

• We are committed to developing instruments and flying them on non-research satellites when it makes sense

• TEMPO as the very first Earth Venture instrument selected will be hosted on a commercial geostationary satellite

• MAIA is the first Earth Venture instrument selected to be hosted on a commercial low earth orbit satellite

• It is not only instruments for which the opportunity exists

• A Principal Investigator can propose hosting as their access to space for their instrument or suite of instruments in the Earth Venture mission line

• The GeoCarb PI is working with SES to host an instrument at GEO

• Continued discussions and support for the identifying and removing barriers in the hosted payload community will ensure continued opportunities

• Hosting is predicated on industry stating there is capacity to sell at a mutually advantageous price

Earth Venture Projects as Hosted Payloads

GeoCarb (Geostationary Carbon Cycle Observatory) measure key greenhouse gases and vegetation health from space to advance our understanding of Earth’s natural exchanges of carbon between the land, atmosphere and ocean

MAIA (Multi‐Angle Imager for Aerosols) maps airborne coarse, fine, sulfate, nitrate, organic carbon, black carbon, and dust particles, and assesses their impacts on human health

TEMPO (Tropospheric Emissions: Monitoring of Pollution) concurrent high temporal and spatial resolution measurements from GEO of tropospheric ozone, aerosols, their precursors, and clouds

In Summary

• We are committed to the Earth Venture line and its support of the recommendations of the first and second decadal survey

• We continue to look for opportunities to fly instruments on non-research satellites

• The commercial space community has been supportive in ensuring pathways exists for hosting instruments on commercial satellites

• Thanks for the opportunity to share how the commercial hosted payloads opportunity supports our vision of Earth Venture

ESSP Portfolio

13 February 2018

Multi-Angle Imager for Aerosols (MAIA)

Science Overview

David J. Diner Principal Investigator

Jet Propulsion Laboratory, California Institute of Technology

Associating airborne particle types with adverse health outcomes

M A I A

© 2018 California Institute of Technology.

Government sponsorship acknowledged. 16

Science Overview

Health Impacts of Particulate Matter (PM)

Inhalation of airborne PM has been associated with cardiovascular and respiratory diseases, heart attacks, low birth weights, lung cancer, and premature deaths.

The relative toxicity of specific PM types—mixtures having different proportions of coarse particles, fine particles, and chemical components—is poorly understood.

Coarse particles (PM10-PM2.5) irritate our respiratory systems.

Fine particles (PM2.5) penetrate deep into our lungs. Toxins can migrate to other organs.

MAIA’s primary objective is to assess the impacts of PM type on adverse birth outcomes, cardiovascular and respiratory diseases, and premature deaths.

Primary Science Objective

Science questions

For which PM types is maternal exposure during pregnancy linked to adverse birth outcomes such as restricted intrauterine growth, preterm delivery, and low birth weight?

For which PM types is short-term (daily to monthly) exposure linked to acute illness events (e.g., asthma flare-ups) and premature death?

For which PM types is chronic (multi-year) exposure linked to cardiovascular and respiratory disease?

Science Overview18

NASA selected MAIA under the Earth Venture Instrument-3 solicitation as a Hosted Payload.

MAIA is the first competitively selected NASA satellite mission with applications/societal benefit as its primary objective.

At the heart of the MAIA instrument is a spectropolarimetric camera system on a 2-axis gimbal.

The MAIA investigation integrates the satellite instrument observations, ground monitor data, and chemical transport model results to map size and compositional components of ambient PM.

Epidemiologists on the MAIA team will use the resulting data products to conduct health impact investigations.

Overview

MAIA Instrument Integrates Multiple Observing Modalities

Multi-angle radiometry Enhances the aerosol signal relative to surface reflection Sensitive to aerosol particle size and shape

Multi-angle polarimetry Sensitive to particle size and compositional proxies such as refractive index

Broad spectral coverage Ultraviolet: Aerosol absorption and height Visible/near-infrared: Fine mode aerosols Shortwave infrared: Coarse mode aerosols and cirrus cloud screening

Science Overview

Instrument design accommodates a 600-850 km sun-synchronous orbit.

� Scan (along-track) gimbal axis provides multi-angle viewing using a “step and stare” observing sequence (±60º field of regard)

Targets are observed repeatedly (~5 times at different view angles during each overpass)

� Pan (cross-track) gimbal axis allows access to targets that are off the sub-spacecraft track, and assists in onboard calibration (±45º field of regard)

Multi-angle Implementation

The requirement for multi-angle viewing makes low Earth orbit the appropriate orbit choice for MAIA.

MAIA is a Targeting Instrument

Science Overview

Candidate Primary Target Area (PTA):

Main candidate for project epidemiological studies

Potential PTA:

Additional site under consideration

Secondary Target Area (STA): Supports other air quality, aerosol and cloud climate studies

Calibration/Validation Target Area (CVTA):

Routinely observed site for vicarious calibration and instrument stability monitoring

List is not finalized. Host orbit is a key consideration in final target selection.

Observations of at least 10 globally-distributed PTAs covering a broad range of PM concentrations and particle types � Candidate PTAs currently include areas with low pollution (e.g., Canada) to areas with high pollution (e.g., India)

Each PTA observed, on average, at least 3 times per week Orbital mission duration: 3 years (baseline), 2 years

(threshold) Orbit altitude: in the range 600-850 km Polar, sun-synchronous orbit with mean equator-crossing time between 9:00 am and 3:00 pm, exclusive of 11:30 am to 12:30 pm

Level 1 Science Requirements

Concept of Operations

Illustration of operations that occur on a typical MAIA orbit. Earth science data are collected on the orbit dayside only.

On average, fewer clouds are expected in the morning than in the afternoon.

� Since clouds interfere with MAIA’s ability to determine PM concentrations, a morning equator crossing time is preferred.

Late morning allows time after sunrise for the near-surface boundary layer to become well mixed, which benefits MAIA’s ability to determine near-surface particle concentrations from the satellite measurements.

Drift in equator crossing time over mission life of up to 30 minutes is acceptable, provided 11:30 am - 12:30 pm keepout zone is avoided.

Equator Crossing Time Preferences

Higher spatial resolution favors lower altitudes, but being able to cover more cities with a given target area favors higher altitudes

Increased target revisit frequencies favor higher altitudes Target revisit pattern is related to orbit period, leading to certain discrete altitude ranges being more or less desirable For the final RFP, this chart will be simplified

� Narrow preference ranges will be smoothed out and there will be less variability with altitude

� General preference for orbits in the 700-800 km range will be retained

Orbit Altitude Preferences

Ascending vs. descending node � When multiple targets are observable on the same orbit track, the instrument can typically acquire data over only one of them, so it is necessary to choose which target to observe.

� The frequency of such conflicts depends on the specific geographic locations of the targets, and whether the orbit dayside is on the ascending or descending node.

� Given the specific target locations under consideration by the MAIA Science Team, we prefer an ascending node orbit.

Eccentricity � To provide consistency in spatial resolution and coverage between different PTAs, and between successive observations of the same PTA, circular or near-circular orbits are preferred, with eccentricity < 0.001.

Other Orbit Preferences

We look forward to your feedback on the draft RFP, your responses to the final RFP, and a productive partnership to benefit Earth science and human health.

Questions?

Concluding Remarks

© 2018 California Institute of Technology.

Government sponsorship acknowledged.

13 February 2018

Multi-Angle Imager for Aerosols (MAIA)

Instrument Overview

Kevin A. Burke Project Manager

Jet Propulsion Laboratory, California Institute of Technology

Associating airborne particle types with adverse health outcomes

M A I A

Instrument Overview - 1

The MAIA Instrument, currently under development, incorporates a spectropolarimetric camera system on a bi-axial gimbal that provides scan rotation (pointing the cameras along-track) and pan rotation (pointing the cameras cross-track).

Operation of the bi-axial gimbal � During launch: the MAIA cameras point internal to the MAIA Instrument with a launch lock engaged � During MAIA In-Orbit Checkout: the launch lock would be disengaged � During nominal operations: the MAIA Instrument’s scan and pan actuators would be commanded, via ground commands and scripts relayed to the MAIA Instrument Electronics, to point the cameras to targets of interest within the Instrument’s Field-of-Regard or to an on-board calibrator (OBC)

� During spacecraft thruster usage: the MAIA cameras point to a location within the MAIA Instrument as a means of contamination protection

Instrument Overview

Instrument Overview - 2

Instrument Overview - 3

The MAIA Instrument configuration shown on the previous slide is in the configuration consistent with a sun synchronous ascending orbit with day-side equator crossing time in the morning (this is the preferred orbit)

This configuration is identical to the configuration for a sun synchronous descending orbit with day-side equator crossing time in the afternoon

There are two additional orbit options:

� ascending orbit with day-side equator crossing time in the afternoon � descending orbit with day-side equator crossing time in the morning For the latter two options, the instrument would rotate 180º about the nadir (+Z) axis so that the Focal Plane Radiator is located on the anti-sun side of the instrument

The scan (along-track) gimbal axis provides multi-angle viewing of selected target areas using a “step and stare” observing sequence. The pan (cross-track) gimbal axis allows access to targets that are not directly situated on the sub-spacecraft track

Field of regard: ±60º along-track ±45º cross-track, at the instrument

Target area dimensions: at least 300 km 150 km, increasing with orbit altitude

Nadir footprint ~200 m Radiance measured in 14 spectral bands in the

UV/VNIR/SWIR, polarization measured in 3 of the bands

Instrument Characteristics - 1

Maximum expected mass: 80 kg Maximum expected dimensions: 70 cm (along-track)

90 cm (cross-track) 50 cm (height) Maximum expected power: 85 W (orbit average), 100 W

(peak) Maximum expected data rate: 10 Mbps (average), 100

Mbps (peak) Class C instrument per NASA NPR 8705.4

Instrument Characteristics - 2

Implementation Approach

JPL In-house development, integration and test with significant reliance on industry for components � Detector, Telescope, Modulator, Filters, Polarizers and Gimbal

Assemblies are sub-contracted � Camera Electronics in-house � Instrument Electronics out-of-house � Mechanical/Thermal in-house (numerous purchases) � Instrument Operations System (IOS) and Science Data System

(SDS) in-house Leverages architecture and development team from similar airborne instruments developed at JPL (AirMSPI / AirMSPI-2) Leverages Science Data System (SDS) from AirMSPI, and

Instrument Operations System and SDS from precursor spaceborne instrument (MISR)

Project Status

SRR/IDR completed March 2017 Subsystem PDRs nearing completion All subcontracts are in place PDR scheduled for April 2018 CDR tentatively planned for early 2019

Procurement Information/Other

Michael Kaszyca, Contracting Officer Office of Procurement (OP)

Procurement Specifics (1 of 3)

• Full & Open Competition under NAICS 541715 - Research and Development in the Physical, Engineering, and Life Sciences (Except Nanotechnology and Biotechnology (Size Standard of 1,000 employees). (SF1449)

• Commercial Item/Service in accordance with FAR Part 12. (Section 2)

• Contract type is Firm-Fixed-Price (FFP) with Milestone Payments. (Clauses

1.1 & 2.16; Exhibit D)

• Potential period of performance (POP) will be ~9 years consisting of a ~6-year base period and three, 1-year options. (Clause 1.3) ‒ Exact POP will be dependent on Offeror solutions; however the preferred launch date is no later than June 2022 based on a planned MAIA Instrument delivery availability of June 2020.

‒ Operations are planned for 36 months following launch and the 90 calendar day In-orbit Checkout Period.

‒ Option periods will be utilized for any extended mission operations.

Procurement Specifics (2 of 3)

• MAIA Instrument and Instrument-Specific Ground Support Equipment

(GSE) will be provided as Government-Furnished Property (GFP).

(Clauses 2.8 & 2.15) ‒ Contractor accountable for MAIA Instrument after completion of post-ship testing through the period up to launch vehicle ignition, at which time accountability transfers back to NASA.

‒ NASA will test the MAIA Instrument prior to transfer of accountability to the Contractor at the Contractor’s facility for integration with the spacecraft.

‒ GFP Includes:

• The MAIA Instrument.

• GSE including, but not limited to:

‒ Electrical and optical support equipment for testing the MAIA Instrument upon arrival at the Contractor’s facility (e.g., target sources, power supplies, electrical simulator for spacecraft functions and control computers).

‒ Handling fixtures including two lift fixtures, baseplates, and a cart with provision for moving and rotating the instrument.

• Containers for shipping and storing the MAIA Instrument and the GSE.

‒ The MAIA shipping container will contain purge equipment to control MAIA

Instrument contamination during shipping and storing.

Procurement Specifics (3 of 3)

• Contractor shall be AS9100 compliant as of the date of proposal submission.

(Clause 2.14 & Provision 5.2.6) ‒ If AS9100 certified/registered, provide certificate with proposal.

‒ If not AS9100 certified/registered, provide documentation required in provision

5.2.6.

• Contractor required to obtain and maintain all necessary licenses, permits, clearances, etc. required to perform services (Clause 2.18)

• Contractor shall remain a “United States commercial provider” (as defined at 51 U.S.C. §50101) throughout the entire contract period of performance, including any exercised option periods. (Clauses 2.20 & Provision 4.3)

Proposal Preparation/Evaluation (1 of 3)

• Please read the solicitation carefully and ask questions!

– This presentation is not covering the specific proposal and evaluation instructions, requirements, and process contained therein.

– Anticipate possible changes in Final RFP compared to DRFP.

• Ensure proposal contains all necessary information, required documentation, and is complete in all aspects.

– Offeror responsible for proposal clarity and ensuring it considers the entire solicitation, including information in any solicitation Attachments, such as Attachment 3, Reference Documents. (Provision 5.2.1)

– Ensure all Offeror-required fill-ins are complete (e.g., Section 1.1, Contract Pricing; Exhibit D, Milestone Payment Schedule; Items in Exhibit C, MRD).

(Provision 5.2.5)

– Total POP is based on Offeror’s overall approach to meeting requirements.

(Section 1.3 & Provision 5.1.5)

– Additional Required Documentation (AS9100 Compliance & Government Property Management Information) NOT part of overall evaluation/selection, but IS part of overall responsibility determination. (Provisions 5.2.6 & 6.2)

Proposal Preparation/Evaluation (2 of 3)

• Electronic proposals ONLY; no paper. (Provision 5.2.2)

• NASA is not establishing Small Business Goals.

‒ Offeror responsibility to propose goals and Small Business Subcontracting

Plan (Exhibit E). (Provision 5.2.7, Subfactor 4) ‒ NASA Small Business Specialist available to discuss any specific questions.

• NASA may, unilaterally, choose to incorporate any positive aspects of an Offeror’s approach to meeting/exceeding contract requirements into the final awarded contract, particularly if any positive proposal area results in Strength or Significant Strength findings in the Mission Suitability evaluation. (Provisions 5.2.7 & 6.3)

• NASA may reject any proposal that fails to comply with all proposal instructions, including those for electronic submissions, as incomplete and unacceptable.

(Provision 5.2.1)

• Method of Evaluation (Provision 6.2) ‒ Proposals received in response to this solicitation will be evaluated by a

Source Evaluation Board (SEB) in accordance with NFS 1815.3.

‒ A best value trade-off process, as described at FAR 15.101-1, Tradeoff

Process, will be used in making the source selection.

‒ Evaluation is based upon actual material presented and not on the basis of what is implied.

• The Government intends to award a contract without discussions, but reserves the right to hold discussions if the Contracting Officer deems necessary. (Provision 52.212-1(g))

• Overall, in the selection of a Contractor for contract award, Mission Suitability and Past Performance will be of approximately equal importance. In accordance with FAR 15.304(e), Mission Suitability and Past Performance, when combined, are approximately equal to Price.

(Provision 6.4)

Proposal Preparation/Evaluation (3 of 3)

Schedule (Tentative)

• Draft RFP Comments Due March 1, 2018

• RFP Release April 30, 2018

• Proposal Due RFP Release + 30 calendar days

• Proposal Evaluation Period June – October 2018

• Award October 2018

Break