3. Statement of Work (SOW)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 2._Questions_and_Answers_Template.pdf | ||
| 1._JOFOC_(redacted).pdf | ||
| 80KSC019Q0015_rev2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NASA, KENNEDY SPACE CENTER
Tasks for Mindrum Precision
Statement of Work
April 3, 2019
1.0 Background
The Water Analysis and Volatile Extraction (WAVE) fluid subsystem is developing its Protoflight and Flight hardware, the continuation of a testing effort using Mindrum Microvalves and Gland Assemblies for the last five years. The Gland Assemblies interface directly to the Microvalve and WAVE manifold, and are essential in continuation and maturation of the previous testing effort for progression to flight.
Mindrum will perform proof pressure testing and leak testing of the Gland Assemblies to verify workmanship and leak rates of the welded assemblies in time to meet the milestones of the SMD-funded project
2.0 Objectives
Mindrum will use its existing test setup for pressure testing and characterization of six (6) Gland Assemblies up to a maximum of 450 psia. Mindrum will deliver the resulting pressure and leak testing data.
3.0 Tasks
The contractor shall perform each of the following tasks:
1. Revive previous fixture and setup (developed in 2017) for pressure and leak testing of the Mindrum Gland Assemblies up to a maximum of 450 psia
2. Proof pressure test:
a) Six (6) 1/8” Gland Assemblies in the pressure test setup to 450 psia
3. Leak test per Mindrum’s helium leak test procedure, and verify leak rate is < 5x10-9 atm-cc/sec steady state
a) Six (6) 1/8” Gland Assemblies
4.0 Deliverables
1. Deliver test setup diagram
2. Deliver pressure and leak test data for each Gland Assembly
Quote line item 5
3. Deliver four (4) Flight Microvalves (part number 6810) by June 2019
Quote line item 1
4. Deliver eight (8) Upper Internal Pressure Seals (part number 6823) by August 2019
Quote line item 2
5. Deliver eight (8) Lower External Pressure Seals (part number 6824) by August 2019
Quote line item 3
6. Deliver six (6) 1/8” Gland Assemblies (part number 6827) by June 2019
Quote line item 4
NASA, KENNEDY SPACE CENTER
7. Deliver six (6) Platinum Seals (part number 6822) by May 2019
Quote line item 6
9.0 Period of Performance
Delivery within 120 days of award