80GSFC18R0053_Request_for_Proposal.pdf

PDF 886 KB Posted

Attached to
Plankton, Aerosol, Cloud, ocean Ecosystem (PACE) Thruster Federal contract opportunity
Solicitation number
80GSFC18R0053
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

Request for Proposal

View the file

Other files for this federal contract opportunity

Other files attached to Plankton, Aerosol, Cloud, ocean Ecosystem (PACE) Thruster, newest first.
File Type Posted
SF30_Amendment_One.pdf PDF
Attachment_A_Statement_of_Work.pdf PDF
80GSFC18R0053_RFP.pdf PDF
Enclosure_L.1_Thruster_Past_Performance_Questionaire.pdf PDF
Attachment_B_Specifications.pdf PDF
Enclosure_L.2_Compliance_matrix.pdf PDF
Attachment_A_Statement_of_Work.pdf PDF
RFP_Cover_Letter.pdf PDF
SF33.pdf PDF
Attachment_C_Small_Business_Subcontracting_Plan_Goals.pdf PDF
PACE_THRUSTER_SPEC_LIST_draft.pdf PDF
PACE_THRUSTER_SOW_draft.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

80GSFC18R0053

1 | P a g e

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 1852.216-78 FIRM FIXED PRICE (DEC 1988)

The total firm fixed price of this contract is $TBD

(End of clause)

B.2 GSFC 52.211-90 SUPPLIES AND/OR SERVICES TO BE PROVIDED (SEP 2017)

The Contractor shall provide all resources (except as may be expressly stated in the contract as furnished by the Government) necessary to deliver and/or perform the items below in accordance with the Statement of Work (SOW), incorporated as Attachment A.

Deliverable Items List and Schedule (DILS)

Item

Description Reference Schedule Delivery

Method/Addressee(s)

1 Reserved

2 Monthly Status Report SOW 3.2 Fourteen (14) calendar days following the month being reported.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

For Information

Purposes.

3 Reserved

4 Notifications SOW 3.3 Seven (7) calendar days in advance of all mandatory hardware inspections, test activities, TIM’s, and deliveries.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

5 Kick Off Meeting SOW 3.4.1 Fourteen (14) calendar days after contract effective date

In person at Contractor

Facility.

Review Required.

6 Kick Off Meeting Package SOW 3.4.1 Three (3) working days before the meeting

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required

7 Design Conformance Review

(DCR)

SOW

3.4.2, 6.4

Three (3) months after contract effective date

In person at Contractor

Facility.

2 | P a g e

Review Required.

8 Design Conformance Review

Presentation Package

SOW

3.4.2, 6.4

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

9 Design Conformance Review

Report

SOW

3.4.2, 6.4

Fourteen (14) calendar days after completion of DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

10 Pre-Environmental Review

(PER) (Option)

SOW 3.4.3 Seven (7) calendar days before start of environmental testing on first Flight Unit

After Option Exercise

In person at Contractor

Facility.

Review Required.

11 Pre-Environmental Review

Presentation (Option)

SOW 3.4.3 At PER

After Option exercise

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

12 Flight Unit(s) Pre-Ship

Review (PSR)

SOW 3.4.4 Seven (7) calendar days prior to delivery of each

Flight Unit

In person at Contractor

Facility.

Review Required.

13 Flight Unit(s) Pre-Ship

Review Presentation Package

SOW 3.4.4 At PSR Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

14 Flight Unit(s) End Item Data

Package(s) (EIDP)

SOW

3.4.4, 7.8.3, 7.7.1, 7.8.6

With each delivered Flight

Unit and available at PSR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

15 TIM SOW 3.4.5 As Negotiated In person at Contractor

Facility.

Review Required.

16 Interface Control Document(s) SOW 4.1 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

3 | P a g e

17 Drawing Package SOW 4.2 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

18 Computer Models SOW 4.3 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

For Information

Purposes.

19 Structural Analysis Report SOW 4.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

20 Structural Finite Element

Model

SOW 4.5 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

21 Thermal Analysis Report SOW 4.6 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

22 Thermal Model &

Documentation

SOW 4.7 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

23 Worst Case Circuit Analysis

Report

SOW 4.8 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

24 Parts Stress Analysis Report SOW 4.9 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Review Required.

4 | P a g e

25 Parts Stress Analysis Criteria if different from EEE-INST-

SOW 4.9 Twenty-eight (28) calendar days after contract effective date

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

26 NA

27 Reliability Analysis Report SOW 4.11 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

28 FMECA Report SOW 4.12 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

29 Reserved

30 Y Reserved

31 User/Instruction Manual SOW 4.15 Fourteen (14) calendar days before PSR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required

32 Reserved

33 Verification Plan (Including

Verification Matrix)

SOW 6.1,

7.5.1

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

34 Individual Verification Test

Plan(s) (if needed)

SOW 6.1 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

35 Acceptance Verification Test

Procedure(s)

SOW 6.2 Twenty-eight (28) calendar days before start of testing and as changes occur.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

36 Acceptance Verification Test

Report(s)

SOW 6.3 At PSR Electronic – Provide submittal in electronic

5 | P a g e format to the COR and

Review Required.

37 Quality Assurance Plan SOW 7.1.1 Twenty-eight (28) calendar days after contract effective date

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

38 Anomaly/Failure Reports SOW 7.1.3 Deliver initial submission within 24 hours of occurrence for information for Major Anomaly.

Deliver notice of a change in status within 24 hours of occurrence for information.

Deliver the proposed closure prior to closure for approval.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

39 Class I Configuration

Management (CM) Changes

SOW 7.1.4 Seven (7) calendar days after Contractor CM review

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

40 Class II CM Changes SOW 7.1.4 Seven (7) calendar days after Contractor CM review

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

41 Safety/Hazard Controls SOW 7.2 Three (3) working days after Contractor disposition

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

42 Trended Parameters List SOW 7.3.1 Seven (7) calendar days prior to EIDP

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

43 Limited Life Items List SOW 7.3.2 Fourteen (14) calendar days before DCR

Electronic – Provide

6 | P a g e

44 Expired Shelf Life Waiver SOW 7.3.2 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

45 Reserved

46 Reserved

47 Alternate Workmanship

Standards

SOW 7.6.3 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

48 Reserved

49 Reserved

50 EEE Parts Identification List

(PIL)

SOW 7.7.1 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

As-Built Parts List (ABPL) SOW 7.7.1 As part of EIDP (DIL #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

51 Reserved

52 Reserved

53 Recertification Plans for Parts

> 7 years old (if applicable)

SOW 7.7.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

54 GIDEP Alert Disposition and

Preparation

SOW 7.7.5 Three (3) working days after Contractor evaluation

Summary in Monthly Status

Report

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

55 Part Failure Reporting SOW 7.7.7 Twenty-four (24) hours after failure determination

Electronic – Provide

7 | P a g e

Approval Required.

56 Materials and Processes List SOW

7.8.3, 7.9.3

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

As-Built Materials List SOW 7.8.3 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

57 Materials Usage Agreement SOW 7.8.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

Materials Certificate of

Compliance

SOW 7.8.6 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

58 List of Atomic Oxygen

Exposed Materials

SOW 7.8.5

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

59 Nondestructive Evaluation

(NDE) Plan

SOW 7.8.5

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

60 Fastener Integrity Control

Plan

SOW 7.8.5

Thirty (30) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

61 List of Critical Fasteners

SOW 7.8.5

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic

8 | P a g e

62 Contamination Control Plan SOW 7.9.1 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

63 Reserved

64 NA

65 NA

66 Inherited Items Package (if needed)

SOW 3.7.2 Initial: Thirty (30) calendar days after contract effective date

Final: Ninety (90) calendar days after Kick Off Meeting

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

67 Thruster Flight Unit(s)

Quantity: 8

SOW 5.2 12 Months after contract effective date

As specified in Clause

GSFC 52.247-94

68 Thruster Flight Unit (Spare)

Quantity: 1

SOW 5.2 12 Months after contract effective date

69 Red Protective Cover for

Thruster

Quantity: 9

SOW 5.5 With Item #67 As specified in Clause

70 Alignment Fixture with

Nozzle Plugs for optical alignment

Quantity: 8

SOW 5.5 With Item #67

71 GSE(s)Nozzle Plugs with AN interface

SOW 5.5 With Item #67 As specified in Clause

72 Vendor’s Welding and

Inspection Procedure

SOW 7.8.8 Twenty-one (21) calendar days after DCR

Electronic – Provide submittal in electronic format to the COR and

Notes:

A = Approval – Items in this category require approval from the National Aeronautics and Space

Administration (NASA)/Goddard Space Flight Center (GSFC) Contracting Officer (CO). In general, documents shall be provided in contractor format as long as required content, as specified in the Plankton, Aerosol, Cloud, ocean Ecosystem (PACE) Thruster Statement of Work (PACE-PROP-SOW-0048), is

9 | P a g e addressed. The NASA GSFC CO reserves the time-limited right of disapproval for each submission. The time-limited period is two weeks from receipt of documents.

R= Review – Items in this category do not require formal NASA GSFC CO approval, but will be reviewed by the GSFC or its designated representatives in order to determine contractor effectiveness in meeting contract objectives. When Government review reveals inadequacies, the contractor may be requested to correct the inadequacies. GSFC will review and comment within 20 working days of receipt.

I = Information – Items in this category are informal and are for information only.

B.3 GSFC 52.232-99 MILESTONE PAYMENT SCHEDULE (FIXED PRICE) (NOV 2013)

(a) Subject to other limitations and conditions specified in this contract, milestone payment shall be made to the Contractor upon delivery and acceptance of the milestone events described under paragraph (b).

(b) The payment schedule amount shall be calculated by the application of the contract percentage established per milestone event to the total fixed price amount indicated under

Section B contract clause NFS 1852.216-78, Firm-Fixed Price.

No.

Event Qty

Contract

Value %

Total

Amount Completion Determination

1 Kick-Off Meeting 1 30 TBP

Final presentation package received in accordance with Section 3.4.1 of SOW, Attachment A

Design Conformance

Review (DCR)

1 15 TBP

Final presentation package received in accordance with Section 3.4.2 of SOW, Attachment A

DCR Action Item

Closure

1 5 TBP

Final presentation package received in accordance with Section 3.4.2 of SOW, Attachment A

ATP Performance

Testing

1 10 TBP

Verification test reports received in accordance with Sections 3.4.4 and 6.3 of

SOW, Attachment A

5 PSR Thruster Delivery 1 30 TBP

Hardware received in accordance with

Sections 5.2 and 5.5 of SOW, Attachment

A

6 Final Documentation 1 10 TBP

EIDP received in accordance with

Sections 3.4.4, 7.7.1, 7.8.3, and 7.8.6 of

SOW, Attachment A

(c) The Contractor may submit requests for payment not more frequently than monthly, in a form and manner acceptable to the Contracting Officer. Unless otherwise authorized by the

Contracting Officer, all milestone payments in any period for which payment is being requested shall be included in a single request, appropriately itemized and totaled.

(d) The Contractor shall not be entitled to payment of a request for milestones payment prior to successful accomplishment and acceptance by the Government of the milestone event. The

Contracting Officer shall determine whether the milestone event or performance criterion for

10 | P a g e which payment is requested has been successfully accomplished and accepted by the

Government in accordance with the terms of the contract. The Contracting Officer may, at any time, require the Contractor to substantiate the successful performance of any event or performance criterion which has been or is represented as being payable.

B.4 GSFC 52.217-91 OPTION FOR INCREASED QUANTITY (SEP 2013)

In accordance with the Option for Increased Quantity--Separately Priced Line Item clause of this contract, the Government may increase the quantity of items as follows:

Option Description Qty. Delivery Date Firm Fixed

Price Amount

Pre-Environmental

Review (PER)

(Option)

Seven (7) calendar days before start of environmental testing on first Flight Unit

$TBP

Pre-Environmental

Review Presentation

(Option)

1 At PER $TBP

This option may be exercised by the Contracting Officer by written notice to the

Contractor within the time period specified in FAR clause 52.217-7, "Option for

Increased Quantity--Separately Priced Line Item" of this contract.

[END OF SECTION B]

10 | P a g e

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 GSFC 52.211-91 SCOPE OF WORK (FEB 2016)

The Contractor shall provide the personnel, materials, and facilities, except as otherwise specified in this contract, necessary to perform the work and to furnish the items specified in the

Supplies and/or Services To Be Provided clause of this contract in accordance with the Statement of Work (SOW), Attachment A; and Specification (SPEC), Attachment B.

C.2 GSFC 52.235-91 REPORTS OF WORK (CORE) (AUG 2013)

(a) Monthly progress reports. The Contractor shall submit monthly progress reports of all work accomplished during each month of contract performance. Reports shall address the accomplishments and progress of all work performed the month being reported. The report shall be in narrative form and brief in content. The report shall include a description of technical accomplishments and status of deliverables. Also the report shall provide a quantitative description of overall progress and identify any risks or problems, which may impede performance and proposed corrective actions. Also the report shall have a discussion of the projected work activities to be performed during the next monthly reporting period.

(b) Submission. The Contractor shall submit the reports required by this in electronic format to

COR, Contract Specialist, and Contracting Officer.

(c) Submission dates. Monthly reports shall be submitted fourteen (14) calendar days following the month being reported. If the contract is awarded beyond the middle of a month, the first monthly report shall cover the period from award until the end of the following month. The final report shall be submitted within 30 days after completion of the contract.

[END OF SECTION C]

11 | P a g e

SECTION D - PACKAGING AND MARKING

D.1 SECTION D CLAUSES INCORPORATED BY REFERENCE

The clause below is incorporated by reference, with the same force and effect as if they were given in full text. Clauses incorporated by reference which require a fill-in by the Government include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire clause. The full text of the clause is available at the addresses contained in clause 52.252-2, Clauses Incorporated by Reference, of this contract.

1852.211-70 PACKAGING, HANDLING, AND TRANSPORTATION (SEP 2005)

D.2 1852.245-74 IDENTIFICATION AND MARKING OF GOVERNMENT

EQUIPMENT (JAN 2011)

(a) The Contractor shall identify all equipment to be delivered to the Government using NASA

Technical Handbook (NASA-HDBK) 6003, Application of Data Matrix Identification Symbols to Aerospace Parts Using Direct Part Marking Methods/Techniques, and NASA Standard

;(NASA- STD) 6002, Applying Data Matrix Identification Symbols on Aerospace Parts or through the use of commercial marking techniques that: (1) are sufficiently durable to remain intact through the typical lifespan of the property: and, (2) contain the data and data format required by the standards. This requirement includes deliverable equipment listed in the schedule and other equipment when no longer required for contract performance and NASA directs physical transfer to NASA or a third party. The Contractor shall identify property in both machine and human readable form unless the use of a machine readable-only format is approved by the NASA Industrial Property Officer.

(b) Equipment shall be marked in a location that will be human readable, without disassembly or movement of the equipment, when the items are placed in service unless such placement would have a deleterious effect on safety or on the item's operation.

(c) Concurrent with equipment delivery or transfer, the Contractor shall provide the following data in an electronic spreadsheet format:

(1) Item Description.

(2) Unique Identification Number (License Tag).

(3) Unit Price.

(4) An explanation of the data used to make the unique identification number.

(d) For equipment no longer needed for contract performance and physically transferred under paragraph (a) of this clause, the following additional data is required:

(5) Date originally placed in service.

(6) Item condition.

12 | P a g e

(e) The data required in paragraphs (c) and (d) of this clause shall be delivered to the NASA center receiving activity listed below:

NASA Goddard Space Flight Center Building 35, Code 279 Greenbelt MD 20771

(f) The contractor shall include the substance of this clause, including this paragraph (f), in all subcontracts that require delivery of equipment.

[END OF SECTION D]

13 | P a g e

SECTION E - INSPECTION AND ACCEPTANCE

E.1 SECTION E CLAUSES INCORPORATED BY REFERENCE

The clauses below are incorporated by reference, with the same force and effect as if they were include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire

52.246-2 INSPECTION OF SUPPLIES—FIXED PRICE (AUG 1996)

52.246-16 RESPONSIBILITY FOR SUPPLIES (APR 1984)

E.2 1852.246-71 GOVERNMENT CONTRACT QUALITY ASSURANCE

FUNCTIONS (OCT 1988)

In accordance with the inspection clause of this contract, the Government intends to perform the following functions at the locations indicated:

Item Quality Assurance Location Function

Deliverables In accordance with Attachment A, Statement of Work, Section 7.0

E.3 1852.246-72 MATERIAL INSPECTION AND RECEIVING REPORT (APR 2015)

(a) At the time of each delivery to the Government under this contract, the Contractor shall prepare and furnish a Material Inspection and Receiving Report (DD Form 250 series). The form(s) shall be prepared and distributed as follows:

(1) Via mail and marked "Advance Copy", one copy each to the Contracting Officer, the

Contracting Officer's Representative/Technical Officer (designated in Clause F.3), and to the cognizant Administrative Contracting Officer, if any.

(2) Via mail, the original and 1 copy (unfolded) to the shipment address (delivery point) specified in Section F of this contract. Mark the exterior of the envelope "CONTAINS

DD FORM 250". This must arrive prior to the shipment.

(3) With shipment in waterproof envelope (one copy) for the consignee.

(4) If the shipment address is not directly to the Goddard Space Flight Center

(Greenbelt) or GSFC/Wallops Flight Facility (Wallops) central receiving areas, then one copy of the DD Form 250 must be provided (via mail) to one on the following addresses:

Receiving and Inspection (Code 279), Goddard Space Flight Center, Greenbelt, MD 20771.

14 | P a g e

(b) The Contractor shall prepare the DD Form 250 in accordance with NASA FAR Supplement

1846.6. The Contractor shall enclose the copies of the DD Form 250 in the package or seal them in a waterproof envelope, which shall be securely attached to the exterior of the package in the most protected location.

(c) When more than one package is involved in a shipment, the Contractor shall list on the DD

Form 250, as additional information, the quantity of packages and the package numbers. The

Contractor shall forward the DD Form 250 with the lowest numbered package of the shipment and print the words “CONTAINS DD FORM 250” on the package.

E.4 GSFC 52.246 94 MATERIAL INSPECTION AND RECEIVING REPORT NOT

REQUIRED (APR 1989)

NASA FAR Supplement clause 1852.246-72 of this contract requires the furnishing of a Material

Inspection and Receiving Report (MIRR) (DD Form 250 series) at the time of each delivery under this contract. However, a MIRR is not required for deliverable items one through sixty six

(1-66) and seventy two (72).

E.5 GSFC 52.246-102 INSPECTION SYSTEM RECORDS (APR 2013)

The Contractor shall maintain records evidencing inspections in accordance with the Inspection clause of this contract for six (6) years after delivery of all items and/or completion of all services called for by the contract.

[END OF SECTION E]

15 | P a g e

SECTION F - DELIVERIES OR PERFORMANCE

F.1 SECTION F CLAUSES INCORPORATED BY REFERENCE

include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire

52.211-17 DELIVERY OF EXCESS QUANTITIES (SEP 1989)

52.242-15 STOP-WORK ORDER (AUG 1989)

52.242-17 GOVERNMENT DELAY OF WORK (APR 1984)

52.247-34 F.O.B. DESTINATION (NOV 1991)

F.2 1852.247-72 ADVANCE NOTICE OF SHIPMENT (OCT 1988)

Five (5) work days prior to shipping item(s) sixty seven through seventy one (67-71) from

Clause B.2, the Contractor shall furnish the anticipated shipment date, bill of lading number (if applicable), and carrier identity to the Contracting Officer’s Representative and to the

F.3 GSFC 52.247-94 SHIPPING INSTRUCTIONS--CENTRAL RECEIVING (FEB

2016)

Shipments of the items required under this contract shall be to:

Receiving Officer, Goddard Space Flight Center

Building 35, Code 279

Greenbelt, Maryland 20771

Marked for:

Technical Officer: Jacob Stahl, Code 597

Building: 11, Room: E141

Contract No.: TBD

Item(s) No.: TBD (from Clause B.2)

Compliance with this clause is necessary to assure verification of delivery and acceptance and prompt payment.

As this is a fixed price type contract, delivery--for purposes of the Prompt Payment Act--must be through the above shipping address unless another location has been authorized by the

Contracting Officer. If delivery is made to other than the Receiving Officer listed above and shipment to that other location has not been authorized by the Contracting Officer, a delivery for the purposes of the Prompt Payment Act has not occurred and no interest penalty under the Act

16 | P a g e shall result. Shipment to other than Receiving Officer listed above will be construed as contract noncompliance.

[END OF SECTION F]

17 | P a g e

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 SECTION G CLAUSES INCORPORATED BY REFERENCE

include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS (DEC 2014)

1852.223-71 AUTHORIZATION FOR RADIO FREQUENCY USE (APR 2015)

1852. 227-70 NEW TECHNOLOGY – OTHER THAN A SMALL BUSINESS FIRM OR

NONPROFIT ORGANIZATION (APR 2015)

1852.227-72 DESIGNATION OF NEW TECHNOLOGY REPRESENTATIVE AND PATENT

REPRESENTATIVE (APR 2015)

G.2 INVOICES - SUBMISSION OF (GSFC 52.232-95) (MAR 2018)

(a) Payment Office. The designated payment office is the NASA Shared Services Center (NSSC) located at FMD Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS

39529. Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.

(b) Invoices. Except for classified invoices, invoices shall be prepared in accordance with the invoicing instructions in FAR 52.212-4(g). In addition, invoices shall be submitted using the steps described at the NSSC’s Vendor Payment information web site at https://www.nssc.nasa.gov/vendorpayment.

(c) Improper invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in any invoices within seven calendar days of receipt by the NSSC

Payment Office. Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.

(d) In the event that amounts are withheld from payment in accordance with provisions of this award, a separate payment request for the amount withheld will be required before payment for that amount may be made.

G.3 GSFC 52.245-94 INVENTORY OF GOVERNMENT OWNED PROPERTY--

SPECIAL PROCEDURES FOR FLIGHT QUALIFIED INVENTORY (DEC 2007)

(a) The Contractor shall ensure that flight qualified assemblies and parts that are residual https://www.nssc.nasa.gov/vendorpayment

18 | P a g e inventory under this contract are properly stored in a secure area that is certified for electostatic discharge (ESD) handling. The parts shall be handled in accordance with electrostatic discharge

(ESD) standards and procedures. The Contractor shall also maintain a system to ensure that the associated heritage, test, and qualification documentation is available and traceable to such individual items of inventory.

(b) In accordance with the “Physical inventory” required in FAR clause 52.245-1(f)(iv), the

Contractor shall identify any hardware, components or parts suitable for space flight or at any time such inventory is excess to the needs of this contract.

(c) Compliance with this clause is required until:

(1) The Government exercises its right under the Government Property clause of this contract and under FAR 45.6 to require delivery of any such inventory or the transfer of such inventory to another Government contract. [Flight qualified assemblies or parts remaining in residual inventory shall remain subject to this clause]; or

(2) The Contractor and the Government agree to, partly or completely, discontinue the requirements of this clause for specific items of flight qualified assemblies and parts; or.

(3) The period stated in this contract for the Contractor to maintain inspection records under the

Inspection clause of this contract has expired.

(d) In the event of (c)(1) above, the delivered or transferred flight qualified inventory shall be accompanied by all data and records regarding the flight certification of each of item(s) comprising the flight qualified inventory for which the Government's right is exercised.

(e) When flight qualified inventory is no longer subject to this clause because of (c)(1), (c)(2) or

(c)(3) of this clause, the designated flight qualified inventory item(s), shall subsequently be managed no more stringently than other government property in accordance with FAR 52.245-1.

G.4 GSFC 52.245-99 SUPPLEMENTAL FINANCIAL REPORTING OF NASA

PROPERTY IN THE CUSTODY OF CONTRACTORS. (MAR 2017)

(a) In addition to the annual 1018 reporting required under clause NFS 1852.245-73 of this contract, the Contractor shall submit monthly property financial reports as described below if, at either award or any time during contract performance, the cumulative amount of NASA property is $10 million or more.

(1) Monthly property financial reports shall be submitted including item-level supporting data for all items acquired/fabricated/modified where the total acquisition cost of the item is

$500,000 or more, in the contractor’s or its subcontractors’ possession. This data shall be submitted for all items in the property classifications of real property, equipment, special test equipment, special tooling, and agency peculiar property.

(2) Monthly data shall also be submitted for items of any acquisition cost in the classifications of materials and contract work-in-process (WIP). Specifically, itemized monthly

19 | P a g e data is required for materials and WIP line items when the estimated total acquisition cost of any item at completion will be $500,000 or more.

(b) The monthly reports shall be electronically submitted using the Contractor-Held Asset

Tracking System (CHATS) at https://chats.nasa.gov using the format described in the CHATS user’s manual.

(c) Acquisition costs shall be developed using actual costs to the greatest extent possible, especially costs directly related to fabrication such as labor and materials. Supporting documentation shall be maintained and available for all amounts reported, including any amounts developed using estimating techniques.

(d) All adjustments shall be thoroughly explained and directly related to a specific Government

Fiscal Year (GFY). If the GFY cannot be determined, the default shall be the previous GFY.

(e) Work Breakdown Structures (WBS) shall be provided for all Contractor acquired property

(CAP), WIP, and any new materials acquired. The format shall be a five digit numerical level.

(i.e., 803-10). If the WBS is not identifiable, contact the NASA GSFC Property Office for further guidance, as provided in paragraph (f)(4) below.

(f)(1) The data required for the monthly submission is due the 21st day after the close of the month.

e.g., August 21 for the month ending July 31

September 21 for the month ending August 31

October 21 for the month ending September 30

(2) The monthly property financial reports required by this clause are separate from, and in addition to the annual NF 1018 reports.

(3) Both the NF 1018 report data and the September monthly report data are as of September 30.

Corrections in monthly report data shall be handled as adjustments in the next monthly report after discovery of the error. (e.g., Errors in the September monthly report shall be reported as adjustments in the October monthly report. The NF 1018 shall reflect the corrected numbers and the contractor shall provide a note regarding the corrected monthly report error under Comments in the NF 1018.) Errors in the NF1018 found after the November 30 submission shall be reported as adjustments in the NF 1018 for the next reporting year, unless immediate correction and resubmission are directed by NASA.

(4) Questions may be directed to the following individuals of the NASA GSFC Property Office:

Kia Hughes, (301) 286-0810, email kia.hughes@nasa.gov

Loren Phillips (301) 286-0785, e-mail: loren.j.phillips@nasa.gov

[End of Clause] https://chats.nasa.gov/ mailto:barbara.scott@nasa.gov mailto:loren.j.phillips@nasa.gov

20 | P a g e

G.5 1852.245-73 FINANCIAL REPORTING OF NASA PROPERTY IN THE CUSTODY

OF CONTRACTORS (JAN 2017)

(a) The Contractor shall submit annually a NASA Form (NF) 1018, NASA Property in the

Custody of Contractors, in accordance with this clause, the instructions on the form and NFS subpart 1845.71, and any supplemental instructions for the current reporting period issued by

NASA.

(b)(1) Subcontractor use of NF 1018 is not required by this clause; however, the Contractor shall include data on property in the possession of subcontractors in the annual NF 1018.

(2) The Contractor shall mail the original signed NF 1018 directly to the cognizant NASA Center

Industrial Property Officer and a copy to the cognizant NASA Center Deputy Chief Financial

Officer, Finance, unless the Contractor uses the NF 1018 Electronic Submission System (NESS) for report preparation and submission.

(3) One copy shall be submitted (through the Department of Defense (DOD) Property

Administrator if contract administration has been delegated to DOD) to the following address:

[Insert name and address of appropriate NASA Center office.], unless the Contractor uses the NF

1018 Electronic Submission System (NESS) for report preparation and submission.

(c)(1) The annual reporting period shall be from October 1 of each year through September 30 of the following year. The report shall be submitted in time to be received by October 31st. The information contained in these reports is entered into the NASA accounting system to reflect current asset values for agency financial statement purposes. Therefore, it is essential that required reports be received no later than October 31st.

(2) Some activity may be estimated for the month in which the report is submitted, if necessary, to ensure the NF 1018 is received when due. However, contractors’ procedures must document the process for developing these estimates based on planned activity such as planned purchases or NASA Form 533 (NF 533) Contractor Financial Management Report) cost estimates. It should be supported and documented by historical experience or other corroborating evidence, and be retained in accordance with FAR Subpart 4.7, Contractor Records Retention. Contractors shall validate the reasonableness of the estimates and associated methodology by comparing them to the actual activity once that data is available, and adjust them accordingly. In addition, differences between the estimated cost and actual cost must be adjusted during the next reporting period. Contractors shall have formal policies and procedures, which address the validation of

NF 1018 data, including data from subcontractors, and the identification and timely reporting of errors. The objective of this validation is to ensure that information reported is accurate and in compliance with the NASA FAR Supplement. If errors are discovered on NF 1018 after submission, the contractor shall contact the cognizant NASA Center Industrial Property Officer

(IPO) within 30 days after discovery of the error to discuss corrective action.

(3) In addition to an annual report, if at any time during performance of the contract, NASA-owned property in the custody of the Contractor has a value of $10 million or more, the

Contractor shall also submit a report no later than the 21st of each month in accordance with the requirements of paragraph (c)(2) of this clause.

(4) The Contracting Officer may, in NASA’s interest, withhold payment until a reserve not http://www.hq.nasa.gov/office/procurement/regs/1845.htm https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%204_7.html https://nef.nasa.gov/

21 | P a g e exceeding $25,000 or 5 percent of the amount of the contract, whichever is less, has been set aside, if the Contractor fails to submit annual NF 1018 reports in accordance with NFS subpart

1845.71, any monthly report in accordance with (c)(3) of this clause, and any supplemental instructions for the current reporting period issued by NASA. Such reserve shall be withheld until the Contracting Officer has determined that NASA has received the required reports. The withholding of any amount or the subsequent payment thereof shall not be construed as a waiver of any Government right.

(d) A final report shall be submitted within 30 days after disposition of all property subject to reporting when the contract performance period is complete in accordance with paragraph (b)(1) through (3) of this clause.

G.6 1852.245-75 PROPERTY MANAGEMENT CHANGES (JAN 2011)

(a) The Contractor shall submit any changes to standards and practices used for management and control of Government property under this contract to the assigned property administrator prior to making the change whenever the change —

(1) Employs a standard that allows increase in thresholds or changes the timing for reporting loss, damage, or destruction of property;

(2) Alters physical inventory timing or procedures;

(3) Alters recordkeeping practices;

(4) Alters practices for recording the transport or delivery of Government property; or

(5) Alters practices for disposition of Government property.

G.7 1852.245-76 LIST OF GOVERNMENT PROPERTY FURNISHED PURSUANT TO

FAR 52.245-1 (JAN 2011)

For performance of work under this contract, the Government will make available Government property identified below or in Attachment [Insert attachment number or ‘‘not applicable’’] of this contract on a no charge-for-use basis pursuant to the clause at FAR 52.245-1, Government

Property, as incorporated in this contract. The Contractor shall use this property in the performance of this contract at [Insert applicable site(s) where property will be used] and at other location(s) as may be approved by the Contracting Officer. Under FAR 52.245-1, the Contractor is accountable for the identified property.

http://www.hq.nasa.gov/office/procurement/regs/1845.htm https://www.acquisition.gov/sites/default/files/current/far/html/52_245.html

22 | P a g e

Description

Acquisition

Date

Acquisition

Cost

Quantity

If equipment

Manufacturer

Model

Serial

Number

Operational

Thermostat

10/10/18 $771.84/ea 20 Sensata G311P641/05K060A075-

05-05-15

N/A

Survival

Thermostat

10/10/18 $771.84/ea 20 Sensata G311P641/05A050A065-

05-05-15

N/A

[END OF SECTION G]

18 | P a g e

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 SECTION H CLAUSES INCORPORATED BY REFERENCE

include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire

1852.223-75 MAJOR BREACH OF SAFETY OR SECURITY (FEB 2002)

1852.228-78 CROSS-WAIVER OF LIABILITY FOR SCIENCE OR SPACE EXPLORATION

ACTIVITIES UNRELATED TO THE INTERNATIONAL SPACE STATION (OCT

2012)

1852.235-73 FINAL SCIENTIFIC AND TECHNICAL REPORTS (DEC 2006) – ALT II (FEB 2003)

1852.224-70 GEOGRAPHIC PARTICIPATION IN THE AEROSPACE PROGRAM (APR 1985)

H.2 1852.225-70 EXPORT LICENSES (FEB 2000)

(a) The Contractor shall comply with all U.S. export control laws and regulations, including the International Traffic in Arms Regulations (ITAR), 22 CFR Parts 120 through 130, and the

Export Administration Regulations (EAR), 15 CFR Parts 730 through 799, in the performance of this contract. In the absence of available license exemptions/exceptions, the

Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at any NASA facility, where the foreign person will have access to export- controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

H.3 ADDITIONAL REPORTS OF WORK—RESEARCH AND DEVELOPMENT (FEB 2003)

In addition to the final report required under this contract, the Contractor shall submit the following report(s) to the Contracting Officer:

19 | P a g e

(a) Monthly progress reports. The Contractor shall submit separate monthly reports of all work accomplished during each month of contract performance. Reports shall be in narrative form, brief, and informal. They shall include a quantitative description of progress, an indication of any current problems that may impede performance, proposed corrective action, and a discussion of the work to be performed during the next monthly reporting period.

(b) Submission dates. Monthly reports shall be submitted by the 15th day of the month following the month being reported. If the contract is awarded beyond the middle of a month, the first monthly report shall cover the period from award until the end of the following month. The final report shall be submitted within 30 days after the completion of the effort under the contract.

H.4 GSFC 52.219-90 SMALL BUSINESS SUBCONTRACTING PLAN AND REPORTS

(NOV 2016)

a. Subcontracting Plan (Contractor)

FAR clause 52.219 9, "Small Business Subcontracting Plan", is included in this contract. The agreed to Subcontracting Plan required by the clause is included as an attachment to the contract.

b. Subcontracting Plan (Subcontractors)

In accordance with FAR clause 52.219 9 Small Business Subcontracting Plan, the Contractor must require that certain subcontractors adopt a plan similar to the Plan agreed to between the

Contractor and the Government.

c. Individual Subcontract Reports (ISRs)

The Contractor shall prepare and submit their Individual Subcontract Reports (ISRs) (formerly known as the Standard Form 294), in accordance with the instructions listed in the Electronic

Subcontract Reporting System (eSRS), available at http://esrs.gov.

ISRs must be submitted electronically in eSRS on a semi-annual basis. This report must be received no later than April 30 and October 30 each year for the reporting periods ending March

31 and September 30, respectively. Reports are required when due, regardless of whether there has been any subcontracting activity since the inception of the contract or since the last reporting period. A final ISR must be submitted after contract completion. The final ISR submittal must be received no later than the due date for what would have been the next semi-annual report.

d. Summary Subcontract Reports (SSRs)

The Contractor shall prepare and submit Summary Subcontract Reports (SSRs) (formerly known as the Standard Form 295), in accordance with the instructions listed in the eSRS, available at http://esrs.gov and in accordance with FAR clause 52.219-9 Small Business Subcontracting Plan of this contract.

20 | P a g e

The SSRs must be submitted electronically in eSRS on an annual basis. This report must be submitted no later than October 30 each year for the twelve month period ending September 30.

e. Subcontractor Reporting

FAR clause 52.219 9 Small Business Subcontracting Plan requires that the Contractor ensure that

ISR and SSR reports are submitted by those subcontractors that have been required to adopt a

Subcontracting Plan under the terms of the clause. These subcontractor reports must be submitted as required by paragraphs (c) and (d) above. The reports may be submitted through the Contractor or submitted directly. Regardless, the Contractor is responsible for ensuring proper and timely submittal of the required reports.

H.5 GSFC 52.227-93 APPLICABILITY OF RIGHTS IN DATA – SPECIAL WORKS

(MAR 2008)

The "Rights in Data - Special Works" clause of this contract applies to the following aspects (or items):

Any data requested by the Government for any legitimate government use.

H.6 GSFC 52.227-99 RIGHTS IN DATA (JUN 2012)

The default Data Rights clause under this contract is FAR 52.227-14 RIGHTS IN DATA-

GENERAL— Alternate II and Alternate III as modified by NASA FAR Supplement

1852.227-14 and GSFC 52.227-90. Any exceptions to this clause will be covered by FAR

52.227-17 RIGHTS IN DATA--SPECIAL WORKS as modified by NASA FAR Supplement

1852.227-17, if applicable, and GSFC 52.227-93.

H.7 GSFC 52.243-91 LAUNCH DELAYS (FEB 1991)

The delivery schedule and/or period of performance of this contract is based upon a spacecraft launch date of August 2022. In the event of a Government directed delay of the launch date, the Contracting Officer may inform the Contractor, in writing, of the revised launch date, and allow the Contractor to submit a proposal for the effect of this delay on the cost, delivery schedule, or other terms of the contract. This may result in an equitable adjustment to the estimated cost, fee(s), if any, and delivery schedule or period of performance. Failure to agree to and adjustment shall be considered as a dispute under the Disputes clause. However, nothing in this clause shall excuse the Contractor from proceeding with the contract as extended.

21 | P a g e

[END OF SECTION H]

22 | P a g e

SECTION I - CONTRACT CLAUSES

I.1 SECTION I CLAUSES INCORPORATED BY REFERENCE

The Clauses below are incorporated by reference, with the same force and effect as if they were include the text of the affected paragraph(s) only. This does not limit the clause to the affected paragraph(s). The Contractor is responsible for understanding and complying with the entire

52.202-1 DEFINTIONS (NOV 2013)

52.203-3 GRATUITIES (APR 1984)

52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP

2006)

52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR

IMPROPER ACTIVITY (MAY 2014)

52.203-10 PRICE OF FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY

2014)

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL

TRANSACTIONS (OCT 2010)

52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (OCT 2015)

52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY

AGREEMENTS OR STATEMENTS (JAN 2017)

52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT

PAPER (MAY 2011)

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT

AWARDS (OCT 2016)

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2016)

52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2016)

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND

CERTIFICATIONS (DEC 2014)

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL (JAN 2017)

52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING

WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR

DEBARMENT (OCT 2015)

52.209-9 UPDATES ON PUBLICLY AVAILABLE INFORMATION REGARDING

RESPONSIBILITY MATTERS (JUL 2013)

52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC

CORPORATIONS (NOV 2015)

52.211-5 MATERIAL REQUIREMENTS (AUG 2000)

52.215-2 AUDIT AND RECORDS—NEGOTIATION (OCT 2010)

52.215-8 ORDER OF PRECEDENCE—UNIFORM CONTRACT FORMAT (OCT 1997)

52.215-14 INTEGRITY OF UNIT PRICES (OCT 2010)

52.215-17 WAIVER OF FACILITIES CAPITAL COST OF MONEY (OCT 1997)

52.217-2 CANCELLATION UNDER MULTI-YEAR CONTRACTS (OCT 1997)

52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL

BUSINESS CONCERNS (OCT 2014)

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)

52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN (JAN 2017)

52.219-16 LIQUIDATED DAMAGES—SUBCONTRACTING PLAN (JAN 1999)

52.222-1 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)

23 | P a g e

52.222-3 CONVICT LABOR (JUN 2003)

52.222-19 CHILD LABOR—COOPERATION WITH AUTHORITIES AND REMEDIES (JAN

2018)

52.222-20 CONTRACTS FOR MATERIALS, SUPPLIES, ARTICLES, AND EQUIPMENT

EXCEEDING $15,000 (MAY 2014)

52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)

52.222-26 EQUAL OPPORTUNITY (SEP 2016)

52.222-37 EMPLOYMENT REPORTS ON VETERANS (FEB 2016)

52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR

RELATIONS ACT (DEC 2010)

52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015)

52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)

52.223-6 DRUG-FREE WORKPLACE (MAY 2001)

52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE

DRIVING (AUG 2011)

52.225-1 BUY AMERICAN —SUPPLIES (MAY 2014)

52.225-8 DUTY-FREE ENTRY (OCT 2010)

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)

52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)

52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT

INFRINGEMENT (DEC 2007)

52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013) FEDERAL, STATE, AND

LOCAL TAXES (FEB 2013)

52.232-1 PAYMENTS (APR 1984)

52.232-8 DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)

52.232-11 EXTRAS (APR 1984)

52.232-17 INTEREST (MAY 2014)

52.232-18 AVAILABILITY OF FUNDS (APR 1984)

52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)

52.232-25 PROMPT PAYMENT (JAN 2017)

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD

MANAGEMENT (JUL 2013)

52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)

52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS

CONTRACTORS (DEC 2013)

52.233-1 DISPUTES (MAY 2014)

52.233-3 PROTEST AFTER AWARD (AUG 1996)

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

52.24…