About this file

This document outlines rework and repair procedures for nonconforming materials on federal contracts. It defines rework as reprocessing material to fully conform to requirements, while repair reduces but does not eliminate nonconformance. Contractors must document rework procedures and submit them to the Government Quality Assurance Representative for review before using. Repair procedures require submission on a Request for Deviation/Waiver form to the Contracting Officer for written approval. Submissions for review must include a description of the nonconformance cause and actions to prevent recurrence. Reworked or repaired items must pass reinspection according to a procedure ensuring government assurance of meeting reprocessing standards. These requirements flow down to all contractors, suppliers, vendors and subcontractors.

The related federal contract opportunity is a solicitation from the Department of the Air Force Materiel Command Lifecycle Management Center for C-17 and F-15 remanufacturing services under solicitation number FA821323R3024.

View the file

Other files for this federal contract opportunity

Other files attached to C-17 & F-15 Reman, newest first.
File Type Posted
6 CDRLS.pdf PDF
3 SOW Packaging.pdf PDF
9 Item Description 016457398.pdf PDF
10 CPM Original SPREADSHEET.xlsx XLSX spreadsheet
Solicitation.pdf PDF
4 CADPAD Item Marking Instruction - Ver 1.6.pdf PDF
5 SPI 001383770.pdf PDF
2 Reship.pdf PDF
9 Item Description 015601520.pdf PDF
5 SPI 013820650.pdf PDF
1 SOWAppendixA.pdf PDF
7 GFP Form.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 5

(ES7034)

REWORK AND REPAIR OF NONCONFORMING MATERIAL

Jan 2012 (version)

(a) Rework and Repair are defined as follows:

(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.

(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.

(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.

(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.

(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.

(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.

(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.

(End of clause)