Attach 5 Measurement and Payment Hansville.pdf

PDF 138 KB Posted

Attached to
Septic for 2 Port Gamble Homes Federal contract opportunity
Solicitation number
75H70121Q00048
Issued by
Department of Health and Human Services Indian Health Service

View the file

Other files for this federal contract opportunity

Other files attached to Septic for 2 Port Gamble Homes, newest first.
File Type Posted
Attach 1 Aerials.pdf PDF
B01 75H70121P00048.pdf PDF
Attach 3 IHS Technical Provisions.pdf PDF
Attach 6 Wage Determination WA20210071.pdf PDF
Attach 4 Bid schedule.xlsx XLSX spreadsheet
Attach 2 Septic Design Hansville Road.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEASUREMENT AND PAYMENT FOR BID SCHEDULE

LINE ITEMS

MOBILIZATION AND DEMOBILIZATION

Payment for transportation of equipment, material, and personnel to and from the job site location (regardless of trips required), all required permits and fees, taxes, and all other necessary items to complete the work.

4” SOLID SEWER PIPE

Payment for solid sewer pipe as specified on the Design shall be made for the size of pipe listed based on the number of linear feet installed. Payment shall include excavation, backfill and compaction; all pipe and fittings; connection of the solid sewer pipe to an existing sewer service line or home; testing; resurfacing trenched areas to equal or better condition than existing; and all other necessary items for a complete and operational installation.

UNDERGROUND CLEANOUT (DOUBLESWEEP)

Payment for the underground cleanout as specified on the Design shall be made for the number of underground cleanouts installed. Payment shall include excavation, backfilling and compaction, all pipe and fittings, and all other necessary items for a complete and operational installation. No payment shall be made for cleanouts installed above grade as part of the connection to existing house, or as part of drop manholes.

1,000 GALLON TWO-COMPARTMENT CONCRETE TRASH TANK

Payment for the septic tank, as specified in the Design, shall be made at the contract unit price for the size listed based on the number of tanks installed. Compensation shall include payment for excavation, backfilling and compaction, sand or gravel where non-uniform native soil or groundwater is present, septic tank, baffles, two access risers and lids, testing, installing all piping, waterproofing, valves and fittings in the tank; testing; and all other necessary items for a complete and operational installation.

2,000 GALLON PUMP TANK

Payment for pump tanks shall be made at the contract unit price based on the number of complete pump tanks installed. Compensation shall include payment for excavation, backfilling and compaction, pump tank, basin, effluent pump, pump tank piping, valves and fittings, floats, conduit, fused disconnect (when required), electrical controls and alarm, lid and riser, mechanical level control switches, electrical and control cable, installing all piping, waterproofing, valves and fittings in the tank; testing; and all other necessary items for a complete and operational installation.

2” PVC SEWER FORCE MAIN

Payment for sewer force main pipe connections from the pump chamber to the drainfield manifold shall be made at the contract unit price for the sizes of pipe listed based on the number of linear feet installed. Compensation shall include payment for excavation, backfilling, pipe and fittings, connections, and all other necessary items for a complete and operational installation.

SAND BED GRAVELLESS CHAMBER UNIT DRAINFIELD

Payment for gravelless infiltrator chamber drainfield shall be made at the contract unit price for the width of chamber units listed based on the number of linear feet installed.

Compensation shall include payment for excavation, backfilling and compaction, manifold, valve box, chamber units and fittings, connections, , drainfield filter fabric, manifold pipe, distribution laterals, observation ports, end caps, inspection risers, excavation, distribution boxes, imported sand, pressurized flow testing, backfilling, final grading, and all other necessary items needed for a complete and operational installation.