KIMBALL CAT SOW 23127.docx

DOCX document 25 KB Posted

Attached to
#2 and #3 SSDG Load Bank Federal contract opportunity
Solicitation number
70Z08524P739
Issued by
Department of Homeland Security US Coast Guard

About this file

This scope of work document outlines alignment, pinning and load bank testing services required for two shipboard diesel generators aboard the USCGC KIMBALL. The contractor will provide technical support and proprietary tools for engine-generator alignment, load bank equipment and cabling, and conduct a load bank test on generator #2 and an alignment, pinning and load bank test on generator #3. The generators are rated at 1360 KW, 450 Volt AC, 3 Phase, 60 Hz. Load bank testing will include load levels of 25%, 50%, 75% and 100% applied over specified durations. The period of performance for the work is January 15-29, 2024 aboard the vessel at its homeport. The related federal contract opportunity on the Department of Homeland Security's US Coast Guard website is solicitation number 70Z08524P739 for load bank services on generators #2 and #3. Ship force will provide machinery operation support and points of contact are provided.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work: CGC KIMBALL Perform alignment, pinning and load bank on #2 and #3 SSDG

POP: 15 JAN 2024 – 29 JAN 2024

Location: USCGC KIMBALL 400 Sand Island Pkwy Sand Island, HI

Background: #2 SSDG Non-drive end bearing and #3 SSDG drive end bearing and non-drive end bearings were replaced and requires alignment and load bank testing to prove the bearing.

Summary: CTR to provide the requested service Ships force will provide personnel to operate machinery

Statement of Work:

CTR will provide:

· Provide technical support for engine-generator alignment, including shims, drilling and pinning alignment holes

· Provide all load bank equipment and cabling and technical support for hooking and un-hooking cables to switchboards

· Provide all proprietary tools and software

· Make any adjustments/repairs

· Submit CFR for any additional parts or labor hours

· Conduct load bank on #2 gen. and an alignment, pinning and load bank on #3 gen.

· Generator rating is: 1360 KW, 450 Volt AC, 3 Phase, 60 Hz Load Bank .08pf 2.5 Hour test.

· 25% 30 min

· 50% 30 Min

· 75% 30 Min

· 100% 60 Min

Gov. Furnished Equipment:

· N/A

Ship Contacts:

LCDR Spencer Ross, Engineer Officer Spencer.E.Ross@uscg.mil

Asset Manager MKCM Andrew Rothdeutsch Andrew.C.Rothdeutsch@uscg.mil

File details come from the government source that posted it. Updated .