#1 MGT LAGGING
USCGC JOHN MIDGETT
1. Background.
1.1. Due to multiple MGT casualties and subsequent extensive repairs, CGC JOHN MIDGETT requires newly fabricated lagging on the #1 Main Gas Turbine prior to operating. USCG does not have comprehensive drawings and specs for MGT lagging.
2. Tasks.
2.1. Contractor to provide the following:
2.1.1. Exhaust Blankets from Turbine Enclosure Box to elephant trunk.
Measure & Fabricate new exhaust blankets.
Materials to match existing materials. Expected material is, 2-inch Fiberglass High Temp Mat, Silicon impregnated Fiberglass Cloth, Stainless Steel Mesh, Stainless Steel attachments.
2.2. Shipping to Seattle
2.2.1. Contractor to provide shipping to Coast Guard Base Seattle. Shipping shall be expedited and fastest means available shall be used.
2.3. Site visit required to measure and obtain specifications for requested MGT lagging
2.3.1. CG does not have adequate drawings and dimensions to allow a detailed specification to be provided.
2.3.2. If travel is required for site visit, contractor must provide estimated travel costs with quote.
3. Government furnished property. N/A
4. Place of performance- Cutter's home pier, Seattle, WA.
5. Period of performance- Delivery of fabricated blankets by (at latest) 30 SEP