Amendment 3 Page 2 of 2.pdf
PDF 44 KB Posted
- Attached to
- CGC ALERT DD FY21 Federal contract opportunity
- Solicitation number
- 70Z080-21-Q-P45C3200
About this file
This document contains responses to questions regarding an amendment to a solicitation for drydock repairs of the CGC ALERT. The solicitation requests drydocking of the vessel from June 9 to June 22, 2021 to perform specified rudder repairs and sea trials. While seven day work weeks and an extended period of performance to eighteen working days were requested, the Coast Guard declined both requests and will not revise the start date. The earliest available drydock slot is June 19, which was also declined. The solicitation number is 70Z080-21-Q-P45C3200 and is issued by the Department of Homeland Security United States Coast Guard for drydocking of the CGC ALERT from June 9 to June 22, 2021. Repairs are to be performed at the drydock facility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 4 Page 1 of 1.pdf | ||
| Amendment 2 Page 1 of 1.pdf | ||
| Amendment 3 Page 1 of 2.pdf | ||
| Amendment 1 Page 2 of 2.pdf | ||
| Amendment 1 Page 1 of 2.pdf | ||
| Attachment 1-Schedule of Services -Blank Price Schedule.pdf | ||
| Attachment 1-Schedule of Services -Blank Price Schedule.xls | XLS spreadsheet | |
| Attachment 1-Schedule of Services -Blank Price Schedule.xls | XLS spreadsheet | |
| 70Z080-21-Q-P45C3200.pdf | ||
| Attachment 2-Statement of Work -Specification.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question:
1. Contractor experience (and preliminary critical path scheduling) suggests that a minimum of eighteen (18) working days are required to drydock the vessel, perform all of the specified rudder repairs and then perform sea trials.
a. Does the USCG intend to have repairs performed on a seven (7) day per week basis? yes
b. Will the USCG expand the Period of Performance to allow an eighteen (18) working day duration. Not at this time
2. Existing drydock commitments do not allow drydocking of the vessel on or about 6/9/21. The earliest drydock availability appears to be Saturday June 19th,
a. Will the USCG revise the start date for the Period of Performance to June 19th or later? Not at this time
Answer:
1a. Yes
1b. Not at this time.
2a. Not at this time.