Amendment 1.pdf

PDF 114 KB Posted

Attached to
Dockside (DS): USCGC RESOLUTE Depot Maintenance Federal contract opportunity
Solicitation number
70Z080-21-Q-P45B3700
Issued by
Department of Homeland Security US Coast Guard

About this file

This document contains an amendment to a solicitation for depot maintenance repairs on the USCGC RESOLUTE. Amendment 1 extends the solicitation response date from May 11 to May 14, 2021. The amendment also provides answers to three questions from potential offerors. Question 1 confirms the work includes replacing one 60Hz circuit breaker and pulling and re-running a new power cable for two specified areas. Question 2 verifies Rydlyme can be used for the work. Question 3 clarifies the additional cable footage runs up to 110 feet in the specified engineer's office and overhead passageway.

View the file

Other files for this federal contract opportunity

Other files attached to Dockside (DS): USCGC RESOLUTE Depot Maintenance, newest first.
File Type Posted
Attachment 1 RESOLUTE (WMEC 210B) DS Spec.pdf PDF
RFQ SHIP REPAIR COMBINED SYNOPSIS.pdf PDF
RFQ Attachment 2 Schedule of prices.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC RESOLUTE DS FY21

Solicitation # 70Z080-21-Q-P45B3700

Amendment # 1

Solicitation extension:

This solicitation has been extended for three (3) calendar days from 11 May to 14 May 2021.

Questions/Answers:

1Q. Does this work item describes the requirements for the Contractor to replace a designated 60HZ circuit breaker and power cable for the Air Conditioning Plant System located in Main Control Booth (2- 136-0-C) and Sewage Disposal Room (4-84-0-E)?

A. Yes, 1 breaker replaced and 1 cable pulled and re-run a new one.

2. Is it acceptable for the contractor to use Rydlyme?

A. Yes, Rydlyme can be used.

3. Is this meant to be 10'? Or does the additional footage go beyond the Engineering office into other spaces in the engine room?

A. Yes, up to 110’ however, the location is in the engineer office and the space outside of the engineer office, and in the overhead in 2-140-0-L passageway.