Question_&_Answers_Amendment_00001.pdf

PDF 60 KB Posted

Attached to
CGC SPENCER DD Federal contract opportunity
Solicitation number
70Z080-20-Q-P4501700
Issued by
Department of Homeland Security US Coast Guard

About this file

Questions & Answers

View the file

Other files for this federal contract opportunity

Other files attached to CGC SPENCER DD, newest first.
File Type Posted
Question_&_Answers_Amendment_00002.pdf PDF
Amendment_00002.pdf PDF
Amendment_00001.pdf PDF
USCG_OMBUDSMAN_LETTER.pdf PDF
70Z080-20-Q-P4501700.pdf PDF
CGC_SPENCER_DD_SECTION_B.xls XLS spreadsheet
CGC_SPENCER_PAST_PERFORMANCE_INFORMATION_FORM.doc DOC document
CGC_SPENCER_DD_WORK_SPECIFICATION.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Question:

Work item as written does not require removal and reinstallation of propellor shafts.

Paragraph 3.3 refers to the Government's right for changing out propeller shaft(s).

Is contractor to include costs for removal and reinstallation of propeller shafts in submitted offer?

Answer :

The bid should NOT include removing and reinstalling the shaft. If this is needed, a Change Request will be submitted.

2. Question :

Contractor requests an extension of the due date until October 11, 2019.

Answer:

No, the due date is 30 September 19 at 10:00AM EST.