KISKA_(WPB_110B)_DS_FQ3_LKT_19R0.pdf

PDF 801 KB Posted

Attached to
CGC KISKA Dockside Federal contract opportunity
Solicitation number
70Z080-19-Q-P45T6500A
Issued by
Department of Homeland Security US Coast Guard

About this file

Specification for Dockside Repairs

View the file

Other files for this federal contract opportunity

Other files attached to CGC KISKA Dockside, newest first.
File Type Posted
Kiska_Dockside_Combined_Synopsis_Solicitation.pdf PDF
Schedule.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC KISKA (WPB 1336)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2019

Developed By: Lindsay K Taylor

(Rev-0, 21 September 2018)

USCGC KISKA (WPB-110B) DOCKSIDE AVAILABILITY FY2019

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .................................................................................. v Consolidated List of Critical Inspection Items ............................................................................................. vi Principal Characteristics ............................................................................................................................. vii General Requirements WORK ITEM 1: Deck Covering System in Galley and Mess Deck, Renew WORK ITEM 2: Deck Covering, (Carpeting), Renew (CSMP 2018004) WORK ITEM 3: Hull Plating, Structural Repairs, (CSMP 2018002) WORK ITEM 4: Tanks (MP Fuel Service), Clean And Inspect WORK ITEM 5: Ultrasonic Thickness Measurements, Perform iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 110B WPB 085-001, Rev A, Tank Capacity Curves

Coast Guard Drawing 110B WPB 085-012, Rev A, Booklet of General Drawings (Supersedes 110B-

WPB-085-7)

Coast Guard Drawing 110B WPB 111-003, Rev H, Shell Expansion

Coast Guard Drawing 110B WPB 113-001, Rev K, Inner Bottom Plating

Coast Guard Drawing 110B WPB 117-001, Rev H, Transverse Sections (Frames 0 thru 4)

Coast Guard Drawing 110B WPB 121-001, Rev D, Longitudinal Bulkheads

Coast Guard Drawing 110C WPB 085-007, Rev B; Booklet of Gen Drawings (List of Particulars)

Coast Guard Drawing 110-WPB-634-001, Rev-D, Floating Deck Replacement with Sound Abatement

Coating

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior

Deck Covering Systems

OTHER REFERENCES

ASTM International (ASTM) E797, 2010, Standard Practice for Measuring Thickness by Manual

Ultrasonic Pulse-Echo Contact Method

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of

Reliability Is Required

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; For Aromatic Fuel and Oil Resistant Gaskets v (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

This section is not applicable to this package.

vi (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

1 Deck Covering System in Galley and Mess Deck, Renew

5 Ultrasonic Thickness Measurements, Perform vii (Rev-0)

PRINCIPAL CHARACTERISTICS

110’ WPB (B-CLASS)

PHYSICAL

Length overall 110' 0" or 113' if stern flap present

Length between perpendiculars 104' 1/2"

Depth 10' 1/2"

Beam, molded 21' 3"

Depth, molded N/A

Full load draft 6' 5-3/4"

Height of highest projection 55'

Full load displacement 165 long tons

Anchor 150 lb Danforth with 450 ft. 3" nylon rope

Shore tie voltage requirements 450VAC 400A 3PH, 60Hz ungrounded

HULL

Hull BS-4360, GR 43A Steel

Main weatherdeck & superstructure 5086 Aluminum Alloy

Frame spacing Various

Bulkheads Seven watertight transverse

Fin stabilizers Frame 22-1/2

MACHINERY

Main propulsion Two Paxman Type 16 RP200M (Valenta) V-16 Diesel; 2880 BHP each @ 1500

RPM (max)

Reduction gears Two ZF Model BW 1500 reversible reduction gearboxes; 1.839:1 ratio

Number of propellers 2

Number of blades 5

Diameter of propeller 49.6"

Pitch 61.4"

Rpm N/A

Shaft AQUAMET 17

Shaft diameter 4"

Shaft seal Johnson Duramax split face seal

Shaft bearings Rubber Cutless or Thordon

Rudders Twin underslung type, 5 sq ft each

Ship's service generators Two Caterpillar Type 3304BT diesel; 99KW, 460V, 60Hz, 3-phase, 3-wire @ 1800

RPM

TANK

Fuel oil (95%) 9,306 gal.

Fresh water (100%) 940 gal.

Lubricating oil (95%) 109 gal.

1 (Rev-0)

00000_0618_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec

0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC

Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be

3 (Rev-0) followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved

4 (Rev-0) changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing

Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.2.2 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of

SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

8 (Rev-0)

TIME

9 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

12 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

13 (Rev-0)

63400_RJL_0714_110_WPB (A & B Class)

WORK ITEM 1: Deck Covering System in Galley and Mess Deck, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to install sound abatement deck covering system in the galley and mess deck area.

1.2 Government-furnished property.

None

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 110-WPB-634-001, Rev-D, Floating Deck Replacement with

Sound Abatement Coating

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems

OTHER REFERENCES

ASTM International (ASTM) E797, 2010, Standard Practice for Measuring Thickness by

Manual Ultrasonic Pulse-Echo Contact Method

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

14 (Rev-0)

3.3 Inspections.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below listed:

Dishwasher.

Sink.

Stove/range.

Refrigerator/freezer.

Trash compactor.

Hot water heaters.

Cabinet & drawer assemblies.

Mess deck tables & benches.

Fire extinguishers.

Entertainment center.

All associated mounting stanchions, brackets and hardware

False bulkheads and panels.

Doors.

Diesel Fuel Tank 3-17-1-F (2560-gallon capacity)

Diesel Fuel Tank 3-17-2-F (2560-gallon capacity)

Diesel Fuel Tank 3-18-0-F (1480-gallon capacity)

Sewage Tank 3-17-0-K (550 gallon capacity)

CAUTION!

The Contractor shall be aware that fuel tanks are located directly beneath this deck.

3.1.4.1 Fluid handling. Handling of fuel in the affected tanks is addressed under a separate work item.

3.2 Removals. The Contractor shall completely remove the existing floating deck system

(including deck covering, coating system, honey comb panels, isolation pads, and deck insulation materials), to expose the deck/tank top surfaces in the Galley and Mess Deck areas, including deck areas under the stove and cabinets.

15 (Rev-0)

3.3 Inspections. After surface preparation and before surface coating, the Contractor shall conduct the following inspections (Submit CIR):

3.3.1 Visually inspect the following surfaces:

Exposed deck/tank top surfaces.

Bulkhead and deck surfaces in way of the range.

Range exterior metal casing.

Bulkhead and decking behind the sink and dishwasher.

Refrigerator and freezer foundations.

3.3.2 Ultrasonic thickness measurements. Perform a total of 20 thickness measurements of deck/tank top surfaces, in locations designated by the Coast Guard Inspector. (Submit CIR).

Additional measurements may be required by activation of WI 6. The ultrasonic apparatus, procedure requirements, and report shall be in accordance with ASTM E797. The report results shall additionally include, for each test point:

Location.

Design metal thickness.

Measured metal thickness.

Percent deterioration (calculation is based on the original metal thickness).

3.4 Installation and renewals. The Contractor shall modify the following IAW Coast Guard

Drawing 110-WPB-634-001and SFLC Std Spec 0740:

Foundations for cabinets, tables, benches and appliances (reinstalled seating or work surface height from deck shall be the same as previous installation)

False bulkhead mountings

Manholes and covers

3.4.1 Hardware renewals: The Contractor shall renew 100% fasteners, nylon insert/nylock nuts and washers.

NOTE

Foundations for the stoves, cabinets and other interferences require modification to accommodate this new decking system. This system is much more compressed and will result in an approximate two inch difference in height from previous one step deck covering system once installed.

3.5 Deck Coating System Installation. The Contractor shall install the new decking system IAW

Coast Guard Drawing 110-WPB-634-001:

Prepare and coat the exposed deck/tank top surfaces; use the coating system specified for “Metal Decks-in preparation for application of deck coverings”, in

SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems).

Apply 160 mils of sound abatement coating to all exposed tank top/deck

(approximately 260 ft²) including aluminum man hole cover plates. Comply with manufacturers’ application standards and timeline to ensure proper application between coatings.

16 (Rev-0)

Install underlayment between the sound abatement coating and deck covering.

Install a cosmetic polymeric deck covering system, in accordance with Std Spec

6341_STD, Appendix A, “Type III (Single Step – Epoxy Only). Additionally, application shall extend six inches up all adjacent vertical steel bulkheads and side shell plate surfaces.

3.6 Touch-up preservation. The Contractor shall prepare and coat all other new and disturbed exterior and interior surfaces to match existing adjacent surfaces, SFLC Std Spec 6310 and SFLC

Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).

4. NOTES

This section is not applicable to this work item.

17 (Rev-0)

S18_004_63410_ENV_0618_1336

WORK ITEM 2: Deck Covering, (Carpeting), Renew (CSMP 2018004)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the interior deck covering system (carpeting) in Forward Berthing (1-13-0-L), Aft Berthing (2-29-1-L), CPO

Berthing (2-13-1-L), XO Berthing (1-20-0-L) and CO Berthing (1-19-0-L).

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

18 (Rev-0)

Not applicable.

3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

Lockers.

Racks.

3.2 Deck covering renewal. The Contractor shall perform all tasks specified in SFLC Std Spec

6341, and Appendix E (Carpeting), to install a new deck covering system in the location(s) specified in Table I below.

TABLE I - DECKING SYSTEM PARTICULARS

LOCATION

AREA

(*SQFT)

DECK

MTL

(A/S**)

SYSTEM/APPENDIX

(SFLC STD SPEC

6341)

SYSTEM

COLOR

UNDERLAYMENT

REQUIREMENT

1-13-0-L 80 S Carpeting, Single Loop

Pile,Appendix E

As designated by

COR

New: _X_

Retain Existing:__

Insulating:_X_

None:__

2-29-1-L 144 S Carpeting, Single Loop

Pile,Appendix E

As designated by

COR

New: _X_

Retain Existing:__

Insulating:_X_

None:__

2-13-1-L 60 S Carpeting, Single Loop

Pile,Appendix E

As designated by

COR

New: _X_

Retain Existing:__

Insulating:_X_

None:__

1-20-0-L 45 S Carpeting, Single Loop

Pile,Appendix E

As designated by

COR

New: _X_

Retain Existing:__

Insulating:_X_

None:__

1-19-0-L 45 S Carpeting, Single Loop

Pile,Appendix E

As designated by

COR

New: _X_

Retain Existing:__

Insulating:_X_

None:__ *Approximated.

**Note: A = Aluminum; S = Steel.

***See SFLC Std Spec 6341 for definition of cove base.

3.3 Visual inspection. After surface preparation, the Contractor shall visually inspect the exposed deck top surfaces for metal fatigue, corrosion, and all other irregularities. Submit CFR.

19 (Rev-0)

3.4 Ultrasonic thickness (UT) measurement. The Contractor shall take a total of 20 UT measurements in accordance with SFLC Std Spec 0740, Appendix C in locations designated by the Coast Guard Inspector. Additional measurements may be required by activation of WI 6.

Submit a CFR.

3.5 Carpeting requirements. The Contractor shall procure carpeting of the following construction type, for installation:

"Single Cut Pile (52 Oz. Per Sq. Yd. Pile)"

4. NOTES

4.1 Sources for carpeting procurement. Carpeting meeting the requirements specified in SFLC

Std Spec 6341, Appendix E may be procured from the following sources:

NAME CONTACT INFORMATION

Marine Carpet Sales

803-254-9970 http://www.marinecarpetsales.com/marine-carpet-products.cfm

Continental Flooring Company (800) 825-1221; (410) 750-2614

Don Freeman (410) 336.2403

Fleming and Sheely (410) 483-5350

Professional Carpet Sales and Interiors (800) 845-6106 http://www.marinecarpetsales.com/marine-carpet-products.cfm http://www.marinecarpetsales.com/marine-carpet-products.cfm

20 (Rev-0)

S18_002_11000_ENV_0618_1336

WORK ITEM 3: Hull Plating, Structural Repairs, (CSMP 2018002)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform hull structural repairs in Compartment (2-8-0-V).

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 110B WPB 111-003, Rev H, Shell Expansion

Coast Guard Drawing 110C WPB 085-007, Rev B; Booklet of Gen Drawings (List of

Particulars)

Coast Guard Drawing 110B WPB 117-001, Rev H, Transverse Sections (Frames 0 thru

4)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

21 (Rev-0)

None.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the

Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences).

Shelves (2-11-0-L)

Stiffener

3.2 Structural repairs. The Contractor shall renew approximately one square feet of structural plating in accordance with in SFLC Std Spec 0740. Repairs are on the port side of the

Compartment (2-8-0-V) near the aft bulkhead two inches above the deck and one inch away from the skin of the ship. Refer to Coast Guard Drawings 110C WPB 085-007, 110B WPB 111-003 and 110B WPB 117-001 for guidance.

3.3 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13

(Touch-ups and minor coating repairs.)

This section is not applicable to this work item.

22 (Rev-0)

12305_0917_FLT

WORK ITEM 4: Tanks (MP Fuel Service), Clean And Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

TABLE 1 - FUEL SERVICE TANKS

TYPE OF TANK LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION (GALLONS)

Diesel Fuel* 3-17-0-F 2,560 74

Diesel Fuel* 3-17-1-F 1,162 37

Diesel Fuel* 3-17-2-F 1,162 37

*Due to the complex geometrical shape and hard accessibility, it is very difficult to perform thorough visual inspection of these tanks. Tanks are baffled and cannot be fully cleaned by hand.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 110B WPB 085-001, Rev A, Tank Capacity Curves

Coast Guard Drawing 110B WPB 085-012, Rev A, Booklet of General Drawings

(Supersedes 110B-WPB-085-7)

Coast Guard Drawing 110B WPB 113-001, Rev K, Inner Bottom Plating

Coast Guard Drawing 110B WPB 117-001, Rev H, Transverse Sections (Frames 0 thru

4)

Coast Guard Drawing 110B WPB 121-001, Rev D, Longitudinal Bulkheads

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

23 (Rev-0)

OTHER REFERENCES

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS)

C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel and Oil

Resistant Gaskets

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High

Degree of Reliability Is Required

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

Fuel

Piping

Tank access cover

3.1.4.1 The Contractor shall remove up to a total of 3,000 gallons of fuel. Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.1.4.2Arrange to test and stow all fluids at NAVSUP Fleet Logistics Center Yokosuka, site

Marianas, Guam, and re-stow all tank contents upon completion of work. Contractor shall ensure fuel quality is maintained throughout all stages of the process. Contractor is to provide transportation conforming to NAVSUP Fleet Logistics Center Requirements.

NOTE

Vessel may come in with less tank fluid contents than specified above.

24 (Rev-0)

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast

Guard Personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1

(Intent), to demonstrate existing operational condition. Submit a CFR.

3.3 Plug log. The Contractor shall keep a written record of all plugs put in any tanks vents. A separate list shall be kept for each tank being entered.

3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

NOTE

Initial and post repair operational tests apply only to tanks that possess TLIs.

3.4 Cleaning requirements. The Contractor shall remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media;

and wipe up residual moisture with clean lint-free cloths. The Contractor shall refer to Coast

Guard Drawings 110B WPB 085-001, 110B WPB 085-012, 110B WPB 113-001, 110B WPB

117-001 and 110B WPB 121-001 for guidance.

3.5 Tank content and waste disposal. The Contractor shall dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.6 Inspection. The Contractor shall accomplish the following tasks:

3.6.1 Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:

Tank structural condition.

Inaccessible areas.

Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (if tank interior surfaces are coated).

Tank level indicator (TLI) and/or float switch condition, as applicable.

Sounding/vent tube and striker plate condition.

Suction and discharge piping condition.

Fastener material and condition (correct fastener material is stainless steel).

25 (Rev-0)

3.6.2 Measure up to 10 “pits” within each tank as designated by the Coast Guard Inspector using a Contractor supplied ‘Pit Gauge’. Include pit measurement results in CFR specified above, showing where pit measurements were taken and the depth of the pit.

3.7 Tank closing. The Contractor shall ensure that the tank(s) remain open for at least 24 hours after completion of any KO-authorized repair and preservation procedures. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard

Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183. Chase threads on studs to ensure even installation of the access covers. Renew all fasteners and Nylock hex nuts.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.8 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all designated tank TLI’s to be in satisfactory operating condition. Submit a CFR.

26 (Rev-0)

11000_ENV_0918_110WPB

WORK ITEM 5: Ultrasonic Thickness Measurements, Perform

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform up to 20 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor

27 (Rev-0) shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std

Spec 0000, paragraph 3.3.5 (Interferences).

3.1.4.1 If UT measurements cannot be obtained due to interferences, the Contractor shall submit a CFR that details all necessary interference removal/reinstallation work.

3.1.4.2 After the KO has released a CR, remove the interferences and reinstall after completion of associated work.

3.2 UT measurements. The Contractor shall perform up to 20 UT measurements in locations designated by the Coast Guard Inspector in accordance with SFLC Std Spec 0740, Appendix C.

Submit a CIR.

3.2.1 The Contractor shall create a sketch to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item.

3.2.2 The Contractor shall provide a detailed sketch showing the UT measurements/locations and complete Table 1 and provide in the CFR. The CFR shall itemize all areas requiring repairs along with repair recommendations, including complete work scope proposal, for each area.

28 (Rev-0)

TABLE 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT

PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE

File details come from the government source that posted it.