Attachment 1- SOW.pdf
PDF 1 MB Posted
- Attached to
- Office Outfitting- PIT ARSR, Oakdale, PA Federal contract opportunity
- Solicitation number
- 697DCK-18-R-00374
About this file
Attachment 1- SOW (pdf)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1- SOW.pdf | ||
| Exhibit 1b- Drawings.pdf | ||
| Exhibit 1a- Specifications.pdf | ||
| 697DCK-18-R-00374-0001 (Amendment 1 Version).Amendment 1 Version | — | |
| Attachment 2- Wage Determination.pdf | ||
| Amendment 1.pdf | ||
| SIR 697DCK-18-R-00374.pdf | ||
| Attachment 3- Past Performance Questionnaire- Pittsburg.pdf | ||
| Exhibit 1a- Specifications.pdf | ||
| Attachment 2- Wage Determination.pdf | ||
| Exhibit 1b- Drawings.pdf | ||
| SIR 697DCK-18-R-00374.pdf | ||
| Attachment 3- Past Performance Questionnaire- Pittsburg.pdf | ||
| Amendment 1.pdf | ||
| 697DCK-18-R-00374-0001 (Amendment 1 Version).Amendment 1 Version | — | |
| Exhibit 1a- Specifications.pdf | ||
| Exhibit 1b- Drawings.pdf | ||
| Attachment 1- SOW.pdf | ||
| SIR 697DCK-18-R-00374.pdf | ||
| Attachment 2- Wage Determination.pdf | ||
| Attachment 3- Past Performance Questionnaire- Pittsburg.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK:
(SOW)
SITE: PIT - ARSR
LOCATION: Oakdale, PA PROJECT: Fourth Floor Office Fit-Out (JCN: 1403288)
DESCRIPTION OF WORK:
1. GENERAL:
a. The following scope of work was generated based on current conditions relative to the findings and recommendations provided by the Jacobs Engineering report referenced in the NAP.
b. Demolition of the 4th floor south corner interior space had been performed as part of recent fire life safety updates whereby existing combustible wood framed walls were removed and new fire detection and alarm devices were brought into the south corner of the 4th floor. This space was originally occupied by an office, bathroom and conference/break room.
c. Items had remained that are to be demolished for the project including acoustical tiles adhered to the gypsum walls and column; surface mounted outlets, switch boxes and conduits; old lighting pendants; and a section of supply ductwork connected to the 5th floor air handler.
d. The updated area will include an office, unisex bathroom and conference/break room designed in compliance with current code. The new space will be integrated into the recently installed fire life safety system and will be ADA compliant.
e. The approved layout requires the relocation of the BUEC, which needs to be performed by site technicians.
f. This work will also include the replacement of a defunct electric water heater and the removal of an unused slop sink, both located on the 5th floor as part of the plumbing requirement for the project.
g. Construction will need to be coordinated with other work in the building, particularly the elevator upgrade project since the freight elevator is critical to this project.
2. DEFICIENCIES: Existing deficiencies relative to the project description are as follows:
a. HVAC:
• The existing ductwork alone in the south corner is not adequate to serve the new space.
This needs to be modified to provide proper air distribution, ventilation and temperature control for the project.
Page 1 of 5 Version 1.0, Dated 7-14-17
b. ARCHITECTURAL:
• Only the exterior furred gypsum walls (2 sides) are in place which will require the removal of glued acoustical tiles and resurfacing for reuse. New code compliant layout, interior walls, ceilings, lighting and floor finishes are required for the project.
c. ELECTRICAL:
• Existing remaining surface mounted outlets, switches and lighting pendants are not reusable for the project. New electrical circuits will be required for the project.
Security/voice/data connections will also be required.
• Existing building ground bus at interior corner of conference/break room shall remain exposed in place.
3. HVAC:
a. Remove section of supply duct over the fit-out area which extends from the 5th floor air handler, and connect a new length of duct for supply air toward the eastern corner of the equipment room.
b. Cut back existing newer supply duct extending from the 4th floor HVAC system and connect new supply duct to this system for supply air to the new area.
c. Install a new fan-powered VAV terminal with electric heating coil to control temperature in the new area. Thermostat will be located in the break room. Outside air ventilation provided from 4th floor HVAC system.
d. Combination fire-smoke dampers will be installed in ducts penetrating the full height fire rated walls at the perimeter of the office space. Return air will flow from the ceiling plenum through a transfer grille located above the suspended ceiling. F-S damper actuators will need to be connected to the existing fire alarm panel, addressed and programmed by the site’s current fire alarm contractor.
e. Toilet exhaust fan will be provided with ducted discharge through a new exterior wall penetration.
f. A 3.3 kW electric unit heater will be installed in the “former 5th floor bathroom” to provide freeze protection for the new and existing plumbing in this room.
4. PLUMBING:
a. New ADA wall mounted toilet and lavatory will be installed in the bathroom and new plumbing connected to the existing waste, vent and water risers. A new s/s ADA sink will be installed in the break room millwork countertop and plumbed-in.
b. Hot water will be provided from a new 19 gal electric water heater/tank located in the former bathroom on the 5th floor.
c. The existing unused slop sink outside the former bathroom on the 5th floor will be removed at this time to reduce the need to freeze protect its piping. The janitor’s sink in the 5th floor former bathroom is understood to be functional and will be used instead.
d. 14”x14” access panel will be provided between the toilet and lavatory for wet-wall access.
Water isolation valves will be made accessible.
5. ARCHITECTURAL:
Page 2 of 5 Version 1.0, Dated 7-14-17
a. Remove acoustical tiles and adhesive from the existing double layered gypsum wallboard (GWB) at the building SW and SE exterior walls within the area of work. Resurface all damaged GWB using new ½” GWB. Remove acoustical tiles and adhesive on column C-2 and paint the column.
b. Erect full height (16.5 ft.) fire rated GWB at the separation between the equipment room and the new build. Walls will be insulated t for sound attenuation purposes. Other interior walls will be 10 ft. height.
c. Fire rated metal doors will be installed in the fire rated walls.
d. Suspended ceiling will be 2’x 2’ acoustical tiles (with reveal edges). Ceiling heights will be determined.
e. Lighting will be recessed 2’x 2’ fixtures using CFL type lamps.
f. Three existing recently installed smoke detectors will be extended down to the new ceiling.
Existing fire alarm horn/strobe mounted on column C-2 may need to be relocated to coordinate with the new office perimeter wall interface.
g. Floor finishes will include carpet squares in the office and conference room and vinyl tiles for wet areas.
h. Vinyl or rubber wall cove base will be used throughout.
i. Heavy duty corner guards will be installed at perimeter wall corners.
j. Walls will be painted using eggshell finish.
k. Color selections will be by architect and coordinated with the site.
l. Hand towel and toilet paper dispenser selections will be coordinated with the site and provided in the bathroom.
m. A 36”H x 48”W fire rated view panel will be provided in the office NE perimeter wall.
n. ADA compliant cabinetry and sink will be provided in the conference/break room.
6. ELECTRICAL:
a. Remove old surface mounted receptacles, switches, light pendants, wiring and conduits.
b. Provide dedicated 208/3/60 circuit for fan-powered VAV terminal with electric heating coil
(FPVAV-1) from existing electrical panel “D” located on the 4th floor.
c. Provide 120 VAC power to new toilet exhaust fan (EF-1) from panel “D” located on the 4th floor.
d. Install and wire 110 VAC circuits to new receptacles and light fixtures per code from panel “D” located on the 4th floor. Lighting will be recessed 2’x 2’ fixtures using CFL type lamps.
e. Provide GFCI protected receptacles in wet areas.
f. Provide dedicated 208/3/60 circuit for new 3.3 kW Unit Heater (EUH-1) to be located in the 5th floor former bathroom. Power source TBD.
g. Coordinate signal and power wiring needs for smoke detectors and fire-smoke damper motors with the current building fire alarm contractor. Provide low voltage power to two new fire-smoke damper motors.
h. Electrical installation will comply with NEC.
i. New breakers, power wiring and safety switches and bonding/grounding will be provided in accordance with equipment manufacturer and FAA/Site requirements.
j. Provide up to four new voice/data jacks w/cables in office for connectivity at four desks.
Provide new voice/data jack w/cables in break room as required.
Page 3 of 5 Version 1.0, Dated 7-14-17
k. Route communication, data and security cables inside walls and overhead as needed to support the security/voice/data needs for the operation.
l. LOTO will be provided per the facility.
m. Arc Flash labels to be provided where needed.
7. SITE PROVISIONS:
a. Relocation of the BUEC will be performed by site technicians in coordination with the construction schedule.
b. Furniture including desks, chairs, tables, storage cabinets (other than break room millwork), refrigerator, microwave oven, shelving, waste baskets, wall hangers, etc. will be provided by the site.
c. Site to provide access to the building fire alarm panel.
d. Site to provide building and elevator access.
e. Site to provide relocation and setup of security monitoring equipment.
8. PUBLICATIONS: The applicable requirements of the latest edition of the following codes and standards shall apply:
a. American Society of Heating. Refrigeration and Air Conditioning Engineering (ASHRAE)
b. NFPA 70 - National Electric Code (NEC)
c. IMC – International Mechanical Code
d. FAA Std-032
e. FAA Std-019e
f. FAA Std-1217f - Electrical Work – Interior
g. IBC Building code
h. NFPA 101 Fire Life Safety Code
i. UFAS Federal Accessibility Standards
9. ENVIRONMENTAL:
a. Environmental assessment to be performed in areas where construction may disturb existing assemblies.
10. SECURITY AND ACCESS TO THE ARSR-4 SITE:
a. The contractor and all sub-contractors shall be escorted at all times by the FAA on-site representative. Escort will be provided by the RE and/or the ESU site tech.
11. MANUFACTURER'S SPECIFICATIONS AND DRAWINGS:
a. All equipment shall be installed in accordance with manufacturer's specifications and drawings.
All discrepancies are to be reported to the RE for resolution.
12. WORK PERFORMANCE:
a. The contractor shall assure all work is performed and supervised by a trained and qualified person for the trade being performed. The contractor shall insure the certification of all CFC (refrigerant) handlers.
Page 4 of 5 Version 1.0, Dated 7-14-17
13. ACCEPTABLE WORK:
a. All work performed by the contractor and sub-contractor shall be in accordance with all industry and FAA standards and must be approved by the RE. Contractor shall notify RE, five
(5) days prior to completion of all work for final inspection, and testing for acceptance.
14. DISPOSAL AND SITE CLEAN- UP:
a. The contractor shall remove all debris resulting from construction and secure the site at the end of each day. Refrigerant will be recovered per EPA regulations. Final clean up shall be performed by the contractor upon completion of the job.
15. CONTACTS AND TELEPHONE NUMBERS:
b. Kevin Weinheimer SSC Manager 412-269-9241
c. Francis Wichryk ATS Specialist 724-693-8964
d. Craig Gray ATS Specialist 412-461-8825
e. Dennis Hayes SEC Manager 317-247-2696
f. Rob Andrews AJW-2E15K – Architect 718-553-4941
g. Abul Kader AJW-2E15K – Elec. Engineer 718-553-4953
h. Russ Classi AJW-2E15K – Mech. Engineer 718-553-3376
Page 5 of 5 Version 1.0, Dated 7-14-17