- REQUEST FOR OFFER/SCREENING INFORMATION REQUEST - UIS/BUF RTR Tower Project Federal contract opportunity
- Solicitation number
- 6973GH-18-R-00224
About this file
SIR (pdf)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Contractor Release.doc | DOC document | |
| Experience Information Form.docx | DOCX document | |
| Performance Bond.pdf | ||
| Drawings.pdf | ||
| Statement of Work.pdf | ||
| Wage Determination.pdf | ||
| Payment Bond.pdf | ||
| Performance Bond.pdf | ||
| SIR.pdf | ||
| Drawings.pdf | ||
| Payment Bond.pdf | ||
| Statement of Work.pdf | ||
| Experience Information Form.docx | DOCX document | |
| Contractor Release.doc | DOC document | |
| Wage Determination.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section B - Supplies or Services/Prices
Section B - Schedule
Section B - Supplies or Services/Prices
CONTINUATION SHEET
The contractor shall furnish all labor, tools, materials, and equipment required to perform the work identified within the Statement of Work along with other information described herein. All work performed and all materials and equipment used will be subject to approval by the COR and CO. This shall include but not be limited to inspection, scheduling, reporting, and/or submittals.
ITEM NO. DESCRIPTION TOTAL AMOUNT
0001 Base Offer: $ _________________
Clause List
The remainder of this page has been intentionally left blank.
Section C - Description/Specifications
Scope of Work
C.1 SCOPE OF WORK
The contractor shall provide all labor, materials and equipment required to perform the work described within the Statement of Work (SOW) in accordance with requirementsas described herein as well as any attachments. All work performed and any materials and equipment used will be subject to approval by the Contracting Officer Representative (COR) and Contracting Officer (CO). This shall include but not be limited to testing, inspection, scheduling, reporting, and submittals.
C.2 SPECIFICATIONS AND/OR DRAWINGS
The following specifications are applicable to this acquisition.
(a) Statement of Work titled, "Technical specifications for the Antenna Tower Installation at the Buffalo International Airport, Buffalo, NY." June 7, 2018, 64 pages.
(b) Drawings titled, " Remote Tansmitter/Receiver (RTR) Relocation/Tower Project, Buffalo Niagara International Airport, Buffalo, NY." February 22. 2018, 11 pages.
C.3 Bid VS. Offer
References to the terms "bid", "bidder", etc. throughout the specification are intended to refer to "offer", "offeror".
Clause List
AC4548 EMERGENCY SITUATIONS AND EXERCISES DURING CONTRACT PERFORMANCE (JUL
2015)
(a) Emergency situations and exercises are temporary exceptions to the prohibition of contractor personnel not being subject to the direction and control of Government personnel when performing non-personal contract services in FAA facilities.
(b) All contractor personnel at a FAA work site or facility during an actual emergency shall conform to the procedures posted or directed by FAA officials responsible for emergency response at that site or facility. Such officials include evacuation wardens/monitors, security personnel, Emergency Readiness Officers, management, etc.
(c) Contractor personnel shall participate in all emergency exercises, including evacuations, as part of performance under this contract. On rare occasions and based on advance arrangements that are then announced at the time of an exercise, contractor personnel will be excused from evacuations.
(d) Contractor management/supervisors shall ensure that each contractor employee assigned work in FAA facilities possesses a general awareness of emergency and evacuation procedures at all locations where the employees might be during an emergency or exercise. Information on emergency procedures may be requested from the Contracting Officer’s Representative (COR) or a designated FAA contact point at the work site.
Section D - Packaging and Marking
Clause List
SECTION D - N/A
There are no applicable Section D clauses
Section E - Inspection and Acceptance
Clause List
3.10.4-10 INSPECTION OF CONSTRUCTION (SEP 2009)
(a) 'Work' includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) below.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer.
The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless the Government determines that it is in the public interest to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may:
(1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or
(2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(j) In the absence of any formal disputes, a project will be deemed physically and financially complete within one year after final acceptance and excess funds will be deobligated at that time.
(End of clause)
Section F - Deliveries or Performance
Clause List
F.1 WORKING HOURS
The Contractor shall be expected to work during day times, 7:00 AM to 3:30 PM Monday through Friday except for Federal Holidays. Other options may be available, as coordinated with the COR and CO.
a.) Work schedule shall be restricted to daylight hours. (Between 7:00AM to 6:00PM. M-F) b.) The contractor shall establish the working hours at the beginning of the project. The regular work week shall be 40 hours but may be 4 or 5 days. (10 hrs. x 4 days or 8 hrs. x 5 days.)
c.) Weekend work will only be authorized if necessary due to weather. No overtime will be allowed.
d.) Contractor will report & coordinate each day’s work in advance with the Resident Engineer.
F.2 UTILITY OUTAGES AND SHUTDOWN
Utility outages and shutdown shall be coordinated with the Contracting Officer and Project Manager. Outages affecting FAA operations are required to be accomplished at night, on weekends or designated government holidays. Prior to any outage or shutdown, seven (7) working days notification must be made to coordinate scheduling of any work to be performed during any hours.
F.3 TEMPORARY SERVICES AND FACILITIES
Contractor shall provide and pay for all temporary services and facilities as specified below and as necessary for the proper and expeditious execution of the work. Contractor shall make, or have made, all connections to existing services and sources of supply as necessary and/or indicated and pay all charges for same. Contractor shall provide all labor, materials, equipment and appurtenances necessary for the completion of the identified project. All work under this section shall comply with applicable laws, rules, regulations, codes, ordinances and orders of all federal, state and local authorities having jurisdiction for the safety of persons, materials and property. Contractor shall remove all such temporary installations and connections when no longer necessary for the project work.
3.10.1-11 GOVERNMENT DELAY OF WORK (APR 1996)
3.2.2.8-5 LIQUIDATED DAMAGES - CONSTRUCTION (APR 1996)
If the Contractor fails to complete the work within the time specified in the contract, or any extension, the Contractor shall pay to FAA as liquidated damages, the sum of $ for each day of delay.
If FAA terminates the Contractor's right to proceed, the resulting damage will consist of liquidated damages until such reasonable time as may be required for final completion of the work, together with any increased costs to FAA in completing the work.
If FAA does not terminate the Contractor's right to proceed, the resulting damage will consist of liquidated damages until the work is completed or accepted.
3.10.1-24 NOTICE OF DELAY (MAR 2009)
If the Contractor becomes unable to complete the contract work at the time(s) specified because of technical difficulties, notwithstanding the exercise of good faith and diligent efforts in the performance of the work called for hereunder, the contractor shall give the Contracting officer written notice of the anticipated delay and the reasons therefor. Such notice and reasons shall be delivered promptly after the condition creating the anticipated delay becomes known to the contractor, but in no event less than forty-five (45) days before the completion date specified in this contract, unless otherwise directed by the Contracting Officer. When notice is so required, the Contracting officer may extend the time specified in the Schedule for such period as deemed advisable.
(End of clause)
AC1817 ACCELERATED DELIVERY (JAN 1997)
Any Schedule for delivery or performance may be expedited at the contractor's option, if without additional expense to the Government.
Section G - Contract Administration Data
Clause List
3.10.1-23 CONTRACTING OFFICER'S REPRESENTATIVE-CONSTRUCTION CONTRACTS (APR
2012)
(a) The Contracting Officer may appoint other Government personnel to accomplish certain contract administration matters. While there shall be various titles and divisions of duties for these individuals, generically they are known as Contracting Officer's Representatives (CORs). The Contracting Officer will provide written notice of COR appointment(s), setting forth the authorities and limitations, to the Contractor within calendar days prior to the notice to proceed. COR duties may include, but are not limited to:
(1) Perform as the authorized representative of the Contracting Officer for technical matters, including interpretation of specifications and drawings, and inspection and review of work performed.
(2) Perform as the authorized representative of the Contracting Officer for administrative matters, including reviewing payments, and updated delivery schedules.
(b) These representatives are authorized to act for the Contracting Officer in all specifically delegated matters pertaining to the contract, except:
(1) contract modifications that change the contract price or cost, technical requirements or time for performance, unless delegated field change order authority;
(2) suspension or termination of the Contractor's right to proceed, either for default or for convenience;
(3) final decisions on any matters subject to appeal, e.g., disputes under the "Contract Disputes" clause; and
(4) final acceptance under the contract.
(End of clause)
AC0135 INVOICING PROCEDURES - GENERAL (JAN 2017)
(a) In addition to the requirements set forth at AMS Clause 3.3.1-17, Prompt Payment, for the submission of a proper invoice, the contractor shall submit a separate invoice for (1) each month of performance of services, or (2) those items of supplies furnished, as follows:
(1) The original to: 9-AMC-AMZ-FAA-APInvoices@faa.gov (Preferred) or mail to:
DOT/FAA AMK-311/314
P.O. Box 25710
Oklahoma City, OK 73169-0710
(2) One Copy to janice.hammonds@faa.gov or:
FAA, Mike Monroney Aeronautical Center
Office of Acquisition Services (AAQ- )
P.O. Box 25082
Oklahoma City, OK 73l25
(3) One Copy to pattie.ctr.tidmore@faa.gov or:
FAA, Mike Monroney Aeronautical Center
Janice Hammonds, AAQ-722
P.O. Box 25710
Oklahoma City, OK 73l25
(b) Each invoice shall highlight the following information:
(1) Contract number and applicable Delivery Order number.
(2) Noun description of services and/or supplies, including applicable line item number(s) and quantity(s) that were provided.
(3) Extended totals for invoiced quantities.
(c) All contractors invoicing services to the FAA in labor hours shall maintain on file, and submit when required for verification or audit, certified time logs showing a daily start and ending work times, the daily total of productive hours charged to the contract, a daily entry for any non-productive work-hours and cumulative totals for each pay period.
AC1227 RELEASE FORM (JAN 1997)
The contractor will be required to execute Contractor's Release Form DOT F 4220.4 (2-71) prior to final payment under the contract. (Note: A copy of Form DOT F 4220.4 (2-71) is attached hereto for information purposes.)
Section H - Special Contract Requirements
Clause List
H.1 PERMITS AND RESPONSIBILITIES
The Contractor shall secure and pay for all permits, licenses, special inspections, etc., required in the execution of the work, whether of a permanent or temporary nature.
H.2 ACCIDENT AND FIRE REPORTING
(a) The Contractor shall report to the CO any accident or fire occurring at the site of the work which causes:
(1) A fatality or as much as one lost workday on the part of any employee of the Contractor or subcontractor at any tier;
(2) Damage of $1,000 or more to Federal property, either real or personal;
(3) Damage of $1,000 or more to Contractor or subcontractor owned or leased motor vehicles or mobile equipment; or
(4) Damage for which a contract time extension may be requested.
(b) Accident and fire reports required by paragraph (a) above shall be accomplished by the following means:
(1) Report immediately by telephone to the CO or his/her authorized representative and shall be confirmed by email or facsimile transmission within 24 hours to the Contracting Officer. Such email or facsimile transmission shall state all known facts as to extent of injury and damage and as to cause of the accident or fire.
(2) Accident and fire reports required by paragraph (a) above may be reported by the Contractor using a state, private insurance carrier, or Contractor accident report form which provides for the statement of:
(i) The extent of injury; and
(ii) The damage and cause of the accident or fire. Such report shall be mailed or otherwise delivered to the Contracting Officer within 48 hours of the occurrence of the accident or fire.
(c) The Contractor shall assure compliance by subcontractors at all tiers with the requirements of this clause.
3.1.9-1 ELECTRONIC COMMERCE AND SIGNATURE (JUL 2013)
(a) The Electronic Signatures in Global and National Commerce Act (E-SIGN) establishes a legal equivalence between:
(1) Contracts written on paper and contracts in electronic form;
(2) Pen-and-ink signatures and electronic signatures; and
(3) Other legally-required written records and the same information in electronic form.
(b) With the submission of an offer, the offeror acknowledges and accepts the utilization of electronic commerce as part of the requirements of this solicitation and the resultant contract.
(c) Certain documents may need to be provided or maintained in original form, such as large scale drawings impractical to convert to electronic format or a document with a raised seal signifying authenticity. This clause does not change or affect any other requirements that a document must be in paper format to satisfy legal requirements such as for certain real estate transactions.
(d) The use of electronic signature technology is authorized under this solicitation and the resulting contract.
Contractors may use the following means of electronic signature technology such as a digital signature.
(End of Clause)
AC1231 NOTIFICATION REQUIREMENTS WHEN FRIABLE ASBESTOS MATERIAL IS
REMOVED/DISTURBED (JAN 1997)
(a) Prior to any planned and/or scheduled disturbance of friable asbestos material, mainly CAFCO ceilings, the contractor shall present a written plan to the Contracting Officer. The plan shall include, but not be limited to, location, type facility, size of area to be disturbed or removed, method of containment to be used, disposal procedures, clean-up procedures, number of employees involved, protective clothing/equipment to be used, the date and time removal/disturbance is planned and any other information requested by the Contracting Officer. The contractor shall not proceed with any removal or disturbance of friable asbestos material without written approval from the Contracting Officer.
(b) If during the performance of the contract the contractor inadvertently disturbs friable asbestos material, mainly CAFCO ceilings, the contractor shall immediately cease operations and notify the Contracting Officer. The contractor shall remain at the site of disturbance for the Contracting Officer's instructions.
AC4555 NOTICE OF CONTRACTOR TESTIMONY (SEP 2006)
(a) The contractor shall notify the Contracting Officer promptly in writing of its intention, or the intention of its employees, subcontractors of any tier, or subcontractor employees, either voluntarily or under compulsion of competent authority, to provide sworn testimony on any matter related to or arising under the work required by and/or performed under, this contract. Such written notification at a minimum shall consist of the date and time of the testimony, identification of the court, board, or other body before which the testimony is made, the nature of the testimony to be given to the extent it is known at the time of this report, the nature of the contractor’s involvement in the proceeding and any other circumstances related to the work performed under or related to the contract and the proceeding in which the testimony will be taken.
(b) The contractor shall include the substance of this clause, including this paragraph (b), in all subcontracts executed under this contract and shall require all subcontractors to provide the required report to the contractor.
AC4557 STRIKES OR PICKETING
Notwithstanding any other provision hereof, the Contractor is responsible for delays arising out of labor disputes, including but not limited to strikes, if such strikes are reasonably avoidable. A delay caused by a strike or by picketing which constitutes an unfair labor practice is not excusable unless the Contractor takes all reasonable and appropriate action to end such a strike or picketing, such as the filing of a charge with the National Labor Relations Board, the use of other available Government procedures, and the use of private boards or organizations for the settlement of disputes.
Section I - Contract Clauses
Clause List
3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2011)
This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:
http://conwrite.faa.gov.
(End of clause)
3.1.7-2 ORGANIZATIONAL CONFLICTS OF INTEREST (AUG 1997)
3.2.2.3-33 ORDER OF PRECEDENCE (MAR 2009)
3.2.2.3-42 DIFFERING SITE CONDITIONS (JUL 2004)
3.2.2.3-43 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (JUL 2004)
3.2.2.3-45 MATERIAL AND WORKMANSHIP (JUL 2004)
3.2.2.3-46 SUPERVISING THE CONTRACT WORK (JUL 2004)
3.2.2.3-47 PERMITS AND RESPONSIBILITIES (JUL 2004)
3.2.2.3-48 OTHER CONTRACTS (MAR 2009)
3.2.2.3-49 PROTECTING EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (JUL 2004)
3.2.2.3-50 PROPERTY PROTECTION (OCT 2014)
3.2.2.3-51 OPERATIONS AND STORAGE AREAS (APR 2012)
3.2.2.3-53 CLEANING UP AND ROADWAY MAINTENANCE (JUL 2004)
3.2.2.3-54 PREVENTING ACCIDENTS (JUL 2004)
3.2.2.3-58 LAYOUT OF WORK (MAR 2009)
3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009)
3.2.2.3-68 SAFETY AND HEALTH (OCT 2014)
3.2.2.3-83 PROHIBITION AGAINST CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS
(OCT 2015)
3.2.2.7-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (APR 2011)
3.2.2.7-8 DISCLOSURE OF TEAM ARRANGEMENTS (APR 2008)
3.2.5-1 OFFICIALS NOT TO BENEFIT (APR 1996)
3.2.5-3 GRATUITIES OR GIFTS (JAN 1999)
3.2.5-4 CONTINGENT FEES (OCT 1996)
3.2.5-5 ANTI-KICKBACK PROCEDURES (OCT 2010)
3.2.5-8 WHISTLEBLOWER PROTECTION FOR CONTRACTOR EMPLOYEES (APR 1996)
3.3.1-2 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (APR 1996)
3.3.1-16 PROHIBITION OF ASSIGNMENT OF CLAIMS (APR 1996)
3.3.1-19 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
3.3.1-20 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS SUBCONTRACTORS (OCT
2012)
3.3.1-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER- SYSTEM FOR AWARD MANAGEMENT
(AUG 2012)
3.4.1-7 NOTICE TO PROCEED (APR 1996)
3.4.1-10 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JUL 1996)
3.4.2-6 TAXES - CONTRACTS PERFORMED IN U.S. POSSESSIONS OR PUERTO RICO (OCT 1996)
3.4.2-8 FEDERAL, STATE, AND LOCAL TAXES - FIXED PRICE CONTRACT (APR 2013)
3.5-1 AUTHORIZATION AND CONSENT (JAN 2009)
3.6.1-1 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (JAN 2010)
3.6.1-3 UTILIZATION OF SMALL, SMALL DISADVANTAGED AND WOMEN-OWNED, AND
SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS CONCERNS (MAR 2009)
3.6.2-2 CONVICT LABOR (APR 1996)
3.6.2-9 EQUAL OPPORTUNITY (AUG 1998)
3.6.2-12 EQUAL OPPORTUNITY FOR VETERANS (JAN 2011)
3.6.2-16 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (APR 1996)
3.6.2-18 DAVIS BACON ACT (APR 2017)
3.6.2-19 WITHHOLDING-LABOR VIOLATIONS (JUL 2017)
3.6.2-20 PAYROLLS AND BASIC RECORDS (APR 2017)
3.6.2-21 APPRENTICES, TRAINEES, AND HELPERS (APR 2017)
3.6.2-22 SUBCONTRACTS (LABOR STANDARDS) (APR 2017)
3.6.2-23 CERTIFICATION OF ELIGIBILITY (APR 2017)
3.6.2-35 PREVENTION OF SEXUAL HARASSMENT (AUG 1998)
3.6.2-39 TRAFFICKING IN PERSONS (OCT 2015)
3.6.2-44 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT (JAN 2012)
3.6.3-13 AFFIRMATIVE PROCUREMENT OF RECYCLED CONTENT AND PRODUCTS UNDER
SERVICE AND CONSTRUCTION CONTRACTS (OCT 2016)
3.6.3-14 USE OF ENVIRONMENTALLY PREFERABLE PRODUCTS (OCT 2016)
3.6.3-16 DRUG FREE WORKPLACE (MAR 2009)
3.6.3-23 DELIVERY OF ELECTRONIC AND PAPER DOCUMENTS (OCT 2016)
3.6.3-24 ASBESTOS NESHAP COMPLIANCE (OCT 2015)
3.6.4-5 BUY AMERICAN - STEEL AND MANUFACTURED PRODUCTS (JUL 2010)
3.6.4-8 BUY AMERICAN ACT - NAFTA IMPLEMENTATION ACT - BALANCE OF PAYMENTS
PROGRAM (OCT 2014)
3.6.4-10 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JAN 2010)
3.6.4-11 INCONSISTENCY BETWEEN ENGLISH VERSION AND TRANSLATION OF CONTRACT
(APR 1996)
3.9.1-1 CONTRACT DISPUTES (OCT 2011)
3.9.1-2 PROTEST AFTER AWARD (AUG 1997)
3.10.1-7 BANKRUPTCY (APR 1996)
3.10.1-8 SUSPENSION OF WORK (SEP 1998)
3.10.1-15 CHANGES-CONSTRUCTION, DISMANTLING, DEMOLITION, OR REMOVAL OF
IMPROVEMENTS (JUL 1996)
3.10.1-16 CHANGES AND CHANGED CONDITIONS (APR 1996)
3.10.1-26 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (APR 2013)
3.10.3-1 DEFINITIONS (APR 2012)
3.10.6-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (OCT 1996)
3.10.6-6 DEFAULT (FIXED PRICE CONSTRUCTION) (OCT 1996)
3.13-5 SEAT BELT USE BY CONTRACTOR EMPLOYEES (OCT 2001)
3.13-13 CONTRACTOR POLICY TO BAN TEXT MESSAGING WHILE DRIVING (JAN 2011)
3.13-14 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
(JAN 2018)
3.14-3 FOREIGN NATIONALS AS CONTRACTOR EMPLOYEES (OCT 2017)
3.14-4 ACCESS TO FAA FACILITIES, SYSTEMS, GOVERNMENT PROPERTY AND SENSITIVE
INFORMATION (JAN 2018)
3.1.7-5 DISCLOSURE OF CONFLICTS OF INTEREST (MAR 2009)
It is the Federal Aviation Administration (FAA) policy to award contracts to only those offerors whose objectivity is not impaired because of any related past, present, or planned interest, financial or otherwise, in organizations regulated by FAA or in organizations whose interests may be substantially affected by Agency activities. Based on this policy:
(a) The offeror shall provide a statement in its proposal which describes in a concise manner all past, present or planned organizational, financial, contractual or other interest(s) with an organization regulated by FAA, or with an organization whose interests may be substantially affected by Agency activities, and which is related to the work under this solicitation. The interest(s) described shall include those of the proposer, its affiliates, proposed consultants, proposed subcontractors and key personnel of any of the above. Past interest shall be limited to within one year of the date of the offeror's technical proposal. Key personnel shall include any person owning more than 20% interest in the offeror, and the offeror's corporate officers, its senior managers and any employee who is responsible for making a decision or taking an action on this contract where the decision or action can have an economic or other impact on the interests of a regulated or affected organization.
(b) The offeror shall describe in detail why it believes, in light of the interest(s) identified in (a) above, that performance of the proposed contract can be accomplished in an impartial and objective manner.
(c) In the absence of any relevant interest identified in (a) above, the offeror shall submit in its proposal a statement certifying that to its best knowledge and belief no affiliation exists relevant to possible conflicts of interest. The offeror must obtain the same information from potential subcontractors prior to award of a subcontract.
(d) The Contracting Officer will review the statement submitted and may require additional relevant information from the offeror. All such information, and any other relevant information known to FAA, will be used to determine whether an award to the offeror may create a conflict of interest. If any such conflict of interest is found to exist, the Contracting Officer may:
(1) disqualify the offeror, or
(2) determine that it is otherwise in the best interest of the United States to contract with the offeror and include appropriate provisions to mitigate or avoid such conflict in the contract awarded.
(e) The refusal to provide the disclosure or representation, or any additional information required, may result in disqualification of the offeror for award. If nondisclosure or misrepresentation is discovered after award, the resulting contract may be terminated. If after award the Contractor discovers a conflict of interest with respect to the contract awarded as a result of this solicitation, which could not reasonably have been known prior to award, an immediate and full disclosure shall be made in writing to the Contracting Officer. The disclosure shall include a full description of the conflict, a description of the action the contractor has taken, or proposes to take, to avoid or mitigate such conflict. The Contracting Officer may, however, terminate the contract for convenience if he or she deems that termination is in the best interest of the Government.
(End of provision)
3.2.2.3-37 NOTIFICATION OF OWNERSHIP CHANGES (JUL 2004)
(a) The Contractor (you) must notify FAA in writing within 30 days when you become aware that a change in ownership has occurred or will occur and that the change could affect the value of your capitalized assets in the accounting records, asset valuations, or cause any other cost changes.
(b) You must:
(1) Maintain current, accurate, and complete inventory records of assets and their costs;
(2) Provide the Contracting Officer (CO) access to the records on request;
(3) Ensure that all individual and grouped assets, their capitalized values, accumulated depreciation or amortization, and remaining useful lives are identified accurately before and after each of your ownership changes; and
(4) Retain and maintain depreciation and amortization schedules based on the asset records maintained before each ownership change.
(c) You must include the substance of this clause in all subcontracts under this contract with a value exceeding $1,000,000 and that require cost and price data.
(End of clause)
3.2.2.3-41 PERFORMING WORK (JUL 2004)
The Contractor (you) must perform, using your own organization, work equivalent to at least percent of the total amount of work under the contract on the site. The CO may modify this contract to reduce this percentage if you request a reduction and the CO determines that it would be to the Government's advantage to do so.
(End of clause)
3.2.2.3-62 PRECONSTRUCTION CONFERENCE (JUL 2004)
The successful offeror must attend a pre-construction conference at a site the Contracting Officer designates before starting the work.
3.2.2.3-66 CONTRACTOR'S DAILY LOG (JUL 2004)
The Contractor (you) must submit a "Daily Log." You must complete the forms daily and deliver them to the designated FAA Contracting Officer's (CO) Technical Representative. The forms must include, but is not limited to, workers by classification, construction equipment moved on and off the site, materials and equipment delivered to the site, inspections and tests performed, and total cumulative hours worked.
(End of clause)
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (JUL 2004)
The Contractor (you) must
(a) begin work under this contract within 15 calendar days after the date you receive the notice to proceed,
(b) perform the work diligently, and
(c) complete the entire work ready for use not later than 25 April 2019. The time allowed for completion must include final cleanup of the premises.
(End of clause)
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (JUL 2004) -
ALTERNATE I (JUL 2004)
The Contractor (you) must
(a) begin work under this contract within 15 calendar days after the date you receive the notice to proceed,
(b) perform the work diligently, and
(c) complete the entire work ready for use not later than 25 April 2019. The time allowed for completion must include final cleanup of the premises.
(d) The completion date assumes that the successful offeror will receive the notice to proceed by 24 September 2018. The CO will extend the completion date by the number of calendar days after the above date that you receive the notice to proceed, except to the extent that the delay in issuing the notice to proceed results from your failure to execute the contract and give the required performance and payment bonds to FAA within the time specified.
(End of clause)
3.3.1-33 SYSTEM FOR AWARD MANAGEMENT (OCT 2016)
(a) Definitions. As used in this clause
"Data Universal Numbering System (DUNS) number" means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
"Data Universal Numbering System +4 (DUNS+4) number" means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.)
This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts for the same parent concern.
"Registered in the SAM database" means that the Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the SAM database.
"System for Award Management (SAM) Database" means the primary Government repository for Contractor information required for the conduct of business with the Government.
(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in Representations, Certifications and Other Statements of Offerors Section of the solicitation, the DUNS or DUNS +4 number that identifies the offeror's name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number
(i) If located within the United States, by calling Dun and Bradstreet at 1-866-705-5711 or via the Internet at http://fedgov.dnb.com/webform; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company Physical Street Address, City, State, and ZIP Code.
(iv) Company Mailing Address, City, State and ZIP Code (if different from physical street address).
(v) Company Telephone Number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer may proceed to award to the next otherwise successful registered offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document. If registered in SAM as a Service-Disabled Veteran-Owned Small Business (SDVOSB), by submission of an offer, the offeror acknowledges that they are designated as a SDVOSB by the Department of Veterans Affairs, and this designation appears as such on the Veteran Affairs website, https://www.vip.vetbiz.gov.
(g)(1)(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in AMS Procurement Guidance, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to:
(A) change the name in the SAM database;
(B) comply with the requirements of AMS regarding novation and change-of-name agreements; and
(C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide the Contracting Officer with the notification, sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims. Assignees shall be separately registered in the SAM database. Information provided to the Contractor's SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.sam.gov.
(End of Clause)
3.4.1-4 PERFORMANCE BOND REQUIREMENTS (JAN 2017)
(a) The contractor is required to submit a performance bond in a penal amount equal to 100 percent of the contract price, but for this contract the amount required by the Contracting Officer is 100% of the contract price.
(b) The bond must be executed on specified forms, and sureties must be acceptable to the Federal Aviation Administration. Corporate sureties must appear on the list in Treasury Circular 570, and the amount of the bond may not exceed the underwriting limit stated for the surety on that list.
(c) Failure to submit an acceptable bond may be cause for termination of the contract for default.
(End of clause)
3.4.1-5 PAYMENT BOND REQUIREMENTS (JAN 2018)
(a) The contractor is required to submit a payment bond in the penal amount of total contract value within the time required by the Contracting Officer.
(b) The bond must be executed on the forms attached to this SIR, and sureties must be acceptable to the Federal Aviation Administration. Corporate sureties must appear on the list in Treasury Circular 570, and the amount of the bond may not exceed the underwriting limit stated for the surety on that list.
(c) Failure to submit an acceptable bond may be cause for termination of the contract for default.
3.6.2-14 EMPLOYMENT REPORTS ON VETERANS (JAN 2011)
(a) Unless the contractor is a State or local government agency, the contractor must report at least annually, as required by the Secretary of Labor, on:
(1) The total number of employees in the contractor's workforce, by job category and hiring location, who are disabled veterans, other protected veterans, Armed Forces service medal veterans, and recently separated veterans,
(2) The total number of new employees hired during the period covered by the report, and of the total, the number of disabled veterans, other protected veterans, Armed Forces service medal veterans, and recently separated veterans;
and
(3) The maximum number and minimum number of employees of the Contractor or subcontractor at each hiring location during the period covered by the report.
(b) The above items must be reported by completing the form titled 'Federal Contractor Veterans' Employment Report VETS-100A.'
(c) Reports shall be submitted no later than September 30 of each year.
(d) The employment activity report required by paragraph (a)(2) of this clause must reflect total hires during the most recent 12-month period as of the ending date selected for the employment profile report required by paragraph (a)(1) of this clause. Contractors may select an ending date: (1) As of the end of any pay period during the period January through March 1st of the year the report is due, or (2) as of December 31, if the contractor has previous written approval from the Equal Employment Opportunity Commission to do so for purposes of submitting the Employer Information Report EEO-1 (Standard Form 100).
(e) The count of veterans reported according to paragraph (a) of this clause must be based on data known to the contractor when completing the VETS-100A. .The Contractor's knowledge of veterans status may be obtained in a variety of ways, including an invitation to applicants to self-identify (in accordance with 41 CFR 60-300.42), voluntary self-disclosure by employees, or actual knowledge of veteran status by the contractor. This paragraph does not relieve the employer of liability for a determination under 38 U.S.C. 4212.
(f) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order of $100,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor.
(End of clause)
3.6.2-24 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (OCT 2010)
(a) Definitions.
(1) "Employer identification number," as used in this clause, means the last four digits of the Federal Social Security number used on the employer's quarterly federal tax return, U.S. Treasury Department Form 941.
(2) "Minority," as used in this clause, means
(i) Black (all persons having origins in any of the black African racial groups not of Hispanic origin);
(ii) Hispanic (all persons of Mexican, Puerto Rican, Cuban, Central or South American, or other Spanish culture or origin, regardless of race);
(iii) Asian and Pacific Islander (all persons having origins in any of the original peoples of the Far East, Southeast Asia, the Indian Subcontinent, or the Pacific Islands); and
(iv) American Indian or Alaskan Native (all persons having origins in any of the original peoples of North America and maintaining identifiable tribal affiliations through membership and participation or community identification).
(b) If the Contractor, or a subcontractor at any tier, subcontracts a portion of the work involving any construction trade, each such subcontract in excess of $10,000 shall include this clause, including the goals for minority and female participation stated herein.
(c) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate work force in each trade on all construction work in the covered area, are as follows:
Goals for minority participation: 14.3% Goals for female participation: 6.9% (Contracting Officer insert goals)
Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Office of Federal Contract Compliance Programs (OFCCP) area office within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this screening information request. The notification shall list the:
(1) Name, address, and telephone number of the subcontractor,
(2) Employer identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) The Contractor shall implement the affirmative action procedures in subparagraphs (f)(1) through (7) of this clause. The goals stated in this contract are expressed as percentages of the total hours of employment and training of minority and female utilization that the Contractor should reasonably be able to achieve in each construction trade in which it has employees in the covered area. If the contractor performs construction work in a geographical area located outside of the covered area, it shall apply the goals established for the geographical area where that work is actually performed. The Contractor is expected to make substantially uniform progress toward its goals in each craft.
(f) The contractor shall take affirmative action steps at least as extensive as the following:
(1) Ensure a working environment free of harassment, intimidation, and coercion at all sites, and in all facilities where the Contractor's employees are assigned to work. The Contractor, if possible, will assign two or more women to each construction project. The Contractor shall ensure foremen, superintendents, and other on-site supervisory personnel are aware of and carry out the Contractor's obligation to maintain such a working environment, with specific attention to minority or female individuals working at these sites or facilities.
(2) Immediately notify the OFCCP area office when the union or unions, with which the Contractor has a collective bargaining agreement, has not referred back to the Contractor a minority or woman sent by the Contractor, or when the Contractor has other information that the union referral process has impeded the Contractor's efforts to meet its obligations.
(3) Develop on-the-job training opportunities and/or participate in training programs for the area that expressly include minorities and women, including upgrading programs and apprenticeship and trainee programs relevant to the Contractor's employment needs, especially those programs funded or approved by the Department of Labor. The Contractor shall provide notice of these programs to the sources compiled under subparagraph (f)(2) above.
(4) Review, at least annually, the Contractor's equal employment policy and affirmative action obligations with all employees having responsibility for hiring, assignment, layoff, termination, or other employment decisions. Conduct reviews of this policy with all on-site supervision, personnel prior to initiation of construction work at a job site. A written record shall be made and maintained identifying the time and place of these meetings, persons attending, subject matter discussed, and disposition of the subject matter.
(5) Disseminate the Contractor's equal employment policy externally by including it in any advertising in the news media, specifically including minority and female news media. Provide written notification to, and discuss this policy with, other Contractors and subcontractors with which the Contractor does or anticipates doing business.
(6) Conduct, at least annually, an inventory and evaluation at least of all minority and female personnel for promotional opportunities. Encourage these employees to seek or to prepare for, through appropriate training, etc., opportunities for promotion.
(7) Maintain a record of solicitations for subcontracts for minority and female construction contractors and suppliers, including circulation of solicitations to minority and -female contractor associations and other business associations.
(g) The Contractor is encouraged to participate in voluntary associations that may assist in fulfilling one or more of the affirmative action obligations contained in subparagraphs (f)(1) through (7). The efforts of a contractor association, joint contractor-union, contractor-community, or similar group of which the contractor is a member and participant, may be useful in achieving one or more of its obligations under subparagraphs (f)(1) through (7).
(h) A single goal for minorities and a separate single goal for women shall be established. The Contractor is required to provide equal employment opportunity and to take affirmative action for all minority groups, both male and female, and all women, both minority and non-minority. Consequently, the Contractor may be in violation of Executive Order 11246, as amended, if a particular group is employed in a substantially disparate manner.
(i) The contractor shall not use goals or affirmative action standards to discriminate against any person because of race, color, religion, sex, or national origin.
(j) The Contractor shall not enter into any subcontract with any person or firm debarred from Government contracts under Executive Order 11246, as amended.
(k) The Contractor shall carry out such sanctions and penalties for violation of this clause and of the Nondiscrimination and Affirmative Action clause, including suspension, termination, and cancellation of existing subcontracts, as may be imposed or ordered under Executive Order 11246, as amended, and its implementing regulations, by the OFCCP. Any failure to carry out these sanctions and penalties as ordered shall be a violation of this clause and Executive Order 11246, as amended.
(l) Nothing contained herein shall be construed as a limitation upon the application of other laws that establish different standards of compliance.
(End of clause)
3.6.3-5 ESTIMATE OF PERCENTAGE OF RECYCLED CONTENT FOR DESIGNATED ITEMS TO BE
USED IN THE PERFORMANCE OF THE CONTRACT (JAN 2017)
(a) Definitions. As used in this clause:
(1) "Post-consumer material" means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Post consumer material is a part of the broader category of "recycled content."
(2) "Recycled content" means waste materials and by-products which have been recovered or diverted from solid waste including post-consumer material, but such term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract must: