Plans_-_NP-SER_PMS_FY19(3).pdf

PDF 29 MB Posted

Attached to
Southeast Region Pavement Preservation Federal contract opportunity
Solicitation number
693C73-20-B-000003
Issued by
Department of Transportation Federal Highway Administration

About this file

This document outlines a federal contract opportunity for pavement preservation work at multiple national park sites in North and South Carolina. Sealed bids from certified Small Business Concerns will be accepted for projects including removing pavement markings, adding preservation treatments, removing and resetting wheelstops, and adding new markings. The work will be split into multiple schedules with a total expected cost between $1,000,000 to $5,000,000. Bid documents for Solicitation Number 693C73-20-B-000003 will be available on November 5, 2019 on FBO.gov. Bids are due on a date specified in Block 13a of the SF1442 form. In addition to standard contract clauses, the Representations and Certifications form and Vets-4212 form must be completed on SAM.gov and DOL.gov respectively. Questions should be directed to eflhd.contracts@dot.gov.

Plans - NP-SER PMS FY19(3)

View the file

Other files for this federal contract opportunity

Other files attached to Southeast Region Pavement Preservation, newest first.
File Type Posted
Results of Bid Opening - NP-SER PMS FY19(3).pdf PDF
ADV_Bidder's_Qualifications_Form.doc DOC document
VETS-4212_Form.pdf PDF
IFB_Solicitation_-_NP-SER_PMS_FY19(3).pdf PDF
NEPA_CE.pdf PDF
FP14_Eng.pdf PDF
Synopsis_-_NP-SER_PMS_FY19(3).doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

z

PARK ROUTE NO. ROUTE NAME Ill Ill

CARL CARL-0900 VISITOR PARKING LOT

79060

COWP COWP-0010 MAIN ENTRANCE ROAD

75891

COWP COWP-0011 TOUR ROAD 75894

COWP COWP-0200 PICNIC AREA LOOP 75896

COWP COWP-0900 VISITOR CENTER PARKING

75898

COWP COWP-0903 OVERLOOK NUMBER 1 PARKING 75906

COWP COWP-0904 SCRUGGS HOUSE PARKING

75907

COWP COWP-0905 BATTLEFIELD PARKING NUMBER 1 75909

COWP COWP-0906 BATTLEFIELD PARKING NUMBER 2 75911

COWP COWP-0907AZ PICNIC AREA PARKING G

75914

COWP COWP-0907Z PICNIC AREA PARKING A

75914

COWP COWP-0908Z PICNIC AREA PARKING B

75914

COWP COWP-0909Z PICNIC AREA PARKING C

75914

COWP COWP-0910Z PICNIC AREA PARKING D

75914

COWP COWP-0911Z PICNIC AREA PARKING E

75914

COWP COWP-0912Z PICNIC AREA PARKING F

75914

COWP COWP-0914 TRAIL HEAD PARKING 113293

KIMO KIMO-0010 MAIN PARK DRIVE

KIMO KIMO-0900 VISITOR CENTER PARKING

KIMO KIMO-0903 HEADQUARTERS PARKING

Total

Subtotal This Shee t

Rounded Total

SCHEDULE A

STRIPING SUMMARY

Pay Item Pay Item Pay Item Pay Item Pay Item

63401-0300 63401-1500 63405-0550 63405-0600 63405-0850

PAVEMENT

PAVEMENT

PAVEMENT PAVEMENT PAVEMENT MARKINGS, TYPE B,

MARKINGS, TYPE B,

MARKINGS, TYPE B, MARKINGS, TYPE H, MARKINGS, TYPE B, STRAIGHT /TURN

ACCESSIBILITY

SOLID SOLID STRAIGHT ARROW ARROW

SYMBOL

COMBINATION

Lnft Lnft Each Each Each

White Yellow White Yellow White White White

660 6 2

4 752

11 000 5 000

2 647 400 5

425 830 1

505 1 040 1

521 1

302 2

200 1

58 2

191 1

876 148 6 2

30,027 29,700

2 279 4 1 3

9 791 2 418 41171 39452 16 1 21

12 209 80 623 16 1 21

12 800 84 600 16 1 21

PMIS NPS STATE PROJECT SHEET

NO. NO. NUMBER

TITLE 910 NC/SC NP SER PMS FY19(3) C06

SHEET 1497f;

NOTE:

Match existing pavement marking configurations, symbols and words, or as directed by the CO and according to Detail E634-01A.

Pay Item Pay Item Pay Item

63405-2890 63405-2950

63503-0700

PAVEMENT

TEMPORARY

PAVEMENT MARKINGS,

TRAFFIC CONTROL,

MARKINGS, TYPE H,

PAVEMENT

TYPE H STRAIGHT

MARKINGS REMARKS

ARROW

Each Each Lnft

White

(Bicycle & White White Yellow PED symbol)

4 752

3 3 11 000 5 000

30,027 29,700

3 3 41171 39452

3 3 80 623

3 3 84 600

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

STERLING, VIRGINIA

SUMMARIES AND SCHEDULES

SHEET 4 OF 10

(DOUBLE TURN

LANE-USE ARROW)

PMIS NPS STATE PROJECT SHEET

NO. NO. NUMBER

SEE ..2lll... NC/SC NP SER PMS FY19(3) C09 TITLE

SHEET 149713

NOTES:

1. Replace traffic detector wire loop system during pavement preservation treatment as directed by the CO and according to Detail E636-01 and E636-03.

2. Replace Speed Bump to match existing.

3. If the existing speed bumps are in good working condition, the park may salvage the materials.

SCHEDULE A 4. Place new wheelstops according to Detail E609-02A.

Remove and Replace wheelstops as directed

MISCELLANEOUS SUMMARY by the CO.

Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item Pay Item

15706-1000 20301-3410 20301-3600 20301-3900 20302-2600 20303-1600 60915-1000 60920-0000 63328-0000 63406-0000 63502-2000 63602-6020 c:i REMOVAL OF

TEMPORARY

SYSTEM

z SOIL EROSION REMOVAL OF TRAFFIC

PARK ROUTE NO. ROUTE NAME II) CONTROL, REMOVAL OF RAISED

PAVEMENT REMOVAL OF REMOVAL OF

WHEELSTOP, RESET SPEED

RAISED

CONTROL,

INSTALLATIO REMARKS

II) MARKINGS, PAVEMENT PAVEMENT, PAVEMENT N, TRAFFIC

:E INLET SPEED BUMP PAVEMENT CONCRETE WHEELSTOP BUMP PORTABLE

PROTECTION MARKER

SYMBOLS MARKINGS ASPHALT MARKER

CHANGEABLE

DETECTOR

AND WORDS

MESSAGE SIGN

WIRE LOOP

Each Each Each Each Lnft Sqyd Each Each Each Each Each Each

CARL CARL-0400AZ FRONT DRIVE ENTRANCE 79187 3 2

CARL CARL-0400BZ THEY 79187 1

CARL CARL-0900 VISITOR PARKING LOT 79060 3 8 660

COWP COWP-0010 MAIN ENTRANCE ROAD 75891 4,752

COWP-0011 TOUR ROAD 75894 2 6 16,000 32 2

Remove and add new Speed

COWP Burno

COWP COWP-0200 PICNIC AREA LOOP 75896 144

COWP COWP-0900 VISITOR CENTER PARKING 75898 11 5 3,047

COWP COWP-0903 OVERLOOK NUMBER 1 PARKING 75906 482

COWP COWP-0904 SCRUGGS HOUSE PARKING 75907 1 1,255

COWP COWP-0905 BATTLEFIELD PARKING NUMBER 1 75909 1 1,545

COWP COWP-0906 BATTLEFIELD PARKING NUMBER 2 75911 1 521

COWP COWP-0907AZ PICNIC AREA PARKING G 75914 49

COWP COWP-0907Z PICNIC AREA PARKING A 75914 2 302 6

COWP COWP-0908Z PICNIC AREA PARKING B 75914 93 3 3

COWP COWP-0909Z PICNIC AREA PARKING C 75914 1 200 1 2

COWP COWP-0910Z PICNIC AREA PARKING D 75914 2 58 5

COWP COWP-0911Z PICNIC AREA PARKING E 75914 148 3 6

COWP COWP-0912Z PICNIC AREA PARKING F 75914 1 191

COWP COWP-0914 TRAILHEAD PARKING 113293 8 1,024

KIMO KIMO-0010 MAIN PARK DRIVE 42951 1 210 59,727 210 4

KIMO KIMO-0900 VISITOR CENTER PARKING 54287 11 8 2,279

KIMO KIMO-0903 HEADQUARTERS PARKING 54290 1 355 15

Subtotal this sheet 31 2 210 44 92,832 32 13 31 2 210 2 4

Rounded Total 32 2 210 45 100,000 35 13 31 2 210 2 4

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

STERLING, VIRGINIA

SUMMARIES AND SCHEDULES

SHEET 7 OF 10

(REMOVE & RESET)

PMIS NPS STATE PROJECT SHEET

NO. NO. NUMBER

TtfCE ..2.1Q_

SHEET 149713

NC/SC NP SER PMS FY19(3) C10

NOTES:

1. Replace traffic detector wire loop system during pavement preservation treatment as approved by the CO and according to Details E636-01 and

SCHEDULE B

E636-03.

MISCELLANEOUS SUMMARY

2. Replace Speed Hump to match existing.

3. Mount and install all signs accordance with Detail E633-01.

Pay Item Pay Item Pay Item Pay Item Pay Item

20301-3900 20302-2600 60920-0000 63304-0900 63312-0000 4. If the existing speed humps are in good working c:i REMOVAL OF condition, salvage them as directed by the CO.

z SIGNS, PARK ROUTE NO. ROUTE NAME Ul

PAVEMENT REMOVAL OF

RESET ALUMINUM REMARKS

Ul MARKINGS, PAVEMENT SPEED HUMP :E

SYMBOLS AND MARKINGS

WHEELSTOP PANELS, TYPE

IL

3 SHEETING

WORDS

Each Lnft Each Sqft Each

CONG CONG-0100

LONGLEAF CAMPGROUND ACCESS

241978 48

ROAD

CONG CONG-0010 NATIONAL PARK ENTRANCE ROAD 49065 2 12770 25 2 New Speed Hump at NPS Route 10 & Bluff Trail, W17-1

CONG CONG-0900

VISITOR CENTER PARKING AREA -

49064 2 710 31

FIRST LOT

CONG CONG-0901

VISITOR CENTER PARKING AREA -

225801 2 1350 24

BUS LOT

CONG CONG-0909

VISITOR CENTER PARKING AREA -

225800 1040 34

MIDDLE LOT

Subtotal this Sheet 6 15,918 89 25 2

Rounded Total 7 17,000 89 28 2

SCHEDULE C

MISCELLANEOUS SUMMARY

Pay Item Pay Item Pay Item

15706-1000 20301-3900 20302-2600 c:i REMOVAL OF z

PARK ROUTE NO. ROUTE NAME Ul

SOIL EROSION PAVEMENT REMOVAL OF REMARKS

Ul CONTROL, INLET MARKINGS, PAVEMENT :E

PROTECTION SYMBOLS AND MARKINGS IL

WORDS

Each Each Lnft

CARL CARL-0901 ADMINISTRATIVE PARKING 79184 1 1 330

CARL CARL-0902 MAINTENANCE AREA 79185 20

COWP COWP-0401 MAINTENANCE AREA ACCES ROAD 104862 2,590

COWP COWP-0902 MAINTENANCE AREA 75904 9

KIMO KIMO-0901 MAINTENANCE AREA 54288 2 500

Subtotal this sheet 3 1 3,449

Rounded Total 3 2 3,800

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

STERLING, VIRGINIA

SUMMARIES AND SCHEDULES

SHEET 8 OF 10

File details come from the government source that posted it. Updated .