PROJECT_DESCRIPTION.pdf
PDF 190 KB Posted
- Attached to
- WA NPS OLYM 2017(1), Spruce Railrod Trail Segment B Federal contract opportunity
- Solicitation number
- 69056719B000004
About this file
This document outlines a federal construction project solicitation for the Spruce Railrod Trail Segment B located in Olympic National Park, Washington. The project involves construction of a 4.2 mile segment of ADA accessible trail, including a 125-foot prefabricated steel bridge and other earthworks, drainage, and slope stabilization elements. The estimated price range for the project is between $3 million to $5 million, with a tentative completion date of Fall 2020. The solicitation is offered through full and open competition on an unrestricted basis by the Department of Transportation Federal Highway Administration.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WA NPS OLYM 2017(1), Spruce Railrod Trail Segment B, Callam County, Washignton.
The project includes construction of a single span, 125-foot long pre-fabricated steel bridge. Abutments are founded on micro-piles and other small items of work.
Project length: 4.2 Miles
Tentative Fixed Completion Date: Fall 2020 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $3 million to $5 million
Location: 20 Miles West of Port Angeles, Washington
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
Ba se
S ch ed ul e
Op tio n Z
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes Yes 154 Contractor Sampling & Testing (yes/no) Yes No 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes No 157 Soil Erosion & Sediment Control Silt Fence Fiber Roll
500 LF
200 LF
DIVISION 200 – Earthwork 201 Clearing & Grubbing 2.1 AC 203 Removal of Pipe Culvert 1 EA 204 Roadway Excavation Unclassified borrow Rock Excavation Backfill, granular
9900 CY
300 CY
20 CY
70 CY
35 CY
207 Separation-stabilization geotextile, class I Type a nonwoven 15,500 SY 208 Structure Excavation Shoring and bracing
90 CY
LPSM
212 Linear Grading 2 MILE
S ch ed ul e
Op tio n Z
DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap, class 2 Riprap Class 3
50 CY
500 CY
255 Mechanically Stabilized Earth Walls (contractor designed) 5917 SF 257 Contactor-Designed Retaining Walls (contractor completed designs) LPSM 260 Rock Bolts Rock Dowels (exterior) Rock Dowels (interior)
3300LF
776 LF
1420 LF
DIVISION 300 – Aggregate and Base Courses 302 Roadway Aggregate, Method 2 7100 T 2300 T
DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete pavement 3400 T
DIVISION 550 – Bridge Construction 552 Structural Concrete, Class A Expansion Joints
26 CY
24 LF
554 Reinforcing Steel 2700 LB 555 Prefabricated Steel Bridge LPSM 556 Bridge Railing 240 LF 557 Structural Timber and Lumber, untreated 1.1 MFBM 566 Shotcrete 955 SY 567 Micropiles 128 LF
DIVISION 600 – Incidental Construction 602 12” Pipe culvert 24” pipe culverts 24” End Sections
360 LF
12 EA
10 LF
605 Geocomposite Sheet Drains 40 SY 609 Wheelstop, concrete 20 EA 610 Drainage Weep Hole 70 EA 621 Monuments & Markers (construction survey & staking) (yes/no) Yes Yes
S ch ed ul e
Op tio n Z
622 Rental Equipment (yes/no) Yes Yes 623 General Labor (yes/no) Yes Yes 623 Special Labor, Slope Scaling 920 Hour 624 Topsoil (landscaping & related items) 9400 SY 625 Mulching, Dry method (indicate seeding or mulching separately)
1.8 AC
0.5 AC
633 Permanent Traffic Control (traffic control devices) 20 SF 634 Permanent Pavement Markings Accessibility Symbol
890 LF
2 EA
635 Temporary Traffic Control LPSM LPSM 647 Mitigation, Landscaping Log 35 EA 651 Draped Rockfall Protection Midslope Rockfall Attenuator
6870 SY
200 SY
| DIVISION 200 – Earthwork |
| DIVISION 250 – Slope Reinforcement and Retaining Walls |
| DIVISION 300 – Aggregate and Base Courses |
| DIVISION 400 – Asphalt Pavements & Surface Treatments |
| DIVISION 550 – Bridge Construction |
File details come from the government source that posted it. Updated .