T10__Amend_1__Elevators.pdf

PDF 3 MB Posted

Attached to
Elevator Modernization - RC White Federal Building Federal contract opportunity
Solicitation number
47PH0419R0006
Issued by
General Services Administration Public Buildings Service Region 7

About this file

Amendment 0001

View the file

Other files for this federal contract opportunity

Other files attached to Elevator Modernization - RC White Federal Building, newest first.
File Type Posted
T10__RFP__Elevators.pdf PDF
Proposal_Form_TX.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

7PQC-MC

Rosalva Ramos, Contracting Officer

Please see attached

7PQC-MC

Acquisition Management Division Non-Prospectus Branch 1101 East Hackberry, Suite 200 McAllen, TX 78501 USA

Acquisition Management Division Non-Prospectus Branch 1101 East Hackberry, Suite 200 McAllen, TX 78501 USA

EQ7PSBBE-19-00166

1 2

04/17/19

/2018

9A. AMENDMENT OF SOLICITATION NO.

47PH0419R0006

9B. DATED (SEE ITEM 11)

03/19/2019

Description of Amendment/Modification

RFP No. 47PH0419R0006 - Elevator Modernization - RC White Federal Building, El Paso, Texas

This amendment is issued to incorporate the following documents and to extend the proposal due date to Friday, May 3, 2019.

- RFI Log dated 04/16/19

- Pre Proposal Conference Meeting Minutes

- Specifications - Revisions to Section 19 Controller, Section 20 Solid Motor Drive and Section 47 Door Operator

All other terms and conditions remain unchanged.

47PH0419R0006/0001

REQUEST FOR INFORMATION LOG

April 16, 2019

Project Title: Elevator Modernization Project Location: RC White Federal Building, El Paso, Texas RFI # Requested by RFI Question RFI Answered

Incorporated on Amendment 0001

1 William Harrison Group If awarded the contract what percent of the price is required for the performance bond? 100% of the contract amount

2 William Harrison Group Who is the fire service vendor? Western States Fire Protection

3 Thyssenkrupp Elevator Are there any contractors that are GSA site approved for the related work? GSA doesn't have any approved contractors

4 Thyssenkrupp Elevator Can you please contact information for the existing Fire Alarm company?

Eddie Avalos, eddie.avalos@wsfp.us, Phone 915-772-7001, Cell 915- 490-2856

5 Information Requested at Pre-bid

Location of the electrical service that provides power to the elevators and shaft lighting.

See Attached RFI 5 Elevator Power, Panel ELB, 3rd Floor Electrical Room

6 Information Requested at Pre-bid Building height and floor elevations. See Attached RFI 6 Building Section with Elevations

7 Thyssenkrupp Elevator Request For time extension to Bid date Bid date is extended to Friday, May 3, 2019

8 Thyssenkrupp Elevator Please provide a list of GSA-approved vendors for the RC White Federal Building to bidders including electrical, fire-life-safety, general contracting, flooring, etc. vendors.

GSA does not provide a list of approved contractors. It is the contractors responsibility to research and work with responsible sub-contractors that are qualified to perform the work required to provide a complete project.

9 Thyssenkrupp Elevator General: Recognizing the importance of the successful contract providing the least most disruptive modernization project to your building tenants, please specify what work falls under this criteria that must be scheduled at times other than normal duty hours.

Any work that may disrupt the normal operations of the building. Work that generates excessive noise, creates a safety hazard to building occupants and visitors, delivery of materials through public areas during normal business hours, shutdown or disruption of building utilities or life safety devices, electrical power, 10 Thyssenkrupp Elevator Scope of Work -Other Requirements (11.1.6): Is the GSA aware of the existence of any asbestos and/or lead paint within the facility? Please provide any existing asbestos and lead paint condition reports for the building.

Procede under the assumption that there is no issue with Lead paint or Asbestos in the Elevator Equipment Room of the elevator hoistways.

11 Thyssenkrupp Elevator Section 14210-General (1.3): It appears that this section calls for retaining both main and counterweight rails and hoistway entrance sills, headers, and fascias. Does this

YES

12 Thyssenkrupp Elevator Section 14210-9. Maintenance (9): Will bidders be required to demonstrate full maintenance support of the RC White Federal Building through existing service routes, local supervision, offices and personnel in the El Paso area and a dedicated project manager?

YES

13 Thyssenkrupp Elevator Section 14210-9. Maintenance (9.1): Please confirm that full interim maintenance costs for each of the five (5) elevator units is to be included in the base proposal pricing based on the noted schedule of 730 calendar days.

Interim maintenance starts upon manning the job, ends at substantial completion of all elevators. One year warranty period starts then.

14 Thyssenkrupp Elevator Section 14210-11. Power Supply (11.4): Please confirm that emergency power exists for the elevators and how many elevators currently operate under emergency power operation.

All existing elevators are fed from Panel EDP in the main electrical room next to the Generator. EDP is supplied through the ATS and are connected to the building generator. See response to RFI 5.

15 Thyssenkrupp Elevator Section 14210-13. Electrical Feeders and Wiring (13.3): The specification indicates to install new “energy efficient” light fixtures in both the machine room and hoistways. Is the GSA requiring the installation new LED fixture assemblies in these locations?

Specs require "energy efficient" Provide the most energy efficient possible. LED fixtures are acceptable for use at both locations.

16 Thyssenkrupp Elevator

Section 14210-13. Electrical Feeders and Wiring (13.3): The specification indicates to provide a labelled, lockable disconnect in the machine room for the new “energy efficient” lighting. Does this section require that the hoistway light fixtures be part of the machine room lockable disconnect noted or just the machine room lighting? If so, where does the existing wiring for the existing hoistway lighting (currently installed) go to within the building now?

The labeled, lockable disconnect in the machine room is to control the new hoistway lighting. The existing lighting is fed from Panel "ELB" in the electrical closet on the 3rd floor to the west of the elevator shafts.

1 of 5Page 3 of 65

RFI # Requested by RFI Question RFI Answered Incorporated on Amendment 0001

17 Thyssenkrupp Elevator

Section 14210-17. Geared Machine (17.1): Are there any considerations for value engineering (VE) alternate opportunities with the existing machines (i.e. a geared to gearless machine replacement application)? If so, are bidders allowed to cover such VE alternates in their bid letter for potential consideration?

Absolutely. Provide as specified, with value engineering alternative or option.

18 Thyssenkrupp Elevator

Section 14210-17. Group Automatic Operation (17.5): The specifications indicate to replace new vibration isolation machine pads as needed to prevent transmission of machine vibration to the building structure. Has there been any issue, report or complaint of machine vibration on any of the five (5) elevators?

None to our knowledge. The intent is to provide "like new" equipment. If isolation looks bad, replace.

19 Thyssenkrupp Elevator Section 14210-24. Machine Room and Hoistway (24.7): Which company maintains the existing HVAC unit to the machine room and what is their contact information?

There is no existing HVAC supplying the Elevator Equipment Room.

The only air provided to the space is from an exhanust fan that draws air from the building plenum.

20 Thyssenkrupp Elevator Section 14210-24. Machine Room and Hoistway (24.7): What are the existing specifications/duty and BTU-rating of the machine room HVAC unit(s)?

Bidder to calculate heat load and size of new HVAC equipment based upon new elevator equipment needs.

21 Thyssenkrupp Elevator Section 14210- 25. Emergency Power Operation (25.2): Which company maintains the existing emergency power system and what is their contact information?

Allegiant Facilities Services (Juan Galindo, PM 915-351-2700 & Diana Davis, CO 210-279-3192

22 Thyssenkrupp Elevator Section 14210- 25. Emergency Power Operation (25.2): Is there pre-existing “pre-signal” wiring/feature present between the existing automatic transfer switch (ATS) and the elevator controllers/machine room for emergency power?

All elevators feed from the emergency panel located in the main electrical room on the first floor. See response to RFI 5. There does not appear to be any additional signal wire.

23 Thyssenkrupp Elevator Section 14210-40. Telephone (B): Is there an existing dedicated telephone line for each elevator? YES, There is an individual phone line for each elevator.

24 Thyssenkrupp Elevator Section 14210-40. Telephone (B): Which company services the existing telephone lines for each elevator and what is their contact information?

AT&T is the provider for the elevator phone lines.

GSA POC for Phonelines Richard De La Garza | Phone: 817-850-5564 Project Manager | 819 Taylor Street, Fort Worth, TX 76102

25 Thyssenkrupp Elevator

Section 14210-43. Signal System (43.3): The specifications do not appear to indicate how to handle the existing hall lanterns and digital position indicators existing on the 1st floor. Are bidders to provide a replacement combination hall lantern/digital position indicator fixture at the 1st floor on all elevators?

Spec section 43.3 states: "The existing lanterns may be replaced or reused if provided with new electronic chimes and LED lighting is used."

26 Thyssenkrupp Elevator

Section 14210-43. Signal System (43.8): The existing walls appear to be solidconcrete and according to the specifications, all signal fixtures are be flush-mounted. Are bidders allowed to utilize the existing signal fixture back/electrical boxes and cover any cutting/patching after the fact if this allows ADA/Code-compliance? Or will bidders be allowed to utilize matching surface mount hall station fixtures?

The intent is to provide flush mounted fixtures. How the work is performed is up to the bidder. We require code legal and flush mounted fixtures.

27 Thyssenkrupp Elevator

Section 14210-45. Smoke Detectors and Annunciators (45): Section 14210 under Related Work (2.1.F) states to remove all sprinkler piping from machine room. However, under section 14210 (45.1.D) it calls to provide heat detectors within six (6) inches of every sprinkler head within each machine room. Based on this apparent contradiction within the specifications, what scope of work are bidders to include in their pricing?

Removal of all sprinkler piping in machine room, hoistways, and/or pits.

28 Thyssenkrupp Elevator Section 14210-45. Smoke Detectors and Annunciators (A): Which company currently services the existing fire alarm/fire-life-safety system for the building and what is their contact information?

Tyco Integrated Security, POC Pamela Lopez, Office Phone (915) 342-

29 Thyssenkrupp Elevator

General Information. Section I.F. FAR 52.228-1 Bid Guarantee (Sep 96): The bid documents appear to request a bid bond be submitted with the bid response by contractors. Are bidders to use their standard bid bond form provided by their surety company to meet the 20% of the bid price or $3M – whichever is less?

Yes, bidders are to use the standard bid bond provided by the surety company for 20% of the bid price or $3 Million, whichever is less.

2 of 5Page 4 of 65

RFI # Requested by RFI Question RFI Answered Incorporated on Amendment 0001

30 Thyssenkrupp Elevator IV Contract Clauses, IV.A. (6) Buy American Requirements (pgs. 93- 96): Please confirm that the noted “Buy American” requirements within this section applies to this specific project.

The Buy American Requirements do apply. Exceptions can be made based on availability and quality of components to the overall system.

31 Thyssenkrupp Elevator Solicitation, Offer, and Award Form – The form indicates that the project must be completed within 730 calendar days. Please provide a breakdown of the expectation of milestones for this 730-calendar day installation time frame.

It is the contractor’s responsibility to provide a timeline and milestone schedule based on the 730 day time window with their proposal that completes all work including design, fabrication and installation.

3 of 5Page 5 of 65

RESPONSE TO RFI 5

4 of 5Page 6 of 65

RESPONSE TO RFI 6 BUILDING ELEVATIONS

5 of 5Page 7 of 65

Pre-Proposal Conference Meeting Minutes

Date and time: April 3, 2019 at 1:00 PM MST) Solicitation: 47PH0419R0006 Project Description: Design/Build Modernization of 4 Passenger elevators and 1

Freight elevator at the RC White Federal Building Location: GSA Offices

700 E. San Antonio St Suite 403 El Paso, Tx Phone Conference (Call in 844-419-4704 Participant Code 5467708869)

Contracting Officer: Rosalva Ramos COR/Project Manager: George Seibert GSA Building Manager: Silvia Terrazas

Attendees: Sign-in Sheet attached

Topics of Discussion

General Scope:

The work includes the design and construction services for the replacement and modernization of 4 passenger elevators and 1 service elevator at the RC White Federal Building, El Paso, Texas.

Review of Solicitation I. Project Information

A. Project Summary – Reviewed basic project intent. Directed contractors to the RFP for a more detailed description of the requirements.

B. The Contract - Reviewed basic contract intent. Directed contractors to the RFP for a more detailed description of the requirements.

C. Period Of Performance

1. Overall Period of Performance including security clearances, design, fabrication and installation is 730 calendar days.

D. Work Conditions/Site Requirements

1. The building hours are 8:00 am to 5:00 pm

2. The contractor’s work hours are at his discretion. The GSA PM will need to be informed of off hours work so the Building Manager and tenants can be kept informed.

3. Any work that may cause disruption to the daily operations must be scheduled during off hours. Contractor to plan for off hours in their proposal.

4. Work will be phased to take only 1 elevator off line at a time to minimize impact to the daily operation of the building. (See Section 14120 – General: Paragraph 1.2)

5. The contractors were informed that the site is very tight with limited access.

6. No set down or full time staging is available. Staging/storage will be allowed on a limited basis in the area of the loading dock.

7. Use of the loading dock and service entrance will be allowed for deliveries.

Access to the loading dock must be coordinated with Federal Protective Services.

8. In the event that the contractor needs to place a dumpster for debris, it is their responsibility to work with the City of El Paso to permit the street area to be utilized.

1 of 3Page 8 of 65

Due to the building security, the only street placement will be on the east side of the building near the loading dock.

9. There is no onsite parking available. The contractor will be responsible for their own parking.

E. Authorized Representatives (the role of each was discussed) Rosalva Ramos, GSA Contracting Officer.

George (Fred) Seibert, GSA Contracting Officers Representative Silvia Terrazas, GSA Building Manager.

Scott Cumby, GSA Subject Matter Expert

F. Contract Liquidated Damages Rate - Confirmed as $360 per calendar

G. Buy American Exceptions (defined in the Solicitation under Section IV)

H. Statement of Work, Specifications, Drawings, Exhibits and Other Attachments Refer to the Solicitation package for all documents

II. Prices Proposals to be provided as specified under Section II.B. Proposal Format as detailed on starting on Page 111 of the solicitation package. (Price Proposal Volume 1 and Technical Proposal Volume 2) Volumes 1 and 2 to be submitted in separate sealed packages. The initial review will be of Volume 2, Technical Proposal. Bidders will be rated based on their qualifications in Volume 1 prior to review of the proposal pricing Volume 2.

Final award to be based on Best Value to the Government.

A. Basis of Pricing B. Contract Price Form

The overall Contract terms and conditions were not reviewed. The contractors were instructed to follow the requirements as specified in the solicitation and to review all information related to the contract.

Ill. Terms and Conditions A. Commencement, Prosecution and Completion of Work B. Contractor Responsibilities C. Contractor Management and Personnel D. Project Schedule E. Extensions of Time F. Interpretation of Specifications and Drawings G. Submittals H. Substantial Completion and Contract Completions I. Use and Possession Prior to Substantial Completion J. Finality of Contract Modifications K. Liquidated Damages L. Insurance Requirements M. Order of Precedence N. Administrative Matters

0. Non-Compliance with Contract Requirements P. Safeguarding Sensitive Data and Information Technology Resources Q. Options and Allowances

2 of 3Page 9 of 65

IV. Contract Clauses A. Clauses Incorporated in Full Text B. Additional Clauses C. Clauses Incorporated by Reference

Clarifications:

RFIs: There are currently 2 RFI responses pending. The contractors were encouraged to review all documents and information provided with the solicitation and at the Pre-proposal meeting. Send all questions to Rosalva Ramos and cc: Fred Seibert no later than April 11, 2019. An amendment will be issued with a response to all RFIs received.

Did date remains April 26, 2019

1. Conducted site inspection with interested contractors.

Contractors were reminded that this will be the only opportunity they will have to verify site conditions.

Questions during walk-thru:

1. Location of the electrical service that provides power to the elevators and shaft lighting.

Will be researched and information on the existing service provided.

2. Building height and floor elevations. A building elevation with this information will be provided.

3 of 3Page 10 of 65

RC White FOB ELEVATOR MODERNIZATION RTX El Paso, TX TX0272ZZ

ELECTRIC ELEVATORS 14210 - TABLE OF CONTENTS 1

SECTION 14210

ELECTRIC ELEVATORS

TABLE OF CONTENTS

1. GENERAL: --------------------------------------------------- 1

2. RELATED WORK: --------------------------------------------- 3

3. STANDARD REFERENCES: -------------------------------------- 4

4. QUALIFICATIONS: -------------------------------------------- 4

5. SHOP DRAWINGS --------------------------------------------- 5

6. SAMPLES --------------------------------------------------- 7

7. MANUALS --------------------------------------------------- 7

8. WARRANTY AND GUARANTEE ---------------------------------- 8

9. MAINTENANCE ---------------------------------------------- 8

10. INSTRUCTIONS ----------------------------------------------- 9

11. POWER SUPPLY ---------------------------------------------- 9

12. CAPACITY, SPEED, TRAVEL, PLATFORM SIZE --------------------- 10

13. ELECTRIC FEEDERS AND WIRING ------------------------------ 10

14. ACCESSORIES ---------------------------------------------- 12

15. PAINTING AND FINISHING ------------------------------------- 14

16. MACHINE BEAMS AND OTHER SUPPORT STEEL ------------------- 14

1 of 55Page 11 of 65

ELECTRIC ELEVATORS 14210 - TABLE OF CONTENTS 2

17. GEARED MACHINE ------------------------------------------ 15

18. CONTROLLER ---------------------------------------------- 16

19. SOLID STATE MOTOR DRIVE (SCR DRIVE) ------------------------ 17

20. CAR LIGHTING AND FAN CONTROL ----------------------------- 18

21. GROUP AUTOMATIC OPERATION ------------------------------- 18

22. MICROPROCESSOR GROUP SUPERVISORY CONTROL -------------- 20

25. EMERGENCY POWER OPERATION ------------------------------ 24

26. GROUP CAR CONTROL FUNCTIONS ----------------------------- 24

27. INDIVIDUAL CAR CONTROLLER -------------------------------- 26

28. COMPUTING ENVIRONMENT ---------------------------------- 27

29. GUIDE RAILS ----------------------------------------------- 28

30. SAFETY AND GOVERNOR ------------------------------------- 28

31. HOISTING AND GOVERNOR ROPES ------------------------------ 30

32. COUNTERWEIGHT ------------------------------------------- 30

33. CAR AND COUNTERWEIGHT BUFFERS --------------------------- 30

35. TERMINAL STOPPING DEVICES -------------------------------- 31

36. ROLLER GUIDE ASSEMBLIES ---------------------------------- 31

37. CAR FRAME AND PLATFORM ---------------------------------- 32

2 of 55Page 12 of 65

ELECTRIC ELEVATORS 14210 - TABLE OF CONTENTS 3

38. ELEVATOR CARS -------------------------------------------- 32

39. FINISH OF CAR FIXTURES ------------------------------------- 35

40. EMERGENCY CAR LIGHTING ---------------------------------- 36

41. TELEPHONE ------------------------------------------------ 36

42. CERTIFICATE FRAME ---------------------------------------- 37

43. WALL PROTECTION PADS ------------------------------------- 37

44. SIGNAL SYSTEM --------------------------------------------- 38

46. EMERGENCY RECALL OPERATION ----------------------------- 39

47. SMOKE DETECTORS AND ANNUNCIATORS ----------------------- 40

48. PASSENGER ELEVATOR HOISTWAY ENTRANCES ------------------ 41

49. DOOR OPERATORS ------------------------------------------ 43

50. INTERLOCKS AND CONTACTS --------------------------------- 44

50. INDEPENDENT SERVICE -------------------------------------- 45

52. TESTS ----------------------------------------------------- 45

3 of 55Page 13 of 65

ELECTRIC ELEVATORS 14210 - 1

SECTION 14210

ELECTRIC ELEVATORS

Passenger Elevator Nos. 1-4

Service Elevator No. 5

1. GENERAL:

1.1 This section of the specification includes the furnishing of all material and performance of all work required for the removal of existing elevator equipment and installation of new equipment to provide four (4) geared traction passenger elevators and one (1) geared traction service elevator. The passenger elevators are arranged in one group.

1.2 No more than one elevator shall be taken out of service during the normal working hours of the building to perform this work. Any noisy or disruptive work will be performed after the normal working hours of the facility. Include all after hours work within the proposal.

1.3 Equipment to be reused: The following existing equipment may be reused with certain repairs, modifications or adjustments as hereinafter specified:

A. Machine Room:

1. Machine Beams.

2. Geared Machines (New AC Motors)

3. Car frame, platform.

B. Hoistway:

1. Main and counterweight rails.

2. Hoistway entrance sills, headers, and fascias.

3. Counterweight frames and counterweights.

C. All other components of the elevator system shall be installed new, whether or not specifically mentioned in the specifications, in order to provide five (5) complete elevator units.

1.4 All parts of the elevator equipment shall be of such design, size and material as to satisfactorily function under all conditions of loading and operation with specified rated load and rated speed range. All parts shall be built to standard dimensions, tolerances and clearances so that similar parts of similar machines and devices are completely interchangeable. The mechanical fastenings used throughout the equipment on parts subject to wear and requiring replacement shall be key and seat, nut, screw, or other removable and replaceable type not requiring physical deformation or field positioning. The use of rivets or similar devices will not be accepted as mechanical fastenings for such parts.

4 of 55Page 14 of 65

ELECTRIC ELEVATORS 14210 - 2

1.5 The major elevator components shall be the products of one manufacturer of established reputation, except they may be the products, either wholly or in part, of another manufacturer of established reputation provided such items are engineered and produced under coordinated specifications. Also, the major components to be furnished shall be of a make or makes that have performed satisfactorily together under conditions of normal use in not less than two other elevator installations of equal or greater capacity and speed for a period of at least one year. Prior to award, the names and addresses of the buildings and the names of the owners or managers thereof, in which the proposed combination of major components has so performed, shall be furnished.

A. The term "major elevator components" as mentioned above shall mean such items as an elevator hoisting machine, motor drive, controller, selector, and group supervisory control equipment.

1.6 Equipment in the elevator machine room shall be so arranged that such items as rotating elements and sheaves can be removed for repairs or replacement, either by trolley hoist and dolly, or other conventional means, without dismantling or removing other equipment components in the machine room.

1.7 Adequate work space for maintenance and repair operations shall be provided around the elevator equipment in machine room with clear passage to any access or trap doors.

1.8 Where practical, elevator controllers shall be located near, and in the same positions relative to the driving machines they control. The driving machine shall be visible from its controller.

1.9 Trolley beams shall not be utilized as the normal support of elevator equipment such as sheaves for selector cable.

1.10 Elevator data requirements listed below shall be obtained from either the project drawings or within this specification:

A. Elevator Data:

1. Elevator rated load lifting capacity in pounds.

2. Elevator car rated speed in feet per minute.

3. Car travel in feet.

4. Number of landings.

5. Number of openings.

6. Platform size.

7. Class of service, i.e., passenger or freight.

8. Type of machine, i.e., geared or gearless.

9. Type of control, i.e., rheostatic, generator field, or static (3vf Drive).

5 of 55Page 15 of 65

ELECTRIC ELEVATORS 14210 - 3

10. Type of operation, i.e., two stop single car selective collective, two car selective collective or group automatic.

11. Type of design of passenger car.

12. Type of hoistway doors.

13. Type of hoistway door operation.

14. Type of car door or gate.

15. Type of car door or gate operation.

16. Type of signal system.

17. Characteristics of power supply.

18. Finishes.

1.11 The elevator system shall consist of:

A. Four (4) geared electric passenger elevators operating in one group.

B. One (1) geared electric service elevator.

2. RELATED WORK:

2.1 The following related work is included in this section and other sections of the specification and shall be the responsibility of the Elevator Contractor:

A. Elevator hoistways and their enclosures and venting, pit spaces, enclosed machine rooms, trolley beams.

B. Temporary guards at all hoistway openings as required under "Accident

Prevention" clause of the General Conditions.

C. Bevel all ledges and platforms between the hoistways at each landing to not less than 75 degrees.

D. Provide Elevator machine room energy efficient lighting and 110 GFCI outlets, energy efficient pit lighting and 110 GFCI outlets, and energy efficient hoistway lighting circuits. Pit lighting switch shall be accessible from access door.

E. Provide pans under roof drains.

F. Remove sprinklers and heat detectors from the top of the hoistways. Remove all sprinkler piping from machine room.

G. Provide all car top guardrails as required.

H. Provide HVAC for machine room.

6 of 55Page 16 of 65

ELECTRIC ELEVATORS 14210 - 4

3. STANDARD REFERENCES:

3.1 Unless as modified herein or otherwise distinctly specified, all elevator material, design, clearances, definitions, construction, workmanship and tests shall conform to the requirements of the American National Standard Safety Code for Elevators, and, Escalators, (ANSI A17.1-2016) or latest edition, including errata, interpretations and revisions and hereinafter referred to as the A17.1 Code.

3.2 Wherever Federal Specifications, Codes, Standard Details and other standards are referenced, latest editions and amendments shall apply in accordance with the clause entitled "Standard References: in the General Conditions.

3.3 References to the NEC are to the 2015 National Electrical Code (ANSI C1) or latest edition. All electrical work specified in the A17.1 Code shall be done in accordance with the 2015 NEC.

3.4 References to UL standards are to standards of Underwriters Laboratories, Inc.

3.5 References to NEMA are to Standards of the National Electrical Manufacturers

Association.

3.6 Referring to the requirements of clause entitled "Building Codes, Fees and

Charges" in the General Conditions the work shall also comply with the applicable

State and local Code requirements or regulations except the requirements of the

A17.1 Code shall govern in the event of a conflict.

3.7 References to Handicap Provisions are to "Uniform Federal Accessibility

Standard" (UFAS) and the "Americans with Disabilities Act Accessibility

Guidelines" (ADAAG). In case of conflicts in the requirements, the most stringent requirements shall be required.

4. QUALIFICATIONS:

4.1 The bidder shall have had at least five years successful experience in installing and servicing the manufacturer's elevators.

4.2 In addition, the bidder shall have comparable installations operating successfully for at least two years under bidders maintenance. To be considered comparable, prior installations shall have not less than the same number of elevators operating together in one group as the largest number in any group specified for this project, except that a group of two may be considered comparable to a larger group specified for this project.

4.3 A list of the prior comparable installations by the bidder together with the names and addresses of the buildings, the names of the owners or managers thereof, and

7 of 55Page 17 of 65

ELECTRIC ELEVATORS 14210 - 5

any other pertinent information required shall be submitted promptly upon request of the government.

4.4 The names, addresses, experience, and a statement of the work to be performed by each subcontractor be will used for performance of minor portions of the installation of elevators, shall also be submitted promptly upon request by the

Government.

4.5 The bid may be rejected if the bidder has established on former jobs, either

Government, municipal, or commercial, a record for unsatisfactory elevator installations, has repeatedly failed to complete contracts awarded to him within the contact time, or otherwise fails to meet the experience requirements of this clause.

5. SHOP DRAWINGS:

5.1 Shop drawings shall be submitted in accordance with the "General Conditions" and

"Special Conditions" sections.

5.2 Shop drawings shall include the following details as applicable to the systems specified:

A. Full dimension layout in plan and elevation showing the arrangement of equipment and all pertinent details of each elevator unit specified including:

1. Driving machine, controller, selector, motor generator, static motor drive unit, governor and other components located in machine room.

2. Car, counterweight, sheaves, supporting beams, guide rails, buffers, car and counterweight guide shoes, and other components located in hoistway.

3. Rail bracket spacing and maximum vertical forces on guide rails in accordance with the A17.1 Code.

4. Reactions at points of support.

5. Weights of principal parts.

6. Top and bottom clearance and over travel of car and counterweight.

7. Location of circuit breaker, switchboard panel or disconnect switch, light switch and feeder termination at controller.

8. Location of outlets for connection of traveling cables for car light and telephone.

8 of 55Page 18 of 65

ELECTRIC ELEVATORS 14210 - 6

9. Location of hoistway access switches.

B. Hoistway entrances and doors showing their method of operation, details of construction; and method of fastening to the structural members of the building.

C. Car designs specified, showing details of construction, fastenings to platform, car lighting, ventilation, location of all car equipment, handrails, and emergency exits including electric contacts and method of hinging and locking.

D. Details of all signal and operating fixtures including hoistway access switches.

E. Details of sound and vibration isolation units for generator sets, if used.

F. Details of roller guide assemblies.

G. Details of sill sections and supports.

H. Details of selection, recall, and emergency operation switches including wiring diagrams.

I. Other drawings required or hereinafter specified.

5.3 The name of manufacturer, type or style designation, and the additional information called for below shall be listed on the shop drawings for each of the following:

A. Driving machine.

B. Driving machine motor including hp and rpm.

C. Elevator controller.

D. Group supervisory system controller.

E. Indicator panel.

F. Car safety including maximum rated load and speed.

G. Governor.

H. Power door operator.

I. Door interlocks and electrical contacts.

J. Buffers including stroke, certified maximum and minimum loads and maximum striking speed.

9 of 55Page 19 of 65

ELECTRIC ELEVATORS 14210 - 7

K. Car ventilation blower including c.f.m. and hp ratings.

L. Car emergency lighting.

M. Static motor drive unit.

6. SAMPLES:

6.1 Referring to the "Sample" requirements of the General Conditions, submit for approval, four samples of all finishes, car floor materials, operating and signal system fixtures, hoistway entrance and door materials, sills, protection pads, and light fixture lenses.

7. MANUALS:

7.1 Three (3) sets of operating and maintenance manuals shall be furnished in bound form. Manuals shall include:

A. Description of the elevator system's method of operation and control including the functions of signals, door devices and other specified features.

B. Written instructions for the adjustment and care of the equipment.

C. Replacement parts list with part numbers.

D. Type of lubricant required for each lubricated part.

E. Complete set of as-built wiring diagrams.

7.2 The identification label for each manual shall include the subject, building name and location, government contract number and the specific elevator numbers to which the manual applies.

7.3 One set of manuals shall be provided in tool cabinet in elevator machine room unless otherwise directed. The two additional sets shall be delivered to the

Contracting Officer's Representative.

10 of 55Page 20 of 65

ELECTRIC ELEVATORS 14210 - 8

8. WARRANTY AND GUARANTEE:

8.1 All work under this section shall be subject to the terms specified under

"Guarantees" in the General Conditions and the guarantee period for an elevator unit shall be one year after the date the final elevator is placed in normal use by the

Government.

9. MAINTENANCE:

9.1 Furnish full maintenance for the elevators starting on the day the actual work begins at the site during the installation period, and for 12 months after final acceptance by the Government of the last elevator in entire project. The maintenance service shall consist of regular weekly examinations of the installation and shall include the necessary adjustments, repairs, cleaning, lubrication, and supply and replacement of all parts to keep the equipment in proper operating condition.

9.2 All routine adjustments and service shall be performed by trained employees of the elevator contractor and may be made during the regular working hours of the trade.

All services required to ensure safe and reliable performance of the elevators shall be provided by regularly assigned maintenance personnel of the elevator contractor.

9.3 Weekly preventive maintenance program shall be scheduled for each elevator. The date and hours of work shall be scheduled and submitted for approval and acceptance by the Building Manager. All personnel shall register with the proper

Government authority upon entering and leaving the building.

9.4 Provide 24-hour emergency call-back service for the maintenance period, by promptly responding to requests from the Building Manager or his authorized representative by telephone or otherwise, to restore elevator services where a shutdown or trouble should develop. This emergency call-back services shall be limited to minor adjustments required to protect the immediate safety of the equipment and persons in and about the elevator. Contractor shall respond to emergency call backs in one hour or less.

A. The Contractor shall provide and keep current a suitable check chart for each elevator. The charts shall be posted in the machine rooms on which entries shall be made to indicate the status of scheduled items of maintenance work performed, and the time in man-hours. The Contractor must properly initial the chart to indicate that the work has been accomplished.

B. The Contractor shall immediately notify the Contracting Officer (in writing) of the existence or the development of any defects in, or repairs required to the elevators which the Contractor considers he is not responsible for under the terms of the contract, and shall furnish him a written estimate of the cost to make necessary repairs. The Contracting Officer reserves the right to make final determination as to responsibility.

11 of 55Page 21 of 65

ELECTRIC ELEVATORS 14210 - 9

10. INSTRUCTIONS:

10.1 The instruction period for Government employees shall be not less than one (1) eight hour day for the work under this section. Manual and wiring diagram instructions given in elevator machine room will be considered the equivalent to classroom instructions.

10.2 Submit outline of instructions to be given, one (1) month prior to the Instruction

Period, for approval.

10.3 Instructions shall be completed before the warranty and maintenance period expires.

A. If the instructions have not been completed prior to the termination of the maintenance period, that period shall be extended as a part of the contractual requirements until the instruction requirements have been satisfied.

10.4 Provide, without additional expense to the Government, competent instructors to train employees of the Government, in the care, adjustment and operation and sequence functioning of the operation and the control system. Instruction shall be given during regular working hours and take place at the job site. The instruction shall be by qualified, factory trained engineering representatives possessing complete knowledge of the care, adjustment and operation of the elevator system.

A. Approximately half of the time shall be used for classroom instructions. All other time shall be used for instruction at the equipment. Where significant changes or modifications in equipment are made under the terms of the guarantee, additional instruction shall be provided as may be necessary to acquaint the operating personnel of the changes or modifications.

B. Three copies of an operating and maintenance manual, prepared by the contractor, shall be utilized by the contractor for instruction purposes. After completion of all instructions, the three copies of the manual shall be turned over to the Building Manager.

C. Three sets of as-built wiring diagrams with a complete description of operating sequences shall be furnished and delivered to the Construction

Engineer fifteen (15) days prior to the start of the instructions, for use of the instructors.

D. The time and place of the instructions shall be coordinated with the Building

Manager.

11. POWER SUPPLY:

12 of 55Page 22 of 65

ELECTRIC ELEVATORS 14210 - 10

11.1 The power available is 3 phase, 60 hertz, 480 volts alternating current for elevator power and single-phase, 60 hertz 120 volts alternating current for elevator car lighting.

11.2 Before any electrical equipment is manufactured or purchased, the characteristics available for elevator power and lighting shall be verified. Where characteristics are different from those specified above, the equipment shall be furnished for the power as verified by the contractor.

11.3 Failure to verify the power supply shall not relieve responsibility for the satisfactory operation of the equipment.

11.4 Controls shall have provisions for sequential return of all elevators and operation elevators on Emergency Power.

12. CAPACITY, SPEED, TRAVEL, PLATFORM SIZE:

12.1 The elevators shall have a capacity to lift the rated load at the rated speed in feet per minute, specified in the following schedule. The rated load shall be exclusive of the weight of the complete car and cables. The travel, terminal floors, number of stops and openings and the over-all car platform size given in the schedule shall be verified with requirements indicated on the drawings.

ELEVATOR SCHEDULE

RATED RATED OVERALL

ELEVATOR LOAD SPEED TERMINAL NO. OF NO. OF PLATFORM SIZE

NUMBER LBS. F.P.M. FLOORS STOPS OPENINGS WIDTH X DEPTH

1-4 3,500 350 1-7 7 7 RETAIN EXISTING

5 6,000 350 1-7 7 7 RETAIN EXISTING

13. ELECTRIC FEEDERS AND WIRING:

13.1 Retain the existing electric disconnect switches in both machine rooms for elevator power supply for all elevators, unless a change is needed for the new VVVF-AC drive system and new controls.

13.2 Provide new disconnects for the existing 110 Volt A.C. power supply for car light circuits for all elevators. New disconnects shall be labeled, located in the machine room, and lockable in the off position

13 of 55Page 23 of 65

ELECTRIC ELEVATORS 14210 - 11

13.3 Provide new energy efficient light fixtures with guards in the elevator machine rooms. Provide all hoistways with energy efficient fluorescent fixtures with a labeled, lockable disconnect in the machine room. Energy efficient fixtures in the hoistway shall be located at each landing.

Conduits and fittings shall be in accordance with the following Federal

Specifications:

A. Threaded steel conduit WW-C-581E

B. Electrical metallic tubing (EMT) WW-C-563A

C. Flexible metal conduit WW-C-566C

D. Fittings for cable and flexible conduit W-F-406B

E. Fittings for conduit W-F-408C

13.4 Couplings and connectors for EMT shall be steel or malleable iron, shall be

"Concretetight" or "Raintight", and shall be of either the gland and ring compression type or the stainless steel multiple point locking type. All connectors shall have insulated throats. Fittings using set screws or indentations as a means of attachment shall not be used.

13.5 All conduit connecting the various items of elevator equipment in the elevator machine room shall be run concealed where practicable. Metal wireways and auxiliary gutters shall be run exposed in readily accessible locations. All raceways embedded in concrete shall be rigid or intermediate steel conduit. At all other locations any of the other types of raceways specified may be used subject to conditions, specified. Raceway fittings shall provide conductor passageways free from burrs, shoulders or other projections which will reduce internal passage area or cause abrasion of conductors being pulled through.

13.6 All conductors to the car shall consist of flexible traveling elevator cables, conforming with the requirements of the NEC. Cables shall be run from the car junction box to a machine room junction box and from these boxes, conductors shall be run to various required locations. Each traveling cable conductor shall have a distinctive color code for identification of the individual conductors. Each traveling cable shall have at least 20 percent spare conductors. Junction boxes shall contain approved terminal blocks for connection of conductors. Terminal blocks shall have indelible identification numbers for each terminal connection. All connections to terminal blocks shall be made with pressure wire connectors.

A. Traveling cables shall be so suspended, anchored and run that the strain on individual cable conductors will be reduced to a minimum and connections to terminal blocks will be free from all strain. The outer cable covering must

14 of 55Page 24 of 65

ELECTRIC ELEVATORS 14210 - 12

remain intact between junction boxes and abrupt bending of cable producing distortion of cable will not be permitted. If, due to sway or change in relative position of traveling cables, complete freedom from contact with the hoistway construction cannot be avoided, suitable shields or pads shall be provided wherever necessary to prevent chafing or damage to the cables.

B. Traveling cables shall include not less than 10% spares and six (6) spare shielded pairs.

13.7 Furnish and install all wires and cables necessary for the proper connection and operation of all equipment installed under the elevator contract. All conductors shall be in accordance with NEC requirements. The conductor size shall be such that the maximum current carried will not exceed limits prescribed by the NEC.

A. Unless otherwise specified, conductors exclusive of traveling cables, shall be annealed copper with 60 o Centigrade or better insulation and shall be in accordance with Federal Specification J-C-30A. Single and multiple conductor cables shall have color coding or other suitable identification for each conductor. Unless otherwise specified, no joints or splices shall be permitted in wiring except at outlets. Tap connectors may be used in wireways provided they meet all NEC requirements. Installation of conductors in raceways shall conform to the NEC.

13.8 All conductors used for external wiring between the various items of elevator equipment shall be connected to terminal blocks which meet UL Standard 1059

(1975). Crimp-type connectors shall be applied with an appropriate setting tool to ends of all size No. 10 or smaller external wires.

14. ACCESSORIES:

14.1 Three sets each of complete, legible field wiring diagrams, including single line diagrams showing all electrical circuits shall be furnished. All symbols shall be listed corresponding to the identity or markings on machine room and hoistway apparatus of the systems specified. One set of diagrams shall be coated with laminated plastic, or other approved covering, suitably bound and placed in the machine room where directed. Each of the two remaining sets shall be neatly bound and delivered to the Contracting Officers Representative. The diagrams shall be revised to include all field modifications.

14.2 A complete set of tools necessary for making all system adjustments shall be furnished for each elevator machine room and delivered to the Construction

Engineer. (A metal tool cabinet having two shelves and a hinged door shall be provided in each elevator machine room. Cabinet size shall be not less than 48 inches high, 18 inches wide and 14 inches deep.)

15 of 55Page 25 of 65

ELECTRIC ELEVATORS 14210 - 13

14.3 Include an adjuster's level service tool or terminal with complete written installation manuals, service manuals, adjustment information and instructions for performing systems adjustments, special and emergency functions, diagnostic trouble shooting, and systems testing as required by

ANSI A17.1 code. The service tool shall become the property of GSA, and if the device requires reprogramming it shall be performed at no additional cost to the government for the life of the equipment.

14.4 Cylinder locks shall have a bronze cylinder with not less than five pin tumblers or shall have not less than a five disc combination provided wafer keyways, tumblers, and springs are of stainless steel. Provide three nickel silver keys for each lock and deliver same to the Construction Engineer. Provide an identification tag on each key with stamped legend "PROPERTY OF U.S. GOVERNMENT" on reverse side.

Tags shall conform to Federal Specification FF-T-77B, Type A, Class 1, engraved.

Locks shall be independently keyed unless otherwise specified. Key operated switches shall be of the cylinder lock key operated type.

14.5 A hoistway access switch shall be provided at the top and bottom terminal landings for all elevators. Hoistway access switches shall be of the key operated type meeting all requirements of the A17.1 Code.