This document provides details regarding a pre-solicitation notice for solicitation number 47PF0022R0032 for terra cotta repairs. The General Services Administration Region 5 will issue a solicitation for general construction services at a federal building located in Chicago, Illinois to perform terra cotta repairs on various sections of the exterior facade. The repairs include selective demolition and removal of damaged terra cotta units, temporary stabilization of remaining facade elements, fabrication of custom terra cotta units to match existing configurations, installation of fabricated units, joint repointing and sealing, and minor damage repairs. The estimated value is between $1-3 million and the performance period is 450 days upon notice to proceed. Interested firms must demonstrate experience with terra cotta removal, repairs, manufacturing and historical renovation through three similar project examples within the past five years. Firms must also provide a project management plan and information on key personnel, including historic treatment specialists with three years of terra cotta experience and field supervisors experienced in historic treatment work. The contract will be set aside for small businesses and NAICS code 236220 applies. The solicitation will be available on Sam.gov on or about May 6, 2022 and registration is required to download documents and be eligible for award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 01.pdf | ||
| Pre-Solicitation Notice.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA
RREEQQUUEESSTT FFOORR PPRROOPPOOSSAALL
RReeqquueesstt ffoorr PPrrooppoossaall ((RRFFPP))
U.S. GENERAL SERVICES
ADMINISTRATION
GREAT LAKES REGION
PUBLIC BUILDINGS SERVICE
Repair and Alterations Contracting Branch
John C. Kluczynski Federal Building
230 S. Dearborn Street, Suite 3500
Chicago, Illinois 60604
PPRROOJJEECCTT::
PPLLAACCEE OOFF
PPEERRFFOORRMMAANNCCEE::
Terra Cotta Repairs
Federal Building
536 S. Clark Street
Chicago, Illinois 60605
SSOOLLIICCIITTAATTIIOONN NNOO:: 47PF0022R0032
IISSSSUUEE DDAATTEE:: May 26, 2022
CCLLOOSSIINNGG DDAATTEE && TTIIMMEE::
June 27, 2022 4:00 PM (Central Time)
CCOONNTTRRAACCTT NNOO::
TBD
DDAATTEE OOFF AAWWAARRDD:: TBD
IISSSSUUEEDD BBYY::
U.S. General Services Administration Great Lakes Region Public Buildings Service Repair and Alterations Contracting Branch 230 S. Dearborn Street, Suite 3500 Chicago, Illinois 60604
GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA GGSSAA
GSA Solicitation No. 47PF0022R0032
Document: C201-SB GC/AUGUST 2021 (The Solicitation)
Construction Contract for: Terra Cotta Repairs
The Solicitation
Table of Contents
I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction H. Receipt of Offers
II. Proposals
A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors
III. General Provisions
A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI)
Building Information
IV. FAR/GSAR Solicitation Provisions
A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR 101-29
B. FAR 52.211-3, Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Items Description
C. FAR 52.216-1 Type Of Contract D. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of Work E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal
Employment Opportunity for Construction F. Buy American Requirements G. Buy American Exceptions H. FAR 52.233-2 Service of Protest I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference J. GSAR 552.102 Incorporating Provisions and Clauses by Reference
V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition B. Security Requirements
(i) FAR 52.204-9 Personal Identity Verification of Contractor Personnel
(ii) GSAM 552.204-9 Personal Identity Verification Requirements
VI. Method Of Award A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Non Price Factors F. Evaluation of Joint Ventures
Notice of Equal Employment Opportunity (EEO) Compliance Plan
GSA has partnered with the Department of Labor to ensure compliance with equal employment opportunity requirements that apply to this project. An EEO Compliance Plan is required after the award.
I. General Information
I.A. The Solicitation and Contract
(1) This Solicitation is set-aside for Small Businesses in accordance with FAR 19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer.
No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
I.B. List of Solicitation Documents
The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Standard Form (SF) 1442 – Solicitation Offer and Award
(4) The Agreement and Attachments to the Agreement
(5) Attachment A – GC Experience Summary
(6) Attachment B – Past Performance Questionnaire
(7) Total Evaluated Price – Cost Breakdown by Division
(8) Unit Pricing Form
(9) GSA Form 527 Contractor’s Qualifications and Financial information
(10) SF 24 – Bid Bond
I.C. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this Solicitation:
Contracting Officer’s Information
Name: Jennifer Dunne
Address: John C. Kluczynski Federal Building. 230 S. Dearborn Street, Suite 3500, Chicago, Illinois 60604
Telephone: 312-353-8796 (Office) 312-806-6507 (Cell)
Email: jennifer.dunne@gsa.gov
Alternate POC Information
Name: Johanna Nieves
Address: John C. Kluczynski Federal Building. 230 S. Dearborn Street, Suite 3500, Chicago, Illinois 60604
Telephone: 312-353-7659 (Office) 312-758-2467 (Office)
Email: johanna.nieves@gsa.gov
I.D. Pre-Proposal Conference
Date: June 14, 2022
Time: 1:00pm
Location: Federal Building, 536 S. Clark Street, Room 261, Chicago, Illinois 60605
Instructions: Offerors are required to RSVP by June 9, 2022, to jennifer.dunne@gsa.gov and johanna.nieves@gsa.gov. All individuals attending the site pre-proposal conference may be required to wear a face covering and practice social distancing as recommended by the Center for Disease Control.
I.E. Estimated Price Range
The estimated price range for the Project is between $1,000,000 and $5,000,000.
I.F. FAR 52.228-1 Bid Guarantee (Sep 96)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) Pre-registration is required for all attendees to the pre-proposal Site Visit. The Site Visit shall be limited to no more than four (4) representatives from each Offeror. Offerors shall send an email to jennifer.dunne@gsa.gov and johanna.nieves@gsa.gov as noted above under Pre-Proposal Conference section. The email must identify all attendees from their respective team. All individuals attending the site visit may be required to wear face covering and shall practice social distancing as recommended by the Center for Disease Control.
For further information about the site visit or access requirements, please send an email to the following individuals:
Name: Johanna Nieves, Alternate CO POC
Telephone: 312-758-2467
Email: johanna.nieves@gsa.gov
I.H. Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 4:00 pm CST on the following date and at the following address.
Date: June 27, 2022
Please submit all proposals electronically to the GSA Contracting Officer, Jennifer Dunne, at jennifer.dunne@gsa.gov. Please do not submit a hard copy.
(2) Offers sent by commercial package delivery and hand delivery shall be deemed received as of the date and time of delivery to the office designated for receipt of offers.
(3) Offers sent by United States Mail shall be deemed timely if delivered to the address of the government installation designated for receipt of offers on or before the date established for receipt of offers.
II. Proposals
II.A. Proposal Contents
Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
1. Price Proposal
2. Technical Proposal
3. Representations and Certifications
4. Standard Form 24, Bid Bond
5. GSA Form 527 – Contractor’s Qualification and Financial Information
6. Acknowledgement of Amendments (if any)
II.B. Proposal Format
Offerors shall submit one electronic proposal to the attention of the GSA Contracting Officer at jennifer.dunne@gsa.gov. The maximum size capacity for electronic transmissions to GSA is 25mb. Therefore, all submittal information for each email must be within the 25mb limitation.
Offerors may break proposal materials into separate emails to avoid exceeding the limitation.
When separating materials into separate emails, please, ensure that the email’s subject line states how many emails are to be expected. The subject line must also contain the solicitation number and firm name.
For example:
Subject Line:“ RFP 47PF0022R0032, Terra Cotta Repairs, Firm Name Proposal 1 of 5”.
The body of the submission email must include the following information:
“Firm Name
Address
CAGE Code
SAM. gov Unique Entity Identifier
Primary Points of Contact
Offeror Primary Point of Contact Name janedoe@email.com
Telephone
II.C. Price Proposal
(1) Contents
The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) Additional Proposal Requirements
N/A
II.D. Technical Proposal
The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.
1) Past Performance of Offeror (25%)
This factor considers the past performance of the Offeror. The Offeror shall submit a minimum of (3) relevant past performance references no more than (5) references for similar projects substantially completed within the last eight (8) years.
Past performance will be considered relevant if it meets the following criteria:
The project must have been for terra cotta repairs or masonry work comparable in size substantially completed within the last (8) years in an occupied and functioning office building which involved noise control requirements.
One of the three references submitted must be for terra cotta repairs, and one of the references submitted must have involved historic restoration and repair of a building listed or eligible to be listed on the National Register of Historic Buildings.
Offerors are responsible for obtaining past performance information prior to submission of offers. The attached past performance questionnaire (PPQ) shall be completed by the references and submitted directly to the GSA Contracting Officer, Jennifer Dunne, at jennifer.dunne@gsa.gov. An optional sample letter is included to assist in requesting this information. Past Performance Questionnaire must be received by the Contracting Officer by the time set for receipt of proposals.
In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System
(PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all
CAGE/DUNS/SAM UEI numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information
System (FAPIIS), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror. While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain database of past performance questionnaires submitted by Offerors.
(2) Experience of Offeror (25%)
This factor considers the extent of the Offeror’s past experience as a firm in providing similar construction services.
Offerors must demonstrate successful experience as a General Construction (GC) Contractor responsible for the construction of at least three (3) “similarly complex” projects substantially completed within the past eight (8) years.
For each project presented in relation to this factor (at least three total), the Offeror must explain how the characteristics of the project relate to the characteristics of this project. The similarity to this project is more important than the quantity of projects presented. Offerors shall use the GC
Experience Summary to capture this information. In addition, for each project presented, a PPQ shall be provided as described in Factor 1: Past Performance of Offerors.
Factor 3 - Management Plan (50%)
Project Approach:
This factor considers the Offeror’s approach to the project which indicates the means and methods they will employ to ensure management of the project in a manner which will maximize the opportunity for successful completion that is on-time, on-budget, and within quality expectations. This factor will be evaluated based upon a narrative that will be submitted as part of the technical proposal. The narrative should be no longer than two (2) double-sided pages and should delineate the Offeror’s knowledge, programs, and processes, relating them to the unique requirements of this project and demonstrating their approach to its management and execution of the Contract contemplated by this solicitation.
Staffing Plan and Qualifications of Key Personnel:
This factor considers the Offeror’s staffing plan and qualifications of key personnel. This factor will be evaluated based on the Offeror’s written responses; the written response to demonstrate the staffing plan shall not exceed three (3) double-sided pages, including the organizational chart and/or the experience matrix.
The Offeror shall provide a staffing plan that identifies personnel proposed to fill key team member positions, including descriptions of their roles and responsibilities. An organization chart shall show lines of authority and identifies personnel having signatory authority to bind the contractor to contractual actions.
Key team member roles include:
1. Primary Point of Contact that will be responsible for managing the contract (1)
2. Construction Superintendent(s) (may provide more than 1) – Experience with historic masonry work similar in nature to the work required in the specifications and drawings.
3. Project Manager(s) (may provide more than 1) – Experience in managing masonry projects similar in nature to the work required in the specifications and drawings.
4. Stone Mason (1) - Experience in exterior masonry cleaning, repointing, sealant installation, dismantling and resetting terra cotta, manufacture of matching/replication terra cotta material, installation of new (replicate terra cotta), patching and repair of terra cotta, crack repair. Extra consideration will be given to those who hold a International Masonry Institute (IMI) certification and a Historic Masonry Preservation Certificate (HMPC).
5. Other key team members as determined by the Offeror
Resumes shall be provided for key team member(s) filling roles 1-5. Resumes shall indicate currently held position/title, proposed project position/title, education, and qualifications. Do not provide more than eight (8) key personnel. Teams will have to prioritize and provide those that best represent your ability to accomplish the requirements of this contract. Executive personnel should not be submitted unless they will have direct responsibility for managing this contract.
A matrix shall be provided that clearly identifies the work experience that each key team member has on the projects submitted under Factor 2. Only indicate key team members that participated in example projects when they will be performing the exact same role on this contract. If the key team members did not work on any of the projects submitted under Factor 2, provide no more than a one (1) page description of the key team member’s qualifications as they relate to the proposed roles and responsibilities for this contract.
This factor will be evaluated as an indicator of the Offeror’s understanding of the staffing requirements and the proven qualifications of key team members based on successful experience in comparable positions on similar projects. The qualifications of key personnel shall demonstrate that each of the key team members have held comparable position(s) and has the appropriate education, qualifications, professional licensing, and experience to be assigned to this position. Preference will be given to those members having experience on multiple similar projects and/or successful performance in comparable positions.
No changes to specific personnel proposed for key positions may be made without the
Government’s consent.
II.E. Other Information to Submit with Proposal
(1) Representations and Certifications
Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. Offerors shall also submit with their proposal, the Annual Representations and Certifications (FAR 52.204-8), using the attached Offeror’s Representations and Certifications (C301-SAT).
(2) Qualifications of Offerors
Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract. Offerors shall submit this information on the attached GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.
II.F. Requirements of Joint Venture Offerors
(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.
(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.
(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.
(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.
III. General Provisions
III.A. Availability of Funds
Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.
III.B. Requests for Clarification or Interpretation
The Government will attempt to answer all requests for clarifications or interpretations of the
Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 5 calendar days. Prospective Offerors should make such requests not less than 10 calendar days prior to the date set for receipt of offers.
III.C. Notice to Small Business Firms
A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.
III.D. Information Concerning the Disclosure of Solicitation Results
This acquisition is being conducted under the provisions of FAR Part 15 as a negotiated procurement. In accordance with FAR 3.104 and FAR 15.207, after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15.503.
III.E. Affirmative Procurement Program
GSA has implemented an Affirmative Procurement Program (APP) intended to maximize the use of recovered materials, environmentally preferable, and bio-based products. Offerors should familiarize themselves with the requirements for using and reporting on the use of such materials in performance as set forth in the Agreement. Refer to Clause FAR 52.223-10 encouraging vendors to practice waste reduction.
III.F. Notice Concerning Preparation of Proposals
Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.
III.G. Bond Requirements
If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.
III.H. Contractor Performance Information
(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process.
CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment
Completed CPARS evaluations may then be used by Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.
(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS.
The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned. Contractors will be granted one user account to access all evaluations.
(3) Contractor CPARS Training: Contractors may sign up for CPARS training. A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.
(4) Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.
Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.
GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.
Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.
III.I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information
Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.
IV. FAR/GSAR Solicitation Provisions
IV.A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (AUG 98)
(a) The GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29, and copies of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained for a fee by submitting a request to—
GSA Federal Supply Service Specifications Section, Suite 8100 470 East L’Enfant Plaza, SW Washington, DC 20407
Telephone (202) 619-8925 Facsimile (202) 619-8978
(b) If the General Services Administration, Department of Agriculture, or Department of Veterans Affairs issued this solicitation, a single copy of specifications, standards, and commercial item descriptions cited in this solicitation may be obtained free of charge by submitting a request to the addressee in paragraph (a) of this provision. Additional copies will be issued for a fee.
IV.B. FAR 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (JUN 1988)
(a) The specifications cited in this solicitation may be obtained from: GSA Specifications Unit at (202) 755-0325. MIL Specifications may be obtained by calling (215) 697-2179.
(b) The request should identify the solicitation number and the specification required by date, title, and number as cited in the solicitation.
IV.C. FAR 52.216-1 Type of Contract (APR 84)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
IV.D. FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work
(MAY 14)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.
IV.E. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for Minority Participation for Each Trade
Goals for Female Participation for Each Trade
19.6% 6.9%
These goals are applicable to all of the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is: Illinois, Cook County, Chicago
IV.F. Buy American Requirements
FAR 52.225-10 Notice of Buy American Requirement-Construction Materials (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
IV.G. Buy American Exceptions
For Buy American exceptions, if any, see the applicable Buy American clause in Section IV of the Agreement
IV.H. FAR 52.233-2 Service of Protest (SEP 06)
(a) Protests, as defined in section 31.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from the Contracting Officer at the address provided in the provision “Receipt of Offers” in Section I (General Information).
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
IV.I. FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 98)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address:
Federal Acquisition Regulation
NUMBER TITLE DATE
52.214-34 Submission of Offers in the English Language
APR 91
52.215-16 Facilities Capital Cost of Money JUN 03 52.236-28 Preparation of Proposals - Construction OCT 97
IV.J. GSAR Clause 552.102 Incorporating Provisions and Clauses
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
V. Instructions and Clauses
V.A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (Jan 2017)
(a) Definitions. As used in this provision.
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer’s discretion, result in the offeror being allowed to revise its proposal.
“In writing,” “writing,” or “written” means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation’s closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time,” if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals.
(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show.
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, revision, and withdrawal of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and.
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government’s control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award.
Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225- 17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall.
(1) Mark the title page with the following legend:
This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed.in whole or in part.for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of.or in connection with.the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend:
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government’s interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government’s best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency’s evaluation of the significant weak or deficient factors in the debriefed offeror’s offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
V.B. Security Requirements
(i) FAR 52.204-9 Personal Identify Verification of Contractor Personnel
Personal Identity Verification of Contractor Personnel (Jan 2011)
(a) The Contractor shall comply with agency personal identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12 (HSPD-12), Office of
Management and Budget (OMB) guidance M-05-24 and Federal Information Processing Standards Publication (FIPS PUB) Number 201.
b) The Contractor shall…