47PF0018R0143 - Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI_Responses_Dry_Sprinkler_Piping_&_Paint.pdf | ||
| Amendment_0002.pdf | ||
| Amendment_0001.pdf | ||
| Agenda.pdf | ||
| Attendance_Sheet.pdf | ||
| Solicitation_47PF0018R0143.pdf | ||
| GSA527-15.pdf | ||
| SF_1442_47PF0018R0143__Form.pdf | ||
| Combined_Drawings.pdf | ||
| SF24.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Architectural-Engineering Services for Garage Dry Fire Protection Pipe Project at
Carl B. Stokes US Courthouse 801 W Superior Ave
Cleveland, Ohio 44113
Public Building Service – Region 5 Work Order #1508
GS-05-P-16-SC-C-7021
100% CD Submittal 23 November 2016
PROPERTY OF THE UNITED STATES GOVERNMENT. COPYING,
DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS
OR SPECIFICATIONS TO UNAUTHORIZED PERSONS IS PROHIBITED.
R ic ha rd F le is ch m an
P ar tn er s A rc hi te ct s, In c.
H ur on
R od
S ui te
C le ve la nd
, O hi o
T el ep ho ne
Fa cs im ile o ffi ce
St ud io
R
FA
.c om
December 2005
Garage Dry Fire Protection Pipe Carl B Stokes US Courthouse PBS-REG 5 Cleveland, Ohio Work Order #1521
TABLE OF CONTENTS TOC-1
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
PROJECT MANUAL
TABLE OF CONTENTS
100% SUBMITTAL
DIVISION 0 – BIDDING AND CONTRACT REQUIREMENTS
SECTION
TOC TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
SECTION
01 00 10 GENERAL RESTORATION REQUIREMENTS
01 10 10 SUMMARY
01 14 00 WORK RESTRICTIONS
01 25 00 CONTRACT MODIFICATION PROCEDURES
01 29 00 PAYMENT PROCEDURES
01 31 00 PROJECT MANAGEMENT AND COORDINATION
01 31 10 CRITICAL PATH METHOD SCHEDULING
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 SUBMITTAL PROCEDURES
01 35 25 FIRE PREVENTION & PROTECTION IN CONSTRUCTION, ALTERNATION,
AND DEMOLITION PROJECTS
01 35 26 SAFETY AND HEALTH
01 35 53 SECURITY REGULATIONS
01 35 91 HISTORIC TREATMENT PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 42 00 REFERENCES
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 59 60 FIRE PREVENTION & PROTECTION IN CONSTRUCTION, ALTERNATION
AND DEMOLITION PROJECTS
01 60 00 PRODUCT REQUIREMENTS
01 70 00 EXECUTION REQUIREMENTS
01 73 10 CUTTING AND PATCHING
01 73 20 SELECTIVE DEMOLITION
01 77 00 CLOSEOUT PROCEDURES
01 78 10 PROJECT RECORD DOCUMENTS
01 78 20 OPERATION AND MAINTENANCE
01 82 00 DEMONSTRATION AND TRAINING
DIVISION 2 – EXISTING CONDITIONS
NOT USED
TABLE OF CONTENTS TOC-2
DIVISION 3 – CONCRETE
DIVISION 4 – MASONRY
DIVISION 5 – METAL
DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
DIVISION 8 – DOORS AND WINDOWS
DIVISION 9 – FINISHES
09 91 13 EXTERIOR PAINTING
DIVISION 10 – SPECIALTIES
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 – SPECIAL CONSTRUCTION
TABLE OF CONTENTS TOC-3
DIVISION 14 – CONVEYING EQUIPMENT
DIVISION 21 – FIRE SUPPRESSION
21 13 16 DRY PIPE SPRINKLER SYSTEM
21 13 18 CORROSION PROTECTION FOR DRY PIPE SPRINKLER SYSTEMS
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING
DIVISION 26 – ELECTRICAL
26 05 01 BASIC ELECTRICAL REQUIREMENTS
26 05 04 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 05 FIRESTOPPING
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS – COPPER
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 27 39 ELEVATOR POWER MODULE AND WIRING DUMBWAITERS AND
ESCALATORS
26 28 13 FUSES
26 28 16 DISCONNECT SWITCHES
DIVISION 27 – COMMUNICATIONS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 04 FIRE ALARM SYSTEM MODIFICATION
TABLE OF CONTENTS TOC-4
END OF TABLE OF CONTENTS
SUMMARY 01 10 00 - 1
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
SECTION 01 10 00
SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents and Key Contacts
2. Type of the Contract
3. Work under other contracts
4. Government's occupancy requirements
5. Specification formats and conventions
6. Miscellaneous provisions
B. Related Sections include the following:
1. Division 1 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Government's facilities.
1.3 WORK COVERED BY CONTRACT DOCUMENTS AND KEY CONTACTS
A. Project Identification: Garage Dry Fire Protection Project, Carl B Stokes US Courthouse, Garage Levels and associated spaces
1. Project Location: 801 W Superior Ave., Cleveland, OH 44113
2. GSA Property Manager for the Building: Mr. Paul Lentini, Property Manager;
GSA PBS Property Management Division; 801 W Superior Ave; Cleveland, OH 44113; Tel: 216-522-3483
B. Owner (hereafter referred to as “the Government”): U.S. General Services Administration
SUMMARY 01 10 00 - 2
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
1. GSA Contracting Officer (CO): Rhonda Booker, Contract Officer, 201 Superior Avenue, Cleveland, OH 44114-1248.
2. GSA Contracting Officer’s Representative (COR); Mr. Jack Malone, Customer Project Service Center. 201 Superior Ave., Suite 400 Cleveland, OH 44114
3. GSA Project Manager: Mr. Jack Malone, Customer Project Service Center. 201 Superior Ave., Suite 400 Cleveland, OH 44114
C. Architect or A/E: Richard Fleischman + Partners Architects, Inc.; 1020 Huron Road;
Cleveland, Ohio 44115; Mr. Jason Nolde, Project Manager
D. The Work consists generally of the following:
The project involves modification to the piping associated with the dry-pipe automatic suppression system for the Carl B. Stokes US Courthouse. The system shall include all piping, sprinklers, fittings, hangers, valves, flow switches, tamper switches, supervisory switches, check valves, riser trim packages, nitrogen generators, air maintenance devices, nitrogen monitoring equipment, drains, inspector’s test connections, and all other accessories and miscellaneous items required for a complete operating system. The sprinkler system shall be fully tested and ready for full operation prior to acceptance by the Government.
In addition, the contractor shall completely repair, refurbish, and provide additional equipment to the existing completely supervised, multiplex intelligent, analog, addressable fire detection and alarm system.
1.4 TYPE OF CONTRACT
1. Project will be constructed under one, single Prime General Contract.
1.5 WORK UNDER OTHER CONTRACTS
A. General: The Government reserves the right to enter into separate Contracts for other Work during the duration of the Project. Contractor shall cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
1.6 GOVERNMENT'S OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy the entire building during the entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
SUMMARY 01 10 00 - 3
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government.
2. Provide not less than 72 hours' notice to Government of activities that will affect Government's operations.
1.7 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the CSI/CSC's "2004 MasterFormat" numbering system.
1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete because all available Section numbers are not used. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.
2. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied but not stated shall be inferred, as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
1.8 MISCELLANEOUS PROVISIONS
A. Work in the extension of existing conditions shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.
SUMMARY 01 10 00 - 4
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
B. Work shall be in compliance with building code in effect for the Project, from a model code organization acceptable to the Authority Having Jurisdiction.
C. Alterations to Existing Conditions
1. Replacements of removed existing conditions shall match similar existing conditions.
2. Unless specifically indicated otherwise, do not cut or alter existing structural members without authorization by the Contracting Officer or his/her designated representative as directed by GSA.
3. Existing conditions to remain that are damaged during the Work shall be restored to the condition existing at the time of award of Contracts.
4. Discolored or unfinished surfaces exposed by removal of existing conditions that are to remain as final exposed surfaces shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.
D. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer or his or her designated representative as directed by the GSA and shall be protected from damage. Items that become damaged shall be replaced to exact condition at no cost to the Government
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 10 00
WORK RESTRICTIONS 01 14 00 - 1
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 USE OF PREMISES
A. Use of Site: Contractor shall have use a designated area within the building to stage and store equipment.
1. Government Occupancy: Allow for Government occupancy of site and building and use by the public.
2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Smoking is not permitted in the building.
B. Use of Existing Building: Use of existing building is limited to the designated Work areas and Contractor’s designated staging/storage area. All work areas and surrounding areas shall be provided with adequate ventilation to ensure that no odors and off gasing prior to, during and after work has been performed affect the occupants of the building. Repair damage caused by construction operations. Protect building and its occupants during construction period.
1.3 OCCUPANCY REQUIREMENTS
A. Full Government Occupancy: Government will occupy the site and entire existing building during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.
Perform the Work so as not to interfere with Government's operations.
WORK RESTRICTIONS 01 14 00 - 2
PROPERTY OF THE UNITED STATES GOVERNMENT
FOR OFFICIAL USE ONLY
Do not remove this notice Properly destroy documents when no longer needed
B. Work Hours: The Project will be available to the Contractor six (6) days a week.
Normal work hours will be from 6 PM to 6 AM. Only select work operations will be able to be performed during normal business hours. A GSA Building Security representative must accompany each work crew during construction.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01 14 00
CONTRACT MODIFICATION PROCEDURES 01 25 00 - 1
SECTION 01 25 00
CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.
B. Related Sections include the following:
1. Division 1 Section "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Contracting Officer or his/her designated representative as directed by GSA will issue through the COR supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.4 PROPOSAL REQUESTS
A. Government-Initiated Proposal Requests: Contracting Officer or his/her designated representative as directed by GSA will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Proposal Requests issued by Contracting Officer or his/her designated representative as directed by GSA are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.
CONTRACT MODIFICATION PROCEDURES 01 25 00 - 2
2. Within 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to COR.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Division 1 Section "Product Requirements" if the proposed change requires substitution of one product or system for product or system specified.
C. Proposal Request Form: Use AIA Document G709 for Proposal Requests
1.5 CHANGE ORDER PROCEDURES
A. On Government's approval of a Proposal Request, Contracting Officer or his/her designated representative as directed by GSA will issue a Change Order for signatures of Government and Contractor on GSA Form 1137.
CONTRACT MODIFICATION PROCEDURES 01 25 00 - 3
1.6 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Contracting Officer or his/her designated representative as directed by GSA may issue a Change Directive. Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 25 00
PAYMENT PROCEDURES 01 29 00 - 1
SECTION 01 29 00
PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Sections include the following:
1. Division 1 Section "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
2. Division 1 Section "Construction Progress Documentation" for administrative requirements governing preparation and submittal of Contractor's Construction Schedule and Submittals Schedule.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by the Contractor to the COR allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing the monthly Application for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of the Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:
a. Application for Payment forms with Continuation Sheets.
b. Submittals Schedule.
c. Contractor's Construction Schedule.
PAYMENT PROCEDURES 01 29 00 - 2
2. Submit the Schedule of Values to the Contracting Officer or his/her designated representative as directed by GSA at earliest possible date but no later than fifteen days before the date scheduled for submittal of initial Applications for Payment.
B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. Provide at least one line item for each Specification Section in Divisions 2 through 16. Additionally, Division 0 and 1 costs shall be grouped into reasonable Project segments (floors, areas, etc.) subject to approval by the Contracting Officer or his/her designated representative as directed by
GSA.
1. Identification: Include the following Project identification on the Schedule of Values:
a. Project name and location.
b. Name of Contracting Officer and Contracting Officer’s Representative
c. Contractor's name and address.
d. Date of submittal.
2. Submit draft of AIA Document G703 Continuation Sheets.
3. Arrange the Schedule of Values in tabular form with separate columns to indicate the following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value.
1) Percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. For instance, if work will be prosecuted in a floor-by-floor or area/segment sequence, cost breakdowns should reflect that sequence. Also coordinate with the Project Manual table of contents. Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training in the amount of 5 percent of the Contract Sum.
5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
6. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
PAYMENT PROCEDURES 01 29 00 - 3
a. Differentiate between items stored on-site and items stored off-site.
Include evidence of insurance or bonded warehousing for off-site storage.
7. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
8. Allowances: Provide a separate line item in the Schedule of Values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.
9. Each item in the Schedule of Values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.
10. Schedule Updating: Update and resubmit the Schedule of Values when new Change Orders or Construction Change Directives change the Contract Sum.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by Contracting Officer or his/her designated representative as directed by GSA and paid for by Government.
1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.
B. Payment Application Times: Progress payments shall be submitted to Contracting Officer or his/her designated representative as directed by GSA by the 25th day of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.
C. Payment Application Forms: Use AIA Document G702/CMa and AIA Document G703 Continuation Sheets as form for Applications for Payment.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of the Contractor. Contracting Officer or his/her designated representative as directed by GSA will return incomplete applications without action.
1. Entries shall match data on the Schedule of Values and Construction Schedule.
Use updated schedules if revisions were made.
2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
PAYMENT PROCEDURES 01 29 00 - 4
E. Transmittal: Submit 3 signed and notarized original copies of each Application for Payment to Contracting Officer or his/her designated representative as directed by GSA by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
F. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. Government reserves the right to designate which entities involved in the Work must submit waivers.
4. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to Government.
G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. Government reserves the right to designate which entities involved in the Work must submit waivers.
4. Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to Government.
H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of Values.
3. Contractor's Construction Schedule (preliminary if not final).
4. Products list.
5. Schedule of unit prices.
6. Submittals Schedule (preliminary if not final).
7. List of Contractor's staff assignments.
8. List of Contractor's principal consultants.
9. Copies of building permits.
PAYMENT PROCEDURES 01 29 00 - 5
10. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
11. Initial progress report.
12. Report of pre-construction conference.
13. Certificates of insurance and insurance policies.
14. Performance and payment bonds.
15. Data needed to acquire Government's insurance.
16. Initial settlement survey and damage report if required.
I. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Government occupancy of designated portions of the Work.
J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. AIA Document G706, "Contractor’s Affidavit of Payment of Debts and Claims."
5. AIA Document G706A, "Contractor’s Affidavit of Release of Liens."
6. AIA Document G707, "Consent of Surety to Final Payment."
7. Evidence that claims have been settled.
8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Government took possession of and assumed responsibility for corresponding elements of the Work.
9. Final, liquidated damages settlement statement.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 29 00
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1
Do not remove this notice Properly destroy documents when no longer needed
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General Project Coordination and Coordination Drawings.
2. Conservation.
3. Administrative and supervisory personnel.
4. Project meetings.
5. Cleaning and protection
B. Each Contractor shall participate in coordination requirements. Certain areas of responsibility will be assigned to a specific Contractor.
C. Related Sections include the following:
1. Division 1 Section "Construction Progress Documentation" for preparing and
Contractor's Construction Schedule.
2. Division 1 Section "Execution Requirements" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Division 1 Section "Closeout Procedures" for coordinating Contract closeout.
4. Division 1 Section “Construction Waste Management” for requirements to establish a program to maximize recycling of waste materials.
1.3 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2
Do not remove this notice Properly destroy documents when no longer needed
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Government and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Construction Schedule.
2. Installation and removal of temporary facilities and controls.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Pre-installation conferences.
6. Project closeout activities.
7. Startup and adjustment of systems.
D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. Refer to other Sections for disposition of salvaged materials that are designated as Government's property.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to a minimum scale of 1/4”=1’-0”. Do not base Coordination Drawings on reproductions of the Contract
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3
Do not remove this notice Properly destroy documents when no longer needed
Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, fire life safety and electrical systems.
b. Indicate required installation sequences.
c. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer or his/her designated representative as directed by GSA for resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Refer to individual Division Sections for Coordination Drawing requirements for Work in those Sections.
1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL (Only if available)
A. General: The Contractor is solely responsible for the management (planning, supervision and contract coordination) and construction (including all labor, equipment, materials and inspections) to meet requirements of the Contract Documents. He shall provide the following personnel for proper performance of the Work
1. Project Executive (principal of the firm)
2. Project Coordinator
3. Project Manager
4. Architectural and Engineering Review Coordinator
5. Cost Estimating staff
6. CPM Analysts
7. Value Engineering Coordinator
8. Construction Superintendent
9. Quality Control Superintendent
10. Project Engineer
11. Construction Supervisors
12. Testing Engineering firms
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4
Do not remove this notice Properly destroy documents when no longer needed
1.6 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
1. Attendees: Inform participants and individuals whose presence is required, of date and time of each meeting. Notify Government and Contracting Officer or his/her designated representative as directed by GSA of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Government and Contracting Officer or his/her designated representative as directed by GSA, within three days of the meeting.
B. Pre-construction Conference: The Contracting Officer or his/her designated representative as directed by GSA shall schedule a pre-construction conference before starting construction at a time and place convenient to the Contractor. Conduct the meeting to review responsibilities and personnel assignments.
1. Attendees: Authorized representatives of Government (Contracting Officer or his/her designated representative as directed by GSA, Contracting Officer’s Representative and Project Manager), Architect, Engineer, Contractor and its superintendent; major design consultants; major contractors and suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Fire protection during construction
d. Critical work sequencing and long-lead items.
e. Designation of responsible personnel and their duties.
f. GSA pricing policies
g. Environmental goals of the Project
h. Construction waste management and recycling
i. Procedures for processing field decisions and Change Orders.
j. Procedures for requests for interpretations (RFIs).
k. Procedures for testing and inspecting.
l. Procedures for processing Applications for Payment.
m. Distribution of the Contract Documents.
n. Submittal procedures.
o. Preparation of Record Documents.
p. Use of the premises and building
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5
Do not remove this notice Properly destroy documents when no longer needed
q. Work restrictions.
r. Government's occupancy requirements.
s. Responsibility for temporary facilities and controls.
t. Parking availability.
u. Office, work, and storage areas.
v. Equipment deliveries and priorities.
w. First aid.
x. Security.
y. Housekeeping and progress cleaning.
z. Working hours.
3. Minutes: Contractor will distribute minutes within 3 working days after the meeting to all attendees and other interested parties.
C. Pre-installation Conferences: Contractor shall conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: In addition to the Contractor, installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including any or all requirements for the following:
a. The Contract Documents.
b. Options/alternates.
c. Related requests for information/interpretations (RFIs).
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility problems.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's recommendations.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of authorities having jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 6
Do not remove this notice Properly destroy documents when no longer needed
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Within 3 work days of the meeting, Contractor will distribute minutes of the meeting to each party present and to other interested parties, including the Contracting Officer or his/her designated representative as directed by GSA and Architect.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Progress Meetings: The Contractor shall conduct progress meetings at weekly intervals. Coordinate dates of meetings.
1. Attendees: In addition to the Government’s Project Manager, Contracting Officer or his/her designated representative as directed by GSA, Contracting Officer’s Representative, Building Management Representative, Architect, the Contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
b. Review present and future needs of each entity present, including any or all of the following:
1) Fire protection during construction.
2) Environmental goals of the Project
3) Construction waste management
4) Interface requirements
5) Sequence of operations
6) Status of submittals and RFI’s
7) Deliveries
8) Access
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 7
Do not remove this notice Properly destroy documents when no longer needed
9) Site utilization.
10) Temporary facilities and controls.
11) Work hours.
12) Hazards and risks.
13) Housekeeping and progress cleaning.
14) Quality and work standards.
15) Status of correction of deficient items.
16) Status of Change Orders.
17) Documentation of information for payment requests.
18) Updating of Record Documents
3. Reporting: Within 3 work days, the Contractor will distribute minutes of the meeting to each party present and to other concerned parties including the Contracting Officer or his/her designated representative as directed by GSA. He will include a brief narrative summary of progress since the previous meeting.
E. Coordination Meetings: The COR will conduct Project coordination meetings at bi-weekly intervals to verify detailed coordination procedures for upcoming construction operations and to avoid potential problems and misunderstandings. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and pre-installation conferences.
1. Attendees: In addition to the Government’s Project Manager, Contracting Officer or his/her designated representative as directed by GSA, Contracting Officer’s Representative, Contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Contractor shall review and correct or approve minutes of the previous coordination meeting. Review other items of significance that could affect progress, including but not limited to subjects listed for the Progress Meetings.
3. Reporting: Within 3 working days, the Contractor shall record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 General Coordination Provisions
A. Prior to installations, installers shall inspect and approve substrates, and repair substrates before installations if not initially acceptable. Coordinate temporary
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 8
Do not remove this notice Properly destroy documents when no longer needed enclosures with inspections and tests to minimize uncovering completed work for that purpose.
B. Keep construction in progress and adjoining in-place materials clean, and apply protective coverings where required to protect from damage or deterioration.
C. Clean completed construction and provide maintenance as required through the remainder of the construction period. Adjust and lubricate operating components as necessary to ensure operability without damage.
D. Limiting Exposures: Supervise operations to prevent exposure of any part of existing construction to harmful, dangerous damaging or otherwise deleterious conditions, including but not limited to the following:
1. Excessive static or dynamic loading
2. Excessive internal or external pressures
3. Excessive high or low temperatures
4. Thermal shock
5. Excessive high or low humidity
6. Pollution and air contamination
7. Water or ice
8. Chemicals or solvents
9. Light
10. Radiation
11. Puncture
12. Abrasion
13. Heavy traffic
14. Soiling, staining and corrosion
15. Bacteria
16. Rodent and insect infestation
17. Combustion
18. Electrical current
19. High-speed operation
20. Improper lubrication
21. Unusual wear and other misuse
22. Contact between incompatible materials
23. Destructive testing
24. Misalignment
25. Excessive weathering
26. Unprotected storage
27. Improper shipping or handling
28. Theft or vandalism
END OF SECTION 01 31 00
CRITICAL PATH METHOD SCHEDULING 01 31 10-1
SECTION 01 31 10
CRITICAL PATH METHOD SCHEDULING
PART 1 - GENERAL
1.1 SUMMARY
A. Develop a detailed Network Plan utilizing the most current version of Primavera Project Planner demonstrating complete fulfillment of all Work shown in the contract documents. Regularly update the Network Plan in accordance with the requirements of this Section, and utilize it in planning, coordinating, and performing all the Work under this Contract. Schedule activities shall accurately depict the entire scope of work to be performed to complete the project including, but not limited to, all activities of subcontractors, consultants, equipment vendors and suppliers, GSA, and others, as required.
B. The purpose of the Project Schedule shall be to:
1. Ensure adequate planning, staffing, scheduling and reporting during execution of the Work by the Contractor;
2. Ensure coordination of the Work among all affected parties;
3. Assist the AE and GSA in the preparation and evaluation of the Contractor monthly progress payments; and
4. Assist the AE and GSA in monitoring the progress of the work, and evaluating proposed changes to the Contract and/or requests for additional time to Project Completion.
1.2 RELATED SECTIONS
A. This specification supplements GSA Form 3506 schedule clauses.
B. Drawings and provisions of the Contract including General and Supplementary
Conditions apply to this Section as if repeated herein.
1.3 DEFINITIONS
A. Definitions applicable to this Section include the following:
1. Activity - An element of the Work or task performed during the course of the project.
Each schedule activity shall be a clearly defined and manageable task depicting an expected duration, an expected cost, and expected resource requirements.
2. Baseline Schedule - The original work plan approved by GSA as the Project Schedule.
3. Constraint - A scheduling restriction imposed on the start or finish of an activity.
Only contractual/owner-designated constraints are allowed.
4. Critical Path - The Project primary critical path is defined as the path with the least
CRITICAL PATH METHOD SCHEDULING 01 31 10-2
amount of total float which constitutes the longest, continuous path of interrelated activities depicting project work from notice of award (or NTP) to project completion.
All reports and graphics indicating the Critical Path shall depict the longest path of interrelated activities. Unless otherwise approved by GSA, the Baseline Schedule Critical Path shall use all allotted Contract time.
5. Critical Path Method (CPM) - A scheduling technique utilizing activities, durations, and interrelationships/dependencies (logic), such that all activities are interrelated with logic ties from the beginning of the project to the completion of the project.
6. Data Date - The data date of each schedule update shall be the first calendar day of each month and represent all work performed through the last calendar day of the preceding month.
7. Float – is the difference between the planned early dates and the planned late dates; the amount of time an activity can be delayed without affecting the Substantial Completion Date. Float is considered a project commodity jointly shared between GSA and the Contractor and shall be used in the best interest of completing the Project on time.
8. Float Suppression - utilization of zero free float constraints which allows an activity to start as late as possible by using all its' available free float. This technique allows activities to appear more critical than if the activity's total float was based on early dates. Assigning zero free float prevents true sharing of total float between GSA and the Contractor.
9. Fragnet - A subset group of interrelated activities representing only a portion of the CPM schedule.
10. Key Plans - Key Plans are graphic representations on prints of the Contract Documents of the Contractor’s planned breakdown of the project for scheduling purposes. The key plans will clearly define the boundaries of the work for each designated area. The alphanumeric codes on the key plans shall match the code values for the activity code "Area" in the Project schedule.
11. Network Plan - The Network Plan is the entire database of activities, logic, durations, and all items relating to any activity input into the scheduling software and is the complete representation of the Project Schedule prepared using the Critical Path Method and graphically shown in a time-scaled form. The network shows the sequence and interdependence of the activities, and planned and actual progress by activity, required for complete performance of the Work.
12. Project Group – A means used in Primavera Project Planner to divide a large project…
This is the start of the file's text. The full file is on GovTribe.