This document outlines infection control risk assessment (ICRA) procedures for a construction project to expand an existing dialysis center at the Overton Brooks VA Medical Center. The project involves expanding dialysis capacity (Type B medium-scale work) in an area of high patient risk. Based on the ICRA matrix, Class III precautions are required which entails infection control documentation. The related federal contract opportunity is a solicitation issued by the VA Veterans Health Administration VISN 16 for Project 667-23-102 to expand the dialysis center (Project #36C25623R0017). Proposals are due based on the standard solicitation timeframe and award will also follow standard procedures.

View the file

Other files for this federal contract opportunity

Other files attached to Project #667-23-102 Expand Dialysis (DB), newest first.
File Type Posted
36C25623R0017 0001.pdf PDF
36C25623R0017 0002.pdf PDF
P09 Attachment B - 4E Existing Layout.pdf PDF
WD LA20230031 dated 01-06-2023.txt TXT text file
P09 SOW Final.pdf PDF
36C25622R0017 Exhibit A Contractor Evaluation Form - Construction Safety.docx DOCX document
36C25623R0017 FINAL 1-9-23.docx DOCX document
P09 Attachment A - 4E Dialysis Floor Plan.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VA Medical Center Infection Prevention & Control Class III Precautions Step One: Circle the Construction Project Activity Type (A-D). PROJECT: 4 East Dialysis Center Expansion

Type A Inspection and non-invasive activities. Includes but is not limited to:

· Removal of ceiling tile for visual inspection-limited to 1 tile/50 square feet with limited exposure time.

· Limited building system maintenance (e.g., pneumatic tube station, HVAC, fire suppression system, electrical and carpentry work to include painting without sanding) that does not create dust or debris.

· Clean plumbing activity limited in nature.

Type B Small-scale, short duration activities; minimal dust and debris. Includes but not limited to:

· Work conducted above the ceiling (e.g., prolonged inspection/repair of firewalls and barriers, install conduit/cabling, & access to mechanical and/or electrical chase spaces).

· Fan shutdown/startup.

· Installation of electrical devices or new flooring that produces minimal dust and debris.

· The removal of drywall where minimal dust and debris is created.

· Controlled sanding activities (e.g., wet or dry sanding) that produce minimal dust and debris.

Type C Large-scale, long duration activities; moderate amount of dust and debris. Includes but not limited to:

· Removal of preexisting floor covering, walls, casework, or other building components.

· New drywall placement.

· Renovation work in a single room.

· Non-existing cable pathway or invasive electrical work above ceilings.

· The removal of drywall where a moderate amount of dust and debris is created.

· Dry sanding where a moderate amount of dust and debris is created.

· Work creating significant vibration and/or noise.

· Any activity that cannot be completed in a single work shift.

Type D Major demolition and construction activities. Includes but is not limited to:

· Removal or replacement of building system component(s).

· Removal/installation of drywall partitions.

· Invasive large-scale new building construction.

· Renovation work in two or more rooms.

Step Two: Circle the Risk Group(s) affected. Select the higher group, when more than one group will be affected.

Low Risk*
Medium Risk
High Risk
Highest Risk

*Not in patient care areas

· Public hallways & gathering areas

· Office areas

· Breakrooms

· Bathrooms or locker rooms

· Mechanical rooms

· EMS closets

· Waiting areas

· Clinical engineering

· Materials management.

· SPS Decon area

· Kitchen, cafeteria, gift shop, coffee shop, food kiosks.

· Patient care rooms/clinics

· All acute inpatient units

· Emergency department

· Occupation Health

· Pharmacy general areas

· Medication, clean utility & sterile supply rooms

· Imaging/diagnostic suites

· Laboratory.

· All transplant & ICUs

· All oncology units.

· OR suites & restricted areas.

· Procedural suites.

· Pharmacy compounding areas

· SPS: Prep and HLD areas

· Transfusion services.

· Dedicated isolation wards/units.

· Invasive imaging suites:

Step Three: Using the IC Matrix CIRCLE the Class of Precautions as determined by Construction Type and Patient Risk.

Construction Project Type

Patient Risk Group
Type A
Type B
Type C
Type D
IC Matrix
LOW Risk Group1
I
II
II
III
MEDIUM Risk Group1
I
II
III2
IV2
HIGH Risk Group1
I
III
IV2
V2
HIGHEST Risk Group1
III
IV2
V2
V2

1. Amend as follows for environmental conditions that could affect human health (i.e., sewage, mold, asbestos, gray water, and black water). Class IV Precautions for LOW and MEDIUM Risk Groups and Class V Precautions for HIGH and HIGHEST Risk Groups.

2. Infection Control documents required for Class III Precautions in Type C projects and all Class IV & V Precautions.

Preliminary ICRA: ________________

DATE

Final ICRA: _July 25, 2022 DATE image1.emf