3f. QHB ARSR Road Repairs Spec_SOW.pdf
PDF 8 MB Posted
- Attached to
- ST Albans Road Parking Lot Replacement Federal contract opportunity
- Solicitation number
- 697DCK-22-R-00367
About this file
This solicitation is seeking proposals for a road and parking lot replacement project at the Saint Albans Radar site in Vermont. The Federal Aviation Administration is requesting fixed price proposals to refurbish the road and parking area, including removing and replacing asphalt layers, repairing cracks, replacing gate sensors, and other work as detailed in the attached statement of work and drawings. The estimated cost is between $300,000 to $350,000 and proposals are due by July 12, 2022. The NAICS code is 237310 and the size standard is $39.5 million. This opportunity is set aside for small businesses. A site visit is scheduled for June 23, 2022 and questions are due by June 28, 2022.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 3f. QHB proposed pavement repairs.pdf | ||
| Wage Determination VT20220060.pdf | ||
| 16. 697DCK-22-R-00367+Solication+Document sam.gov.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Saint Albans, VT ARSR Bellevue Carriage Rd., Saint Albans, VT
Refurbish Road & Parking area at Radar Site
SPECIFICATIONS
For
Department of Transportation Federal Aviation Administration
NAS Defense Programs
FEDERAL AVIATION ADMINISTRATION APRIL, 2022
QHB ARSR ROAD REPAIRS SAINT ALBANS, VT
Table of Contents
TABLE OF CONTENTS
00 00 00 GENERAL
00 3119 Existing Conditions Information 00 73 19 Safety and Health Requirements
01 11 00 Summary of Work
01 33 00 Submittals Procedure
32 00 00 EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving
APPENDICES
Appendix A: Site Overview
FEDERAL AVIATION ADMINISTRATION April, 2022 QHB ARSR Road Repairs Saint Albans, VT
Safety and Health Requirements 00 73 19 - 1
SECTION 00 73 19 – SAFETY AND HEALTH REQUIREMENTS
PART 1 – GENERAL
1.1 Summary
A. Requirements for Employee Health and Safety
1.2 Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only:
A. Code of Federal Regulations (CFR)
1. OSHA General Industry Safety and Health Standards (29 CFR 1910), Publication V2206; OSHA Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA Publication 2207, which includes a combination of both parts 1910 and 1926 as they relate to construction safety and health.
2. National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61)
3. Federal Standard (Fed. Std.) 313A – Material Safety Data Sheets, Preparation and the
Submission of
4. FAA Order JO 3900.57A, Environmental and Occupational Safety and Health
(EOSH) Requirements in the Planning and Execution of Construction and Maintenance Activities at National Airspace System (NAS) Facilities. Specifically, FAA Form 3900-18, Pre-Construction EOSH Checklist. This checklist will be reviewed with the Contractor and FAA prior to construction.
1.3 Work Covered by This Section
A. This section is applicable to all work covered by this contract.
1.4 Definition of Hazardous Materials
A. Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910; and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, polychlorinated biphenyl’s (PCB’s), explosives, and radioactive material, but may include others.
1.5 Quality Assurance
A. Safety Meeting – Representatives of the Contractor shall meet with the CO and COR prior to the start of work, for the purpose of reviewing the contractor's safety and health programs and discussing implementation of all safety and health provisions pertinent to the work to be performed under this contract. The contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the work to be performed under the contract. If directed by the COR, this meeting may be held in conjunction with other meetings, which are scheduled to take place prior to start of work under this contract. The contractor’s principal on-site representative(s), the general superintendent, and his/her safety representative(s) shall attend this meeting.
B. Compliance with Regulations – All work, including the handling of hazardous materials shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply.
C. Contractor’s Responsibility – The contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of the work.
Safety and Health Requirements 00 73 19 - 2
D. Inspections, Tests and Reports – The required inspections, tests, and reports made by the contractor, subcontractors, specially trained technicians, equipment manufacturers, and others as required, shall be at the contractor’s expense.
E. Site Specific Safety Plan (SSSP) – The Contractor will be required to submit his plan for maintaining a safe work environment for construction workers employed on this project. As a minimum, the plan shall show weekly “tail gate meetings”, scheduled inspections of equipment to check for potential hazards created by wear, etc. and a statement that the current OSHA regulations on safety in the construction industry will be followed. The plan will be used by the COR to insure that the work is accomplished in accordance with safety practices.
The COR may stop any operation, which is in violation of the OSHA standards and fails to comply with the safety plan or accepted safe work practices.
1.6 Submittals
A. Accident and Fire Reporting
1. The Contractor shall report to the Contracting Officer any accident or fire occurring at the site of the work which causes:
a. A fatality or as much as one lost workday on the part of any employee of the Contractor or subcontractor at any tier;
b. Damage of $1,000 or more to Government-owned or leased property, either real or personal;
c. Damage of $1,000 or more to Contractor or subcontractor owned or leased motor vehicles or mobile equipment; or
d. Damage for which a contract time extension may be requested.
2. Accident and fire reports required by paragraph (1) above shall be accomplished by the following means:
a. Accidents or fires resulting in a death, hospitalization of five or more persons, or destruction of Government-owned or leased property (either real or personal), the total value of which is estimated at $100,000 or more, shall be reported immediately by telephone to the Contracting Officer or his/her authorized representative and shall be confirmed by telegram or facsimile transmission within 24 hours to the Contracting Officer. Such telegram or facsimile transmission shall state all known facts as to extent of injury and damage and as to cause of the accident or fire.
b. Other accident and fire reports required by paragraph (a) above may be reported by the Contractor using a state, private insurance carrier, or Contractor accident report form which provides for the statement of:
i. The extent of injury; and
ii. The damage and cause of the accident or fire.
c. Such report shall be mailed or otherwise delivered to the Contracting Officer within 48 hours of the occurrence of the accident or fire.
3. The Contractor shall assure compliance by subcontractors at all tiers with the requirements of this clause.
B. Permits – If hazardous materials are disposed of off-site, submit copies of permits from applicable Federal, State, or municipal authorities.
Safety and Health Requirements 00 73 19 - 3
1.7 Materials and Equipment
A. Special facilities, devices, equipment, clothing, and similar items used by the Contractor in the execution of work shall comply with applicable regulations.
1.8 Hazardous Materials
A. The contractor shall bring to the attention of the COR any material suspected of being hazardous which he/she encounters during execution of the work. A determination will be made by the COR as to whether the contractor shall perform tests, and/or if the material is found hazardous and additional protective measures are needed, a contract change may be required, subject to applicable provisions of this contract.
1.9 Suspension of Work
A. The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government. The Contracting Officer may, in emergency or life threatening situations notify the contractor orally to suspend, delay or interrupt all or any part of the work and issue the notice in writing immediately after the oral notice.
B. If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted:
1. by an act of the Contracting Officer in the administration of this contract, or
2. by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.
3. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
C. A claim under this clause shall not be allowed:
1. for any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and
2. unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
1.10 Protection
A. The Contractor shall take all necessary precautions to prevent injury to the public, building occupants, or damage to property of others. For the purposes of this contract, the public or building occupants shall include all persons not employed by the Contractor or related subcontractor.
Safety and Health Requirements 00 73 19 - 4
B. Work shall not be performed in any area occupied by Federal employees unless adequate steps are taken for the protection of the public and Federal employees.
C. Whenever practicable, the work area shall be fenced, barricaded, or otherwise blocked off to prevent unauthorized entry into the work area.
D. Alternate Precautions
1. When the nature of the work prevents isolation of the work area, alternate precautions such as the posting of signs, the use of signal persons, the erection of barricades or similar protection around particularly hazardous operations shall be used as appropriate.
END OF SECTION 00 73 19
Saint Albans, VT QHB ARSR Pavement Repair
EXISTING CONDITION INFORMATION 00 3119 - 1
DOCUMENT 00 3119 - EXISTING CONDITION INFORMATION
PART 1 - GENERAL
1.1 EXISTING CONDITION INFORMATION
A. This Document with its referenced attachments is part of the Procurement and Contracting Requirements for Project. They provide Owner's information for Bidders' convenience and are intended to supplement rather than serve in lieu of the Bidders' own investigations. They are made available for Bidders' convenience and information, but are not a warranty of existing conditions.
B. Photographic report of existing conditions that includes photographic documentation on existing conditions, prepared by FAA Engineering Services, is attached below.
EXISTING CONDITION INFORMATION 00 3119 - 2
Figure 1- Thickness of top layer outside fence to be removed
EXISTING CONDITION INFORMATION 00 3119 - 3
Figure 2- Gate sensor loops - 2 each side of gate to be removed and replaced
EXISTING CONDITION INFORMATION 00 3119 - 4
Figure 3- Sawcut beyond large crack just beyond 200-foot mark
EXISTING CONDITION INFORMATION 00 3119 - 5
Figure 4- Crackseal all cracks prior to overlay
EXISTING CONDITION INFORMATION 00 3119 - 6
Figure 5- Typical pavement condition outside fence
EXISTING CONDITION INFORMATION 00 3119 - 7
Figure 6- One of several pavement repairs requiring shimming and crack-sealing prior to overlay
EXISTING CONDITION INFORMATION 00 3119 - 8
Figure 7- Large repair to be shimmed and sealed and large parking area behind
EXISTING CONDITION INFORMATION 00 3119 - 9
Figure 8- Total pavement thickness outside fence
EXISTING CONDITION INFORMATION 00 3119 - 10
Figure 9- Typical road condition at one of several newly installed culvert on Bellevue Carriage Rd
EXISTING CONDITION INFORMATION 00 3119 - 11
Figure 10- Typical condition of Bellevue Carriage Rd. leading to site
EXISTING CONDITION INFORMATION 00 3119 - 12
Figure 11- Some of several deep pothole on Bellevue Carriage Rd.
END OF DOCUMENT 00 3119
FEDERAL AVIATION ADMINISTRATION APRIL 2022
QHB ARSR ROAD AND PARKING REPAIRS SAINT ALBANS, VT
Summary of Work 01 11 00 - 1
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SCOPE
Provide all labor, tools, equipment, materials, and supervision required to repair the existing asphalt pavement for the Saint Albans Radar road, parking lot and walkways. All work shall be conducted in accordance with this Statement of Work (SOW), Vermont Agency of Transportation Standard Specs for Construction and the Site Plan. The specified work shall be accomplished at the Radar on Bellevue Carriage Rd., Saint Albans, VT.
In general the work consists of the following:
1. The contractor shall furnish and install all material and equipment as specified in accordance with this statement of work, industry standard, and VTRANS standards.
2. The contractor shall fill potholes on Bellevue Carriage Rd. to allow for safe passage of equipment to the work site. Allowance for 10 tons of asphalt repair and placement to be included in bid price. Locations for repairs to be agree upon with COTR.
3. The contractor shall remove and replace all active gate sensors in pavement (4 total).
4. The contractor shall remove all trees and brush from ditches and restore ditches to original shape.
5. The contractor shall remove the top pavement layer of asphalt outside the fence (200 LF at 2-1/2” +/-). The contractor shall ensure positive drainage into the adjacent ditches.
6. The contractor shall apply a crack sealant and a tack coat over existing sub-base before applying a 2-1/2” wearing course outside the fence.
7. The contractor shall shim, crack-seal, apply a tack coat and install a 1-1/2” compacted wearing course over all existing pavement inside the fence.
8. The contractor shall saw cut along all transitions from any asphalt to be removed and asphalt that will remain.
9. The contractor shall seal joints between new and existing pavement.
10. The Contractor shall be solely responsible for any damage caused that is not directly related to the road work stated in this SOW for the Radar facility. This includes, but is not limited to, damage to underground or overhead cables still in use, sewer / storm drains and lines, the surrounding landscape, and local culverts, roadways/curbs unrelated to this project.
11. The Contractor shall be responsible for providing all temporary services needed for the paving of the SAINT ALBANS RADAR parking lot. This includes, but is not limited to, sanitary facilities, water, and temporary power.
12. The Contractor shall coordinate the schedule of work with the CO, the SSC, the COR and any applicable local authorities.
13. The Contractor shall be responsible for obtaining any permits required for the roadway repairs at the SAINT ALBANS RADAR facility. Contractor shall contact DigSafe prior to any excavation.
Summary of Work 01 11 00 - 2
1.2 APPLICABLE DOCUMENTS
A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and contract drawings referenced in this and the following divisions form a part of this specification are applicable only to the extent they were used as a basis of this design.
All references to codes, standards, specifications, and construction drawings refer to the latest editions (and any supplements) in effect on the date of the contract.
B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
1. CODE OF FEDERAL REGULATIONS (CFR):
a. OSHA General Industry Safety and Health Standards (29 CFR 1910), OSHA Construction Industry Standards (29 CFR 1926). OSHA 2202 is a condensed version of 29 CFR 1926. Each is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.
b. National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61).
2. FEDERAL STANDARD:
a. Preparation and the Submission of 313A Material Safety Data Sheets.
1.3 DEFINITIONS
A. Federal Aviation Administration (FAA) - The terms "Federal Aviation Administration" (FAA) and "Government" as used herein denotes the "owner"
B. Contracting Officer (CO) - The term "Contracting Officer" (CO) as used herein denotes the person designated to act for the Government in the performance of this contract.
C. Contracting Officers Representative (COR) - The term "Contracting Officers Representative" (COR) as used herein denotes the representative of the Contracting Officer at the job site. The COR’s authority is limited. These limitations are defined in the Letter of Delegation provided to the COR and the Contractor at the preconstruction meeting.
D. Contractor and Subcontractor - The term "Contractor" as used herein denotes the firm retained by the FAA to perform and complete work required by the Contract. The term "subcontractor" as used herein denotes the person or firm retained by the Contractor to perform a particular unit of work required by the Contractor. Subcontractors shall be required to meet all specifications required of the Contractor.
E. Furnished Material - The term "furnished material" (GFM) as used herein denotes all
Government Furnished Equipment (GFE) and material furnished by the Federal Aviation Administration. Any and all material not listed as “Furnished” shall be supplied by the Contractor. Furnished material is listed in Section 01 11 00, Part 3.3.
1.4 GOVERNMENT FURNISHED EQUIPMENT AND MATERIAL (GFE & GFM)
Not Applicable
Summary of Work 01 11 00 - 3
1.5 CONSTRUCTION CONDITIONS
A. Preconstruction Conference - The Contractor shall attend a preconstruction conference at the time and location specified by the CO. Local procedures related to ingress, egress and security will be discussed. Requirements for material disposal, security and safety will be discussed.
Compliance with these procedures while on site is mandatory.
B. Conflict Resolution - The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings will rule in all cases. Specifications will govern over drawings. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and the COR shall render an interpretation and decision.
C. Inspection
1. Access for Inspection - The Contractor shall allow the COR complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, will be inspected by the COR before being obscured by the next operation of the Contractor. In all cases, the COR shall be informed accordingly and given access to the work. Work obscured before inspection and acceptance by the COR, may, at the option of the COR be opened for inspection at no additional cost to FAA.
2. Joint Acceptance Inspection - The COR shall inspect all work after substantial completion including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The COR shall notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly. After the COR reviews the contract documents and verify the Contractor has completed all required work, a Joint Acceptance Inspection (JAI), which is a FAA internal approval process, will be held.
D. Existing Utilities - Subsurface utilities and cables, whose existence is known to FAA, are shown on the contract drawings in approximate locations. Other utilities may not be shown on the contract drawings. The Contractor shall ring out and mark the existing power and control cable runs prior to any construction activities so as to maintain clearances from underground cables during construction. The Contractor shall field verify the location of underground utilities before excavating cable trenches and concrete foundations. This will be accomplished, in part, by coordinating with the FAA and the COR.
1. Hand Excavation - Hand excavation methods will be used in locating all existing utilities.
Any damage caused by the Contractor will be repaired immediately by the Contractor at no additional cost to FAA. Repairs, if required, will be in accordance with the specifications and conditions stipulated by the COR.
E. Project Coordination - The Contractor shall be required to coordinate construction activities with the FAA through the COR. All work, which affects Facilities and Equipment, shall be coordinated and approved by FAA personnel through the COR twenty-one (21) days in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. If weather conditions or operations preclude a scheduled shutdown of
Summary of Work 01 11 00 - 4 the FAA facility, the Contractor shall reschedule the work. The Contractor shall be required to coordinate all power shutdowns of existing facilities with the FAA, through the COR, twenty-one (21) days in advance. Each shutdown for testing or cut-overs will be limited to off-peak hours, with the facility placed back in service at the end of the workday or as stipulated by the FAA. The Contractor shall not be allowed any extension of time or compensation for lack of compliance with this requirement.
F. Layout of Work - The Contractor shall field verify measurements and work from the established base lines and bench marks indicated on the drawings and will be responsible for all measurements in connection therewith. The Contractor will furnish, at his/her own expense, all templates, equipment, tools, materials, and labor as may be required in laying out any part of the work.
G. Permits, Inspection, Licenses, Certificates - The Contractor shall obtain and pay fees for permits, licenses, or certificates required by Federal, State and City/Town officials as necessary to perform the work, prior to starting construction, and in a timely manner to avoid delays in starting the job. The Contractor will abide by all requirements dictated by the municipality for such permits without any additional cost.
H. Compliance with Local and Other Codes - The Contractor shall comply with codes and standards, such as the National Electric Code, latest edition or local code. Where the requirements of the specifications and drawings exceed those codes, the Contractor shall comply with the requirements of the specifications and drawings.
I. Temporary Facility - The Contractor shall provide and pay for all temporary services and facilities as specified below and as necessary for the proper and expeditious execution of the work. The Contractor shall make, or have made all connections to existing services and sources of supply as necessary and/or indicated and pay all charges for same. The Contractor shall remove all such temporary installations and connections when no longer necessary for the project work.
1. Temporary Water - The Contractor shall make arrangements to furnish a potable water supply for workers and project work, and pay for all temporary water and services, in accordance with OSHA requirements.
2. Temporary Toilets and Sanitation - The Contractor shall provide ample and suitable on-site sanitary conveniences with proper enclosures for the use of the workers and other personnel employed at the site, in accordance with OSHA requirements. Locations will be subject to approval from the COR. After completion of the work, such conveniences will be promptly removed from the site.
3. Temporary Light and Power - The Contractor shall arrange for, provide and maintain all temporary electric light and power as required throughout the work. The Contractor shall pay all costs for the installation and use of such temporary light and power.
a. The Contractor shall furnish, install, connect and maintain all the wiring, sockets, lamps, receptacles, switches, feeders, circuit work, etc. necessary to provide temporary artificial illumination and power as required for the performance of all work covered by these specifications or which may be required for safety and for inspection purposes.
Summary of Work 01 11 00 - 5
Contractor shall provide all power unless coordinated and approved by the FAA and COR that the contractor may use onsite available receptacles.
K. Protection of Existing Vegetation, Improvements and Structures - The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, foundations, vegetation, etc., during construction. Any areas damaged by the Contractor or any subcontractors, will be repaired or replaced to their original conditions by the Contractor at no additional cost to FAA. Repairs will be approved by the COR and will match to original finish.
The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.
L. Schedules
1. Project Schedule - The Contractor shall, within ten (10) calendar days from date of award of contract, submit to the CO for approval a practical project schedule. The schedule will show the order in which the Contractor proposes to carry out the work, the date on which he/she shall start the several salient features (including procurement of materials, plant and equipment), night work required including cutovers, and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time. The Contractor shall enter on the chart the actual progress at such intervals as directed by the CO.
The project schedule shall include milestone schedule for payments. The milestones should be stated with requested reimbursement for each milestone (based upon actual costs, overhead and profit).
2. Progress Schedule - The Contractor, if requested by the CO, shall submit a progress schedule at such intervals as directed by the CO. If the Contractor fails to submit a progress schedule within three (3) business days, the CO may withhold approval of progress payment estimates until the Contractor submits the required progress schedule.
3. Hours of Work - Unless otherwise approved by the COR, all work shall be based on a standard 8 - hour workday unless longer hours have been approved and accomplished between the hours of 6:00 a.m. to 5:00 p.m. daily, except weekends and Federal holidays.
Any weekend work must be coordinated and agreed upon with the COR.
M. Site Access – Access to the site will be via a pre-determined route identified and agreed upon at the preconstruction conference. The Contractor is advised that the SAINT ALBANS RADAR is part of a secured facility and all personnel, possessions, equipment, materials, vehicles, etc. are subject to inspection at the discretion of security personnel while on the premises. All Contractor personnel shall maintain on their person, at all times while on the grounds, current photo identification. Contractor personnel shall be prepared to relinquish their identification for review by security at any time while on the grounds.
The Contractor shall provide the FAA representative with a list of the personnel requiring access to the site. The contractor shall be prepared to provide additional information on all personnel as required by security to issue temporary badges. It will be necessary to coordinate all activities with the FAA representative to minimize interference with site operations.
N. Special Site Conditions – N/A
Summary of Work 01 11 00 - 6
O. Equipment and Waste Disposal - The Contractor shall provide on-site covered containers for the collection of construction waste materials, debris and rubbish and periodically remove the aforementioned materials from the site. Any spillage on access and haul routes will be cleaned up immediately. Disposal location to be determined by the Contractor and approved by the COR. All equipment, materials, spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents will be disposed of off site in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste. The Contractor will pay disposal fees and miscellaneous charges. Copies of all documentations of the disposal of any hazardous wastes will be submitted in accordance with Section 01 35 43.13.
P. Cleanup - The work site shall be kept clean and orderly during the progress of work.
Q. Final Cleaning - After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment will be cleaned. All debris will be removed from the general site area.
1.6 Sequence of Work
The Contractor shall be required to submit detailed sequence of work for work at the facility. The plans shall limit any impact to the SSC and personnel. The plans will describe, in detail, all preparatory work, and estimated time required for each event listed in the plans. A list of equipment and quantity and type of personnel will be attached.
1.7 SAFETY
OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:
A. Safety Plan - The Contractor shall have a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site. Two (2) copies of the plan shall be submitted to the CO for review and approval. As a minimum, the safety plan shall require weekly "tailgate" meetings, scheduled inspections of equipment which check for potential hazards created by wear, damages, etc. and a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations, are followed. The plan will be used by the COR, who is OSHA trained, to insure that the work is accomplished in accordance with accepted safety practices.
B. First Aid and CPR - At least one (1) employee shall have a current certification in First Aid and
Cardio-Pulmonary Resuscitation (CPR) and be on the site at all times. Such employee shall be designated to provide first response medical treatment to site personnel in the event of an accident or other medical emergency. The employee shall not be permitted to work on live electrical circuits or be placed in any other situation, which may endanger or interfere in their ability to provide medical treatment.
C. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. Documentation or other evidence of training
Summary of Work 01 11 00 - 7 may be requested by the COR at any time. Personnel without adequate training will be prohibited from using such equipment.
D. Material Safety Data Sheets - The Contractor shall have Material Safety Data Sheets (MSDS) conforming to Federal Standard 313A, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. One (1) copy of each MSDS will be submitted to the CO and one (1) copy of each MSDS will be kept on file at the job site at all times. The Contractor and subcontractors shall be prohibited from handling any material, which does not have an applicable MSDS on file at the site until such MSDS arrives on site.
E. Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged, fire extinguishers with the proper NFPA rating.
F. HAZCOM Program - The Contractor shall have a hazard communications (HAZCOM) program.
The Contractor and each subcontractor shall submit a copy of their HAZCOM program as well as a copy of their current OSHA 200 form, if requested.
G. Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent, badged contractor’s foreman is required at the job site. The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.
H. Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.
PART 2 - MATERIALS AND EQUIPMENT
2.1 FAA/GOVERNMENT-FURNISHED EQUIPMENT/MATERIAL
Not Applicable
2.2 CONTRACTOR-FURNISHED MATERIAL AND EQUIPMENT
A. Material Deliveries - All material deliveries made under this contract shall be arranged for delivery to the Contractor's material staging area. This area shall be located as determined at the preconstruction conference. Delivery vehicles shall be directed to the material staging area.
B. Storage and Protection - The Contractor, through the COR, shall secure from FAA all necessary clearances for storage areas on site, including any time limitations upon the use of such areas.
The storage and protection of Contractor material will be the sole responsibility of the Contractor. The Contractor shall provide at his/her own expense all fencing, shelters and security personnel as may be necessary for the protection of the material and equipment.
PART 3 - EXECUTION
3.1 WORK SEQUENCE
A. Work shall be performed in the following sequence:
Summary of Work 01 11 00 - 8
1. FAA shall provide the Contractor with all necessary shop drawings, product data, and samples for all Government furnished equipment.
2. The Contractor shall submit all required product information, shop drawings, and samples as required in the specifications. Protective device time current characteristic curves will be those for the equipment being furnished. Alternate protective devices will be submitted for approval.
3. The Contractor is responsible for handling, storing, and installing all furnished and non-furnished equipment.
4. Upon completion of work the contractor shall clean the affected area and repair any damage caused due to construction. A final walk through will be performed with the COR to insure a satisfactory end result.
3.2 CONTRACTOR USE OF PREMISES
A. General - During the construction period the Contractor shall have full use of the premises for construction operations, including use of the site. The Contractor's use of the premises is limited only by the Government’s right to perform work or to retain other contractors on portions of the Project.
B. Use of the Site - Limit use of the premises to work in areas indicated. Confine operations to areas within contract limits indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated.
1. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government, the Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3.3 GOVERNMENT-FURNISHED EQUIPMENT / MATERIAL- Not Applicable
END OF SECTION 01 11 00
FEDERAL AVIATION ADMINISTRATION April 2022
SUBMITTAL PROCEDURES 01 33 00 - 1
SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 GENERAL
A. Samples, certificates, reports, catalog cuts, letters, shop drawings, etc. required under this specification shall be submitted to the CO and/or Project Engineer. All products specified herein to meet certain published specifications shall have clarifications submitted which state compliance with such specifications. The Contractor shall provide a minimum of ten (10) business days for FAA to review the submittals, unless otherwise noted in the specifications.
Rejection of submittals shall not be grounds for claims by the Contractor.
1.2 SUBMITTAL PROCEDURE
A. Three (3) complete sets (to include one reproducible) of all shop drawings and/or product data shall be submitted by the Contractor to the CO. Two sets will be marked and returned to the Contractor by the Project Engineer, with the approval status noted.
B. All submittals shall be accompanied by transmittal letters identifying the contents of the submittal. Transmittal letters shall consist of one original and one copy.
C. Work requiring an approved submittal shall not be initiated prior to approval of that submittal.
D. Submittals from subcontractors shall be reviewed and approved by the Contractor and coordinated with any other work involved before they are transmitted for review. Submittals shall be complete and detailed, and assembled in sets. Incomplete or inadequate descriptions will not be approved.
1.3 SUBMITTAL APPROVAL
A. Approved As Submitted - If “Approved As Submitted” is marked by the Project Engineer, each copy of the submittal will be identified as having received such approval by being stamped (or annotated) and dated. After submittals have been approved, no changes or substitutions will be permitted without written approval by the Project Engineer.
B. Approved As Noted - If “Approved As Noted” is marked by the Project Engineer, the submittal is satisfactory contingent upon the Contractor’s acceptance of comments and notations. If accepted, resubmittal is not required.
C. Not Approved - If “Not Approved” is marked by the Project Engineer, the submittal does not meet job requirements and the Contractor must resubmit. If submittal is disapproved, the Contractor shall resubmit the corrected material in the same quantity as specified for the original submittal.
1.4 SUBSTITUTE MATERIAL
The Contractor may submit for approval material other than that specified if it meets the following:
A. Meets or exceeds the specifications as determined by the FAA.
B. Material is available on a timely basis.
C. Substitution of a material shall not obligate the FAA for additional costs which may be associated with furnishing and installing the substitute material. Substitution submissions shall be clearly marked as such and shall meet the requirements of paragraph 2.1, Submittals. The
FEDERAL AVIATION ADMINISTRATION April 2022
SUBMITTAL PROCEDURES 01 33 00 - 2
Contractor shall allow ten (10) business days from date of receipt by the Project Engineer for substitute submission approval.
END OF SECTION 01 33 00
ASPHALT PAVING 32 12 16 - 1
SECTION 32 12 16 - ASPHALT PAVING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Hot-mix asphalt paving.
B. Related Sections:
1. Section 31 23 00 "Excavation and Fill"
1.2 DEFINITION
A. Hot-Mix Asphalt Paving Terminology: Refer to ASTM D 8 for definitions of terms.
B. VTRANS: Vermont Agency of Transportation
1.3 SUBMITTALS
A. Product Data: For each type of product indicated. Include technical data and tested physical and performance properties.
1. Job-Mix Designs: For each job mix proposed for the Work.
B. Qualification Data: For qualified Installer.
C. Material Certificates: For each paving material, from manufacturer.
1.4 QUALITY ASSURANCE
A. Manufacturer Qualifications: A paving-mix manufacturer/plant registered with and approved by
VTRANS
B. Testing Agency Qualifications: Contractor shall engage an independent testing agency. Test reports shall be submitted to the government for approval. Qualified according to ASTM D 3666 for testing indicated, as documented according to ASTM E 548.
C. Regulatory Requirements: Comply with materials, workmanship, and other applicable requirements of Vermont Agency of Transportation, Standard Specifications for Construction.
ASPHALT PAVING 32 12 16 - 2
1.5 PROJECT CONDITIONS
A. Environmental Limitations: Do not apply asphalt materials if subgrade is wet or excessively damp, if rain is imminent or expected before time required for adequate cure, or if the following conditions are not met:
1. Prime Coat: Minimum surface temperature of 60 deg F.
2. Asphalt Base Course: Minimum surface temperature of 40 deg F and rising at time of placement.
3. Asphalt Wearing Course: Minimum surface temperature of 60 deg F at time of placement.
PART 2 - PRODUCTS
2.1 AGGREGATES
A. General: Use materials and gradations that have performed satisfactorily in previous installations.
B. Coarse Aggregate: ASTM D 692, sound; angular crushed stone, crushed gravel, or cured, crushed blast-furnace slag.
C. Fine Aggregate: ASTM D 1073, sharp-edged natural sand or sand prepared from stone, gravel, cured blast-furnace slag, or combinations thereof.
1. For hot-mix asphalt, limit natural sand to a maximum of 20 percent by weight of the total aggregate mass.
D. Mineral Filler: ASTM D 242, rock or slag dust, hydraulic cement, or other inert material.
2.2 ASPHALT MATERIALS
A. Asphalt Binder: AASHTO M 320 or AASHTO MP 1a, PG 64-22.
B. Asphalt Cement: AASHTO M226, Table 2, AC-20, except that the loss on heating shall be not greater than 0.8 for viscosity-graded material.
C. Prime Coat: Asphalt emulsion prime coat complying with VTRANS Subsection 702.04 D. Tack Coat: Asphalt emulsion prime coat complying with VTRANS Subsection 702.04.
E. Water: Potable.
2.3 AUXILIARY MATERIALS
A. Sand: ASTM D 1073, Grade Nos. 2 or 3.
ASPHALT PAVING 32 12 16 - 3
B. Joint Sealant: ASTM D 6690, Type II or III, hot-applied, single-component, polymer-modified bituminous sealant. VTRANS Subsection 707.04
2.4 MIXES
A. Hot-Mix Asphalt: Dense, hot-laid, hot-mix asphalt plant mixes approved by VTRANS and complying with the following requirements:
1. Provide mixes with a history of satisfactory performance in geographical area where Project is located.
2. Base Course: 2” minimum VTRANS section 406
3. Wearing Course: 1.5” minimum VTRANS section 401
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that subgrade is dry and in suitable condition to begin paving.
B. Proof-roll subbase using heavy, pneumatic-tired roller to located areas that are unstable or that require further compaction.
C. Proceed with paving only after unsatisfactory conditions have been corrected.
D. Tack Coat: Apply uniformly to vertical surfaces abutting or projecting into new, hot-mix asphalt paving at a rate of 0.05 to 0.15 gal./sq. yd.
一 Allow tack coat to cure undisturbed before applying hot-mix asphalt paving.
一 Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove spillages and clean affected surfaces.
3.2 SURFACE PREPARATION
A. General: Immediately before placing asphalt materials, remove loose and deleterious material from substrate surfaces. Ensure that prepared subgrade is ready to receive paving.
1. Sweep loose granular particles from surface of unbound-aggregate base course. Do not dislodge or disturb aggregate embedded in compacted surface of base course.
B. Prime Coat: Apply uniformly over surface of compacted unbound-aggregate base course at a rate of
0.15 to 0.50 gal./sq. yd. Apply enough material to penetrate and seal but not flood surface. Allow prime coat to cure for 72 hours minimum.
1. If prime coat is not entirely absorbed within 24 hours after application, spread sand over surface to blot excess asphalt. Use enough sand to prevent pickup under traffic. Remove loose sand by sweeping before pavement is placed and after volatiles have evaporated.
2. Protect primed substrate from damage until ready to receive paving.
ASPHALT PAVING 32 12 16 - 4
C. Tack Coat: Apply uniformly to surfaces of existing pavement at a rate of 0.05 to 0.15 gal./sq. yd.
1 Allow tack coat to cure undisturbed before applying hot-mix asphalt paving.
2 Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove spillages and clean affected surfaces.
3.3 HOT-MIX ASPHALT PLACING
A. Machine place hot-mix asphalt on prepared surface, spread uniformly, and strike off. Place asphalt mix by hand to areas inaccessible to equipment in a manner that prevents segregation of mix. Place each course to required grade, cross section, and thickness when compacted.
1 Place hot-mix asphalt base course in number of lifts and thicknesses indicated.
2 Place hot-mix asphalt surface course in single lift.
3 Spread mix at minimum temperature of 250 deg F.
4 Begin applying mix along centerline of crown for crowned sections and on high side of one-way slopes unless otherwise indicated.
5 Regulate paver machine speed to obtain smooth, continuous surface free of pulls and tears in asphalt-paving mat.
B. Place paving in consecutive strips not less than 10 feet wide unless infill edge strips of a lesser width are required.
1. After first strip has been placed and rolled, place succeeding strips and extend rolling to overlap previous strips. Complete a section of asphalt base course before placing asphalt surface course.
C. Promptly correct surface irregularities in paving course behind paver. Use suitable hand tools to remove excess material forming high spots. Fill depressions with hot-mix asphalt to prevent segregation of mix; use suitable hand tools to smooth surface.
3.4 JOINTS
A. Construct joints to ensure a continuous bond between adjoining paving sections. Construct joints free of depressions, with same texture and smoothness as other sections of hot-mix asphalt course.
1 Clean contact surfaces and apply tack coat to joints.
2 Offset longitudinal joints, in successive courses, a minimum of 6 inches.
3 Offset transverse joints, in successive courses, a minimum of 24 inches.
4 Construct transverse joints as described in “Construction of Hot Mix Asphalt Pavements”.
5 Compact joints as soon as hot-mix asphalt will bear roller weight without excessive displacement.
6 Compact asphalt at joints to a density within 2 percent of specified course density.
ASPHALT PAVING 32 12 16 - 5
3.5 COMPACTION
A. General: Begin compaction as soon as placed hot-mix paving will bear roller weight without excessive displacement. Compact hot-mix paving with hot, hand tampers or with vibratory-plate compactors in areas inaccessible to rollers.
1. Complete compaction before mix temperature cools to 185 deg F.
B. Breakdown Rolling: Complete breakdown or initial rolling immediately after rolling joints and outside edge. Examine surface immediately after breakdown rolling for indicated crown, grade, and smoothness.
Correct laydown and rolling operations to comply with requirements.
C. Intermediate Rolling: Begin intermediate rolling immediately after breakdown rolling while hot-mix asphalt is still hot enough to achieve specified density. Continue rolling until hot-mix asphalt course has been uniformly compacted to the following density:
1. Average Density: 96 percent of reference laboratory density according to AASHTO T 245, but not less than 94 percent nor greater than 100 percent.
D. Finish Rolling: Finish roll paved surfaces to remove roller marks while hot-mix asphalt is still warm.
E. Edge Shaping: While surface is being compacted and finished, trim edges of pavement to proper alignment. Bevel edges while asphalt is still hot; compact thoroughly.
F. Repairs: Remove paved areas that are defective or contaminated with foreign materials and replace with fresh, hot-mix asphalt. Compact by rolling to specified density and surface smoothness.
G. Protection: After final rolling, do not permit vehicular traffic on pavement until it has cooled and hardened.
3.6 INSTALLATION TOLERANCES
A. Pavement Thickness: Compact each course to produce the thickness indicated within the following tolerances:
1 Base Course: Plus or minus 1/2 inch.
2 Surface Course: Plus 1/4 inch, no minus.
B. Pavement Surface Smoothness: Compact each course to produce a surface smoothness within the following tolerances as determined by using a 10-foot straightedge applied transversely or longitudinally to paved areas:
1. Base Course: 1/4 inch
2. Surface Course: 1/8 inch
3. Crowned Surfaces: Test with crowned template centered and at right angle to crown.
Maximum allowable variance from template is 1/4 inch.
ASPHALT PAVING 32 12 16 - 6
3.7 FIELD QUALITY CONTROL
A. Testing Agency: Contractor shall engage a qualified testing agency to perform tests and inspections.
B. Additional resting and inspecting at Contractor’s expense shall be performed to determine compliance of replaced or additional work with specified requirements.
C. Thickness: In-place compacted thickness of hot-mix asphalt courses will be determined according to
ASTM D 3549.
D. Surface Smoothness: Finished surface of each hot-mix asphalt course will be tested for compliance with smoothness tolerances.
E. In-Place Density: Testing agency will take samples of uncompacted paving mixtures and compacted pavement according to ASTM D 979.
1. Reference maximum theoretical density will be determined by averaging results from four samples of hot-mix asphalt-paving mixture delivered daily to site, prepared according to ASTM D 2041, and compacted according to job-mix specifications.
2. In-place density of compacted pavement will be determined by testing core samples according to ASTM D 1188 or ASTM D 2726.
a. One core sample will be taken for every 2000 sq. ft. or less of installed pavement, with no fewer than 3 cores taken.
b. Field density of in-place compacted pavement may also be determined by nuclear method according to ASTM D 2950 and correlated with ASTM D 1188 or ASTM D 2726.
F. Remove and replace or install additional hot-mix asphalt where test results or measurements indicate that it does not comply with specified requirements.
3.8 DISPOSAL
A. Except for material indicated to be recycled, remove excavated materials from Project site and legally dispose of them in an EPA-approved landfill.
END OF SECTION 32 12 16
| Cover Page-QHB ARSR Road |
| Table of Contents -QHB ARSR Road |
| 00 73 19 - Safety and Health Requirements -QHB ARSR Road |
| SECTION 00 73 19 – SAFETY AND HEALTH REQUIREMENTS |
| END OF SECTION 00 73 19 |
| 00 3119 - EXISTING CONDITION INFORMATION |
| PART 1 - GENERAL |
| 1.1 EXISTING CONDITION INFORMATION |
This is the start of the file's text. The full file is on GovTribe.