This solicitation document requests proposals for boiler inspection, safety device testing, calibration, and combustion tuning services for five boilers located at the VA Central Iowa Health Care System in Des Moines, Iowa. The base period of performance is from April 1, 2024 to March 31, 2025, with four optional one-year extensions. Proposals are due by December 25, 2023. The solicitation is set aside 100% for veteran-owned small businesses. Services required include annual internal and external boiler inspections, testing of safety devices, and boiler combustion tuning visits twice per year. Inspections must comply with National Board, ASME, and OSHA standards. Technicians must meet minimum qualifications and experience levels. The selected contractor will report inspection findings, test data, and service records and provide recommendations to the VA.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26324Q0148_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF 1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. UEI: EFT:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
636-24-2-9073-0012
36C26324Q0148 12-11-2023
Steve Ashby 319-887-4935 12-25-2023
10:00 CST
Department of Veterans Affairs
NETWORK 23 CONTRACTING OFFICE
1303 5th St, Suite 300 Coralville IA 52241
X 100
X
238220
$19 Million
N/A
X
VA Central Iowa Health Care System 3600 30th Street Des Moines IA 50310
NETWORK 23 CONTRACTING OFFICE
1303 5th St, Suite 300 Coralville IA 52241
Tungsten Electronic Invoicing VA Tungsten Number: AAA544240062 va.registration@tungsten-network.com Refer to VAAR Clause 852.232-72
See CONTINUATION Page
Boiler inspection, and safety device testing and certification. for VA Central Iowa Health Care System.
Period of Performance: 04/01/2024 -03/31/2025
Plus four 1 year option periods.
This is a 100% Veteran Owned Small Business set-aside.
Contractors are responsible for the correct SCA Wage and Determination classification of workers and compliance with all wage and hour laws.
Prospective offerors must be verified as a VOSB in the VIP system and have an active SAM system registration prior to submission of their offer.
See CONTINUATION Page
636-3640162-9073-854100-2543-030050190 636-24-2-9073-0012
X X
X ONE
John Milroy Contracting Officer
36C26324Q0148
Table of Contents
SECTION A
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
B.2 STATEMENT OF WORK
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES (NOV 2023)
C.2 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT
STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (NOV 2023)
C.3 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000) ... 26
C.4 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
C.5 VAAR 852.219-74 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED
VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)
C.6 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)
(DEVIATION)
C.7 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
C.8 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ... 32
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS
SECTION E - SOLICITATION PROVISIONS
E.1 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
E.2 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (SEP 2023)
E.3 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL
SERVICES (NOV 2021)
E.4 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—
COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
E.5 52.216-1 TYPE OF CONTRACT (APR 1984)
E.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
(Continuation from Standard Form 1449, block 18A.)
1. CONTRACT ADMINISTRATION. All contract administration matters will be handled by the following individuals:
a) Contractor Information Company Name and Address:
Data Universal Numbering System (DUNS) Number:
Contact Person(s) Name:
Contact Person(s) Email:
Contact Person(s) Telephone:
b) Government Information
Steve Ashby Contract Specialist Department of Veterans Affairs Network Contracting Office 23 (NCO 23) 2501 W. 22nd Street Sioux Falls, South Dakota 57105
2. CONTRACT REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with FAR 52.232-33, Payment by Electronic Funds Transfer – System for Award Management, and VAAR 852.232-72, Electronic Submission of Payment Requests.
3. INVOICES: Invoices shall be submitted in arrears. Submission will be monthly for the previous 30-day period of performance and no later than 15 calendar days after the close of the period of performance being invoiced for. Invoices shall be based on the applicable fixed rates for services provided to VA as in accordance with the contract terms and conditions. The VA Technical Representative (VATR) will review all invoices submitted. The VATR is responsible for certifying invoices for payment for only those services received and deemed acceptable by VA.
4. GOVERNMENT INVOICE ADDRESS: All invoices shall be submitted by the contractor via the Tungsten Network (previously OB10) electronic invoicing system. Refer to the Tungsten Network website at http://www.tungsten-network.com/us/en/veterans-affairs-us/ for additional information for system registration, user guides, and help desk contacts.
5. ACKNOWLEDGEMENT OF AMENDMENTS: The offeror acknowledges receipt of Amendments to the Solicitation numbered and dated as follows:
Amendment Date
B.2 STATEMENT OF WORK
I. Boiler Inspection
Background:
Contractor shall inspect 5 boilers (described further below) at VA Central Iowa Health Care System.
Boiler #1: 20159_PA-1000 Boiler #2: 20159_PA-2000 Boiler #3: 20148_PA-3000 Boiler #4: 20148_PA-4000 Boiler #5: 88446
Place of Performance:
VA Central Iowa Health Care System 3600 30th Street Des Moines, IA 50310-5753
Period of Performance:
Base period: 04/01/2024 – 03/31/2025 Option 1: 04/01/2025 – 03/31/2026 Option 2: 04/01/2026 – 03/31/2027 Option 3: 04/01/2027 – 03/31/2028 Option 4: 04/01/2028 – 03/31/2029
Services to be performed:
Inspection of Boilers
1. Introduction:
A. The Central Iowa VA Health Care System (VAHCS), 3600 30th Street, Des Moines, Iowa 50310-5753 has.
a central boiler plant to provide steam for heating and air conditioning, domestic hot water, kitchens, laundries and sterilization.
B. Boiler plant safety, reliability, efficiency, and equipment longevity are paramount concerns of VAMC.
management. Boilers are pressurized devices containing steam and hot water. They can fail.
catastrophically causing injuries and death and massive property damage. Regular inspections by experts are an essential part of a program to address these concerns.
http://www.tungsten-network.com/us/en/veterans-affairs-us/ http://www.tungsten-network.com/us/en/veterans-affairs-us/
C. This “Statement of Work” describes the requirements for the boiler inspections to be performed by “Qualified Professional Inspectors” under contract.
D. “Qualified Professional Inspectors” as defined below shall perform internal and external inspections on high pressure (over 15 psig) steam boilers.
E. Part II of this “Statement of Work” covers the work of burner and instrument technicians inspecting, testing and calibrating burners, controls and instruments.
2. “Qualified Professional Inspector” is defined as anyone or combination of:
A. A boiler inspector who has a valid commission from the National Board of Boiler and Pressure Vessel Inspectors (NB).
B. A boiler inspector who has qualified by passing a written examination under the laws, rules and regulations of the State of Iowa.
C. A boiler inspector who is regularly employed as a boiler inspector by a jurisdiction which has adopted and administers one or more sections of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code as a legal requirement, and has a representative serving as a member of the ASME Conference Committee.
D. A boiler inspector who is regularly employed by an insurance company which has been licensed or registered by the appropriate authority of a State of the United States to write boiler or pressure vessel insurance.
3. Reference Materials:
The “Qualified Professional Inspector” shall demonstrate familiarity with and ready access to the current versions of the following codes and manuals:
ASME Boiler and Pressure Vessel Code:
Section I - Power Boilers Section IV - Heating Boilers Section VI - Care and Operation of Heating Boilers Section VII - Care of Power Boilers ASME B31.1, Power Piping Code ASME CSD-1, Controls and Safety Devices for Automatically Fired Boilers ANSI/NB-23, National Board Inspection Code NFPA 85, Boiler and Combustion Systems Hazards Code VHA Boiler Plant Safety Device Testing Manual, 7th Ed.
4. Inspection Requirements:
A. Annual internal and external inspections are required for each boiler.
B. At least two weeks’ notice to VAMC is required prior to an inspection. Also, the inspection must be scheduled for periods when VAMC determines that the boilers that will be inspected internally will not be needed for steam supply and when the VA Technical Representative (VATR) or his/her designate is available on site to monitor the inspections. To maintain steam service, typically only one boiler at a time will be scheduled for internal inspections per inspection visit. Thus, multiple visits per VAMC facility will be necessary every year to inspect all the boilers internally.
C. Coordinate the inspection schedule with the VATR so that VAMC can prepare the boilers for the inspections in advance and have personnel available to monitor the inspections.
D. Boilers scheduled for internal inspection will be prepared for the inspection by VAMC prior to the scheduled arrival of the inspector. This includes cooling the boilers to near ambient temperature and having all manways, handholes and furnace access doors open; the boilers cleaned of loose materials waterside and fireside; electrical “lock-out, tag-out” in place; connecting piping isolated; proper illumination provided;
compliance with “confined space” access requirements including having safety personnel present in the boiler plant.
E. VAMC will comply with any other requirements of the inspector that are considered reasonable by VAMC and have been presented in writing at least two weeks prior to the scheduled inspection.
F. The boiler inspections shall comply with the guidelines in the current issue of the NATIONAL BOARD INSPECTION CODE, Part RB, Inservice Inspection of Pressure-Retaining Items, and ASME Boiler and Pressure Vessel Code, Section VI or VII as applicable. In addition to those guidelines, the inspections shall comply with all VAMC requirements as listed in this document.
G. The inspector must completely enter the internal spaces of the boiler and visually inspect all internal surfaces that can be accessed.
H. Methods for testing safety devices shall comply with VHA Boiler Plant Safety Device Testing Manual, 7th Edition.
I. Summary of the minimum inspection requirements for boilers:
1) Review the boiler history including: operating conditions, date of last inspection, current inspection certificate, ASME stamping on boiler, National Board registration number, history of repairs and modifications. Review boiler logs, water test reports, and reports on tests performed on the burner controls and interlocks.
2) Assess the external parts of the boilers and boiler accessories and piping and valves for safety, accessibility, proper maintenance and operation, cleanliness, and compliance with codes.
3) Inspect for evidence of leakage of combustion gases or fluids, externally and internally, including all gaskets.
4) Inspect foundations for signs of stress such as cracking or movement.
5) Inspect boilers externally and internally for defects including bulges, blisters, cracks, wasted or eroded material, warping, general corrosion, grooving and pitting, damaged insulation.
6) Inspect all accessible internal surfaces for waterside and fireside deposits, including scaling, sediment, debris, carbon deposits.
7) Examine all stays and stayed plates
8) Inspect gas side baffles.
9) Inspect internal drum surfaces and steam separating internals.
10) Inspect soot blowers and verify proper alignment.
11) Inspect tubes, tube ends and tube alignment. Check for sagging tubes.
12) Verify that all nozzles of internal piping such as feedwater admission and bottom blowoff collection are clear with no obstructions.
13) Inspect seating surfaces of manways and handholes.
14) Check that boiler structure is plumb and level with no excessive deformations.
15) Check for missing items such as bolts and nuts.
16) Examine all valve and pipe connections to the pressure vessel.
17) Inspect refractory including burner throat, expansion joint, bull ring, furnace seals, furnace walls and floor.
18) Verify proper alignment of burner assembly.
19) Inspect furnace for evidence of flame impingement.
20) Test operation of water level gage glass.
21) Perform mechanical and electrical inspection of disassembled low water cutouts (disassembly by VA). After reinstallation, test operation to the extent possible. Test low water cutouts on hot boilers by lowering water level gradually.
22) Verify that steam pressure gage is properly calibrated.
23) Test operation of high steam pressure cutouts on hot boilers by raising steam pressure.
24) Inspect safety valve installations and verify that the valves have proper capacity and set pressure and valves, drains and vents are properly installed. Verify that valve locking seals are not broken.
On boilers that are hot, perform an operation test under pressure to confirm operation at proper set pressures. Operate boiler with burner at high fire to verify adequate steam flow capacity of the safety valves (“accumulation test”).
25) Inspect piping connected to the boilers for evidence of leakage, provision for expansion, provision of adequate support, proper alignment, evidence of detrimental conditions.
26) Inspect piping to the water column, low water cutoffs and alarms, gage glass. Verify that interior of piping is clear of obstructions.
27) Inspect valves on boiler feedwater, blowdown, drain and steam systems.
28) Provide recommendations for non-destructive testing when the inspections indicate that this is necessary to assure continued safety and reliability under current operating conditions.
5. Report Requirements:
1. Provide complete written report fully describing all inspections and tests performed, findings, and recommendations. The condition of all items inspected shall be stated whether acceptable or deficient. All deficiencies shall be fully described along with recommendations for methods of correction. Utilize National Board Forms NB-6 and NB-7, or other similar forms acceptable to owner.
2. Provide sketches and photographs as necessary and as requested by owner to show areas identified as not acceptable for continued service or requiring repair.
3. Include test data and calculations. Show locations and extent of all non-destructive testing by sketches.
4. Furnish report within one week of each facility inspection in “Microsoft Word” of PDF format by email to the
VATR.
5. All safety-related deficiencies shall be immediately reported to the VATR during the inspection visit.
6. Provide recommendations on need for re-inspections after correction of deficiencies. Cost of re-inspections shall be extra cost negotiated with VA Contracting Officer.
II. Boiler Combustion Tuning Services
1. Introduction:
The Central Iowa VA Health Care System (VA CIHCS), 3600 30th Street, Des Moines, Iowa 50310-5753 has a central boiler plant to provide steam for heating, domestic hot water, kitchens and sterilization.
Boiler plant safety, reliability, efficiency and equipment longevity are paramount concerns of VA CIHCS management. Malfunctioning burners or controls can cause catastrophic events resulting in injuries and death and massive property damage. Inaccurate or inadequate data management and monitoring systems can fail to warn of unsafe or inefficient performance. Regular inspections, testing and calibration by expert technicians are an essential part of a program to address these concerns.
This Statement of Work describes the requirement for the inspection, testing and calibration of the boiler plant burners, controls and instruments by qualified technicians.
The pieces of equipment to be serviced are:
Boiler #1: 20159_PA-1000 Boiler #2: 20159_PA-2000 Boiler #3: 20148_PA-3000 Boiler #4: 20148_PA-4000 Boiler #5: 88446
Boiler Tuning Service visits will be coordinated through Supervisor of the boiler plant and performed on each boiler at least two times per year at approximately 6-month intervals.
A separate Statement of Work document covers the inspections of the boilers and boiler plant equipment by Qualified Professional Inspectors.
2. Technician Qualification:
a. Technicians shall have completed at least a one-year trade school and have five years successful experience in testing and calibration of burners, controls and instruments. The experience shall be largely with institutional and industrial boiler plants similar in design to the VA CIHCS plant. The Supervisor of the boiler plant may define and accept equivalent qualifications.
b. Technicians shall demonstrate familiarity with and ready access to the current versions of the following reference:
NFPA 85, Boiler and Combustion Systems Hazards Codes;
NFPA 70E, Standard for Electrical Safety in the Workplace; and VHA Boiler Plant Safety Device Testing Manual, 7th Edition.
c. Technicians shall be equipped with portable electronic flue gas analyzers and other test instruments necessary for the required tests and calibrations. Provide calibrated documentation to the Supervisor of the Boiler Plant verifying all instruments were calibrated within one month of the site visits. At facilities with programmable digital controls, the technicians must be capable of programming the controls and have the appropriate hardware and software for this.
A qualified third-party review means the utilization of a vendor that has documented knowledge and experience in the design and construction of boiler plants and VA’s standards for construction and testing of safety devices, www.vaww.ceosh.med.va.gov/01HE/pages/ST_Boiler.plants.shtml3. In addition, the individual shall have demonstrated experience in conducting equipment assessments and performing testing in compliance with the VA safety device testing manual within the past 3 years.
3. Inspection, Testing and Calibration Requirements:
a. Technicians shall provide all tools and labor necessary to perform inspection, tuning, testing calibrating, and adjustments of burners and boiler plant controls at VA CIHCS. This shall be done every six months with dates scheduled through the Boiler plant supervisor. The VA CIHCS may extend the schedule for burners in limited service.
b. Provide at least two weeks’ notice to the Contracting Officers Technical Representative (VATR) prior to performing the work. Work must be conducted when the VATR or his/her designate is available on site to monitor the work.
c. Work cannot be scheduled during heavy steam load periods. Only one boiler at a time can be out of service.
d. The VA CIHCS will have the boilers that are to be serviced prepared for the technicians upon their scheduled arrival. This includes having the boilers clean of soot and loose scale; oil nozzle cleaned; fully warmed and at normal steam pressure; steam exhaust silencer system operable; all boiler, burner and fuel train pressure gauges and thermometers calibrated (pressure/temperature correction factors provided, if applicable); fuel meters in accurate operation; boiler steam flow, stack temperature and flue gas oxygen instruments operating.
e. The VA CIHCS will comply with any requirements of the test personnel that are considered reasonable by VA CIHCS.
f. The inspections and combustion tuning shall comply with:
1) The recommendations and requirements of VHA Boiler Plant Safety Devices Testing Manual, 7th Edition.
2)The written recommendations of the equipment manufacturers.
3) The requirements and recommendations of the NFPA 85 Boiler and Combustion Systems Hazards Code and NFPA 70E Standard for Electrical Safety in the Workplace, including applicable appendices.
4) Burner performance requirements in this document.
g. A Summary of the work is as follows:
1) Meet with Supervisor of boiler plant to discuss any boiler issues.
2) Review boiler plant log sheets and alarm and trouble reports.
3) Review records that show combustion performance (flue gas oxygen, carbon monoxide and NOx).
4) Perform overall visual inspection of systems. Verify that systems comply with referenced code and VA CIHCS requirements stated in this contract.
5) Test and record the operation and set points of all burner/boiler safety interlock devices. Verify that the set points and operating points are within approximately 20% of normal operating parameters. Make adjustments as necessary and record the new settings. The operation of a device must result in burner shutdown and/or proper alarm operation.
6) Operate burner(s) on each fuel from low fire to high fire and back to low fire in at least six increments and record combustion performance, flue gas oxygen, carbon monoxide, Nox, fuel train pressures, atomizing train pressures, burner pressures, combustion air temperature, flue temperatures and boiler steam output.
7) Compare the combustion performance data with VA CIHCS requirements and previous readings. If necessary, make adjustments to the fuel, combustion air controllers, and FGR controller and damper to obtain the required performance. Record the new performance data.
8) Immediately inform VATR of any recommended repairs or modifications.
9)All interlocks and safety devices to be inspected and tested on each boiler/burner/equipment, are contained in the VHA Boiler Plant Safety Devices Testing Manual, 4th Edition, along with testing procedures.
h. Required burner performance (natural gas and #2 fuel oil):
1) Achieve, but do not exceed, boiler maximum steam flow output rating. Measure fuel input at minimum and maximum firing rates.
2) Maximum carbon monoxide: <50 ppm (natural gas), <80 ppm (#2 fuel oil).
3) Maximum Nox: <30 ppm (natural gas), <90 ppm (#2 fuel oil).
4) Flue gas oxygen: 2.5 – 4.2% (up to 5.2% at load below 40% of maximum steam output; no upper limit at minimum firing rate; oxygen can be one percentage point higher on oil firing on single-point positioning systems). Flue gas oxygen (low excess air burners): 1.0 – 2.0% (up to 2.5% at loads below 40% of maximum steam output; no upper limit at minimum firing rate;
oxygen can be one percentage point higher on oil firing on single point positioning systems).
5) Smoke on Natural Gas and #2 Fuel Oil shall not be visible. Comply with local emissions regulations.
6) Note: Copies of the applicable emissions regulations must be available in the boiler plant office.
7) Flames shall be stable with no pulsations, shall be retained near burner, no blow off or flashbacks, no constant flame impingement on refractory or water walls.
i. List of instrumentation and controls to be inspected and calibrated:
1) Steam flow transmitters (all).
2) Steam flow/computer readout.
3) Flue gas oxygen sampling, analyzing and recorder/computer readout.
4) Boiler and economizer stack temperature transmitters and recorder/computer readout.
5) Master Steam pressure and combustion controllers.
6) Boiler outlet draft controllers.
7) Boiler water level controllers.
8) Feedwater deaerator and condensate storage tank water level controllers including overflow.
9) All pressure and temperature sensors and transmitters.
10) All signal processing and readout devices.
4. Invoicing:
Invoices will be submitted after the completion of each semi-annual service. Invoices will not be considered complete until the Supervisor of the boiler plant receives complete written reports to include burner performance, O2 Levels efficiencies, etc.
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
1.00 SV __________________ __________________
BOILER INSPECTION AND CALIBRATION AND SAFETY DEVICE TESTING
SERVICES FOR THE CENTRAL IOWA VA HEALTH CARE SYSTEM IN DES
MOINES, IOWA
Contract Period: Base POP Begin: 04-01-2024
POP End: 03-31-2025 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning Contractors PRODUCT/SERVICE CODE: 4410 - Industrial Boilers
SERVICES FOR THE CENTRAL IOWA VA HEALTH CARE SYSTEM IN DES
MOINES, IOWA
Contract Period: Option 1 POP Begin: 04-01-2025 POP End: 03-31-2026 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning
SERVICES FOR THE CENTRAL IOWA VA HEALTH CARE SYSTEM IN DES
MOINES, IOWA
Contract Period: Option 2 POP Begin: 04-01-2026 POP End: 03-31-2027 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning
SERVICES FOR THE CENTRAL IOWA VA HEALTH CARE SYSTEM IN DES
MOINES, IOWA
Contract Period: Option 3 POP Begin: 04-01-2027 POP End: 03-31-2028 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning
SERVICES FOR THE CENTRAL IOWA VA HEALTH CARE SYSTEM IN DES
MOINES, IOWA
Contract Period: Option 4 POP Begin: 04-01-2028 POP End: 03-31-2029 PRINCIPAL NAICS CODE: 238220 - Plumbing, Heating, and Air-Conditioning
GRAND TOTAL __________________
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered;
and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212- 5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause)
ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES
Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
(End of Addendum to 52.212-4)
C.2 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO
IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204–23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) (Section 1634 of Pub. L.
115–91).
(3) 52.204–25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115–232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015).
(5) 52.232–40, Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).
(6) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(7) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
[] (1) 52.203–6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).
[] (2) 52.203–13, Contractor Code of Business Ethics and Conduct (NOV 2021) (41 U.S.C.
3509).
[X] (3) 52.203–15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
[] (4) 52.203–17, Contractor Employee Whistleblower Rights (NOV 2023) (41 U.S.C. 4712);
this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).
[X] (5) 52.204–10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109–282) (31 U.S.C. 6101 note).
[] (6) [Reserved]
[] (7) 52.204–14, Service Contract Reporting Requirements (OCT 2016) (Pub. L. 111–117, section 743 of Div. C).
[] (8) 52.204–15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (OCT 2016) (Pub. L. 111–117, section 743 of Div. C).
[X] (9) 52.204–27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub. L. 117–328).
[X] (10) 52.209–6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) (31 U.S.C. 6101 note).
[] (11) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters
(OCT 2018) (41 U.S.C. 2313).
[] (12) [Reserved]
[] (13) 52.219–3, Notice of HUBZone Set-Aside or Sole-Source Award (OCT 2022) (15 U.S.C. 657a).
[] (14) 52.219–4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
[] (15) [Reserved]
[] (16)(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
[] (ii) Alternate I (MAR 2020) of 52.219-6.
[] (17)(i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
[] (ii) Alternate I (MAR 2020) of 52.219-7.
[] (18) 52.219-8, Utilization of Small Business Concerns (SEP 2023) (15 U.S.C. 637(d)(2) and (3)).
[] (19)(i) 52.219–9, Small Business Subcontracting Plan (SEP 2023) (15 U.S.C. 637(d)(4)).
[] (ii) Alternate I (NOV 2016) of 52.219-9.
[] (iii) Alternate II (NOV 2016) of 52.219-9.
[] (iv) Alternate III (JUN 2020) of 52.219–9.
[] (v) Alternate IV (SEP 2023) of 52.219–9.
[X] (20)(i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).
[] (ii) Alternate I (MAR 2020) of 52.219-13.
[X] (21) 52.219–14, Limitations on Subcontracting (OCT 2022) (15 U.S.C. 657s).
[] (22) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C.
637(d)(4)(F)(i)).
[] (23) 52.219–27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (OCT 2022) (15 U.S.C. 657f).
[X] (24) (i) 52.219–28, Post-Award Small Business Program Rerepresentation (SEP 2023) (15 U.S.C. 632(a)(2)).
[] (ii) Alternate I (MAR 2020) of 52.219–28.
[] (25) 52.219–29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (OCT 2022) (15 U.S.C. 637(m)).
[] (26) 52.219–30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (OCT 2022) (15 U.S.C. 637(m)).
[] (27) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).
[] (28) l(26) 52.219–33, Nonmanufacturer Rule (SEP 2021) (15 U.S.C. 657s).
[X] (29) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
[] (30) 52.222–19, Child Labor—Cooperation with Authorities and Remedies (DEC 2022) (E.O. 13126).
[X] (31) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
[X] (32)(i) 52.222–26, Equal Opportunity (SEP 2016) (E.O. 11246).
[] (ii) Alternate I (FEB 1999) of 52.222-26.
[X] (33)(i) 52.222–35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).
[] (ii) Alternate I (JUL 2014) of 52.222-35.
[X] (34)(i) 52.222–36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C.
793).
[] (ii) Alternate I (JUL 2014) of 52.222-36.
[X] (35) 52.222–37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).
[] (36) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act
(DEC 2010) (E.O. 13496).
[X] (37)(i) 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627).
[] (ii) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
[X] (38) 52.222-54, Employment Eligibility Verification (MAY 2022). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
[] (39)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA- Designated Items (MAY 2008) (42 U.S.C.6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
[] (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
[] (40) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693).
[] (41) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (JUN 2016) (E.O. 13693).
[] (42)(i) 52.223-13, Acquisition of EPEAT®-Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).
[] (ii) Alternate I (OCT 2015) of 52.223-13.
[] (43)(i) 52.223-14, Acquisition of EPEAT®-Registered Televisions (JUN 2014) (E.O.s 13423 and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .