36C26319Q0704-003.pdf
PDF 151 KB Posted
- Attached to
- Patient-Lifts Federal contract opportunity
- Solicitation number
- 36C26319Q0704
About this file
36C26319Q0704 ATTACHMENT B -Installation-Relocation_Ceiling-Mounted-Lifts-Checklist.pdf
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26319Q0704-A00001000.docx | DOCX document | |
| 36C26319Q0704-005.pdf | ||
| 36C26319Q0704-004.pdf | ||
| 36C26319Q0704-000.docx | DOCX document | |
| 36C26319Q0704-002.pdf | ||
| 36C26319Q0704-001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revision 2.1 1 of 4 Serial #: ____________________
Verify NFPA 99 and NFPA 70 compliance for access to electrical and safety systems.
Verify required access to mechanical, HVAC, and fire systems components within the lift installation area.
Verifiy minimum clearances for operation are compliant with manufacturer recommendations. (Ensure room clearance and that the ceiling height is adequate for lift usage.)
Facility: Manufacturer:
Model:
COMPLETE
Mfgr Contact:VAMC Contact's Phone Number:
Installer:
Serial Number: EE Number:
Work Order:
Installation or Relocation Checklist for Ceiling Mounted Patient Lifts The commissioning for a patient ceiling lift system(s) shall include, but not be limited to, the following points as components of the commissioning procedures.
NOTE: Ceiling mounted patient lifts are not to be installed in treatment units with actively suicidal patients.
Lift Location:
VAMC Contact:
Pre-Installation COMPLETE
Obtain structural and related engineering design drawings and calculations for the new lift installation.
Design drawings shall be developed for specific lift installation under specific pre-existing conditions of the facility.
Mfgr Contact's Phone Number:
Date:Installer's Phone Number:
Verify NFPA 99 and NFPA 70 compliance for proper grounding and bonding.
Verify that the lift is listed by the manufacturer to be installed and operated in the environment that the lift is operating under. (For example, water tight lifts shall be installed and operated in wet, damp or humid locations such as pools or bathrooms.)
Verify NFPA 13 compliance for fire sprinkler system (including but not limited to fire sprinkler heads and piping).
If the facility is located in a seismic area, as identified in VA Handbook H-18-8 Seismic Design Requirements, verify that the ceiling mounted patient lift system installation is in compliance with the requirements of VA Directive 7512 Seismic Safety of VA Buildings and VA Master Design Specification
13.05.041 Seismic Restraint Requirements for Non-Structural Components.
Perform site survey of the pre-existing conditions and as-built drawings above and below finish ceiling at the installation location to confirm existing structural and ceiling conditions.
Perform pre-installation walkthrough to confirm full understanding and consensus of design drawing(s) and installation conditions.
Verify proper connections of the lift's structural system to the building’s structure (including seismic bracing if applicable).
Verify proper interface at the ceiling (hard deck or soft tile) and proper installation of all protective features around the support rods and rails/tracks.
NOTES:
Installation
Revision 2.1 2 of 4 Serial #: ____________________
PASS FAIL
PASS FAIL
COMPLETE
Rails/Tracks and End Stops
NOTES:
Lift Unit and Straps
Inspection of lift unit casing for cracks and alignment.
Inspection and activation of hand control for full operation (e.g., up, down, left, right) and “return to charge” function if applicable.
Confirm any and all lift unit indicator lights are functioning. (e.g., red service warning light, charging state light) Inspection and verification of all emergency functions of the lift unit.
Verification that all fasteners and set screws are properly tightened on the trollies and rails/tracks.
Ensure that the rail/track is free of gaps (unless required by design). If included in installation, verify rail turntable function, exchanger function, gate alignment, and safety block installation.
Confirm track is clean and clear of all debris. (Use manufacturer’s recommended cleaning materials to avoid damage to the motor case and other components.)
Verify proper installation of electric motor per manufacturer's instructions to ensure operational rigidity of motor mounting.
Verify proper electrical connections per design drawings and manufacturer's instructions.
Verification that the lift unit charges properly.
Perform operational test to verify lift functionality.
NOTES:
Perform walkthrough to ensure compliance of the installation per the design drawing(s) and manufacturer's instructions.
Post-Installation
NOTES:
Verify structural component sizing and physical installation to ensure that the correct structural system is in place and properly installed to support the lift.
Verification that all manufacturer specified end stops or docking gates are properly installed.
Revision 2.1 3 of 4 Serial #: ____________________
PASS FAIL
2 Verify that training and competency are documented prior to release for use with patients.
Verify that manufacturer or manufacturer’s representative has provided training on the use of patient handling equipment to clinicians and other staff who move and handle patients.
COMPLETE
COMPLETE
Full extension and inspection of lift strap for loose threads or frays.
Verification of any “soft start” or “soft stop” features and that lifting speed does not exceed 2.5 inches per second with “zero” load.
Verification of load testing and deflection testing at the manufacturer's specified maximum rated lift capacity.
Verification of any “soft start” and “soft stop” features and that lifting speed does not exceed 1.5 inches per second under maximum rated lift capacity.
Verification of function of emergency stop at maximum rated lift capacity.
Verification of emergency lowering feature at maximum rated lift capacity.
NOTES:
NOTES:
Training
NOTES:
Inspection of spreader bar and clips for cracks and for loose or missing rings or cotter pins.
Confirm that the manufacturer's operating and maintenance manuals for this lift have been received.
Load Testing
NOTES:
Manuals
Revision 2.1 4 of 4 Serial #: ____________________
DATE:
DATE:
DATE:
SIGNATURE:
Installing Contractor
ADDITIONAL NOTES:
Manager of the Service Using the Ceiling Mounted Lifts COMPLETE After the activities listed in the above checklist and in the manufacturer's installation/operations/owner’s manual(s) have been completed, the manager of the service using the ceiling mounted lifts confirms that the current staff have received initial training on ceiling mounted lifts and that there is a process in place to provide ongoing training on the proper use of ceiling mounted lifts.
After the activities listed in the above checklist and in the manufacturer's installation/operations/owner’s manual(s) have been completed, the installing contractor shall release the ceiling mounted lift installation to VA representative.
SIGNATURE:
TITLE:
VA Representative After the activities listed in the above checklist and in the manufacturer's installation/operations/owner’s manual(s) have been completed, the VA representative shall review those items with the installing contractor prior to releasing the ceiling mounted lift into service to ensure completion of all requirements.
COMPLETE
SIGNATURE:
TITLE:
TITLE:
COMPLETE
Install and Relocation
| Facility: |
| Work Order: |
| Manufacturer: |
| Lift Location: |
| Model: |
| VAMC Contact: |
| Serial Number: |
| EE Number: |
| VAMC Contacts Phone Number: |
| Mfgr Contact: |
| Installer: |
| Mfgr Contacts Phone Number: |
| Installers Phone Number: |
| Date: |
| NOTES: |
| Serial: |
| NOTES_2: |
| NOTES_3: |
| NOTES_4: |
| Serial_2: |
| NOTES_5: |
| NOTES_6: |
| NOTES_7: |
| NOTES_8: |
| Serial_3: |
| DATE: |
| TITLE: |
| DATE_2: |
| TITLE_2: |
| DATE_3: |
| TITLE_3: |
| ADDITIONAL NOTES: |
| Serial_4: |
| Check Box1: Off |
| Check Box2: Off |
| Check Box3: Off |
| Check Box4: Off |
| Check Box5: Off |
| Check Box6: Off |
| Check Box7: Off |
| Check Box8: Off |
| Check Box9: Off |
| Check Box10: Off |
| Check Box11: Off |
| Check Box12: Off |
| Check Box13: Off |
| Check Box14: Off |
| Check Box15: Off |
| Check Box16: Off |
| Check Box17: Off |
| Check Box18: Off |
| Check Box19: Off |
| Check Box20: Off |
| Check Box21: Off |
| Check Box22: Off |
| Check Box23: Off |
| Check Box24: Off |
| Check Box25: Off |
| Check Box26: Off |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Check Box31: Off |
| Check Box32: Off |
| Check Box33: Off |
| Check Box34: Off |
| Check Box35: Off |
| Check Box36: Off |
| Check Box37: Off |
| Check Box38: Off |
| Check Box39: Off |
| Check Box40: Off |
| Check Box41: Off |
| Check Box42: Off |
| Check Box43: Off |
| Check Box44: Off |
| Check Box45: Off |
| Check Box46: Off |
| Check Box47: Off |
| Check Box48: Off |
| Check Box49: Off |
| Check Box50: Off |
| Check Box51: Off |
| Check Box52: Off |
| Check Box53: Off |
| Check Box54: Off |
| Check Box55: Off |
File details come from the government source that posted it.