This document is an Amendment of Solicitation/Modification of Contract issued by the Department of Veterans Affairs Network Contracting Office 22. The amendment changes the NAICS code from 333924 to 532490 and addresses multiple vendor inquiries regarding a mobile medical imaging system. Key details include:
The solicitation requires a new mobile medical imaging trailer with a GE Voyager system, to be installed and operational by March 15, 2026. Vendors must be OEM authorized distributors with an authorization letter. The system will perform various cardiac exams, including imaging of the heart, and requires a breast coil and breast software. Critical specifications include a 98% uptime guarantee, a 2-hour response time (despite the OEM's 4-hour service contract), and no interim solutions will be accepted. Accessories like pulse oximeter, power injector, and IV contrast warmer are not currently specified, and only imaging (not biopsy) capabilities are required.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQ 36C26226Q0037.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE 7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO. 1. CONTRACT ID CODE
FACILITY CODE CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30 PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243
(Type or print) (Type or print)
(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code)
(If other than Item 6)
(Specify type of modification and authority)
(such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
1 3
664-26-2-405-0009
N/A
36C262
Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815
Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815
To all Offerors/Bidders
36C26226Q0037
X
X X
X 1
The purpose of amendment 36C26226Q0037 P00001 is to change NAICS code from 333924 to 532490 and answer the following inquiries:
Q1: Request the agency remove the requirement that a new item be provided, along with the requirement that the provider be an authorized reseller or dealer with an authorized letter from the OEM.
A1: New item shall be provided. The vendor must be an OEM authorized distributor for the proposed equipment/system, verified by an authorization letter or other documents from the OEM. No grey market items.
Q2: Uptime for any equipment is determined by the OEM, not the owner or lessor. The requested system, a GE Voyager, carries 98% i a 98% uptime guarantee. Will the requirement remain at 100% uptime, or will it be adjusted to reflect the OEM’s guarantee?
A2: 98% is acceptable.
Anthony Dela Cruz Contracting Officer
VA-VHA-RPOW-2024-0101
CONTINUATION PAGE
Q3: Are there any required specifications for the following accessories (Pulse oximeter, Power injector, IV contrast warmer)?
A3: No required specifications as currently not using them.
Q4: PWS specifies a 2-hour response time, while the OEM’s service contract guarantees a 4-hour response time. Per VAAR gray market regulations, we must use the OEM for all service and parts. Will the 2-hour response requirement remain, or can it be adjusted to align with the OEM’s 4-hour response policy?
A4: Historically, we have had imaging trailers that have been able to provide a response time in less than 2 hours. We would like to maintain this expectation. This will allow for issues to be resolved faster with less negative impact on our Veteran’s health care.
Q5: We recently built and delivered a 12x60 transportable for Little Rock VAMC. That project, from award to installation, took approximately 11 months, largely due to some unique variabilities with the project. However, trailer manufacturing typically requires 6–8 months. After completion, the contracting officer did a mod to move the pop date from the time of award to actual performance 11 months later. Is a similar award-to-installation timeline acceptable for this project?
A5: Installed and operational by March 15, 2026.
Q6: If not, would a traditional 8x48 unit be acceptable as an interim solution while the new system is being built?
A6: No
Q7: What specific cardiac exams will be performed on the mobile system?
A7: Various exams from routine cardiac including but not limited to the left chamber of the heart to specialized sequences involving the entire heart.
Q8: In the PWS, the requirement list includes breast software but not the breast coil itself. Can you confirm whether a breast coil is needed?
A8: Yes
Q9: If so, will you require imaging only, or biopsy capability as well?
A9: Imaging only
Q10: If not, is the software still required?
A10: Biopsy software not required
| 2025-11-03T11:04:16-0800 | |