36C26222Q1474 0001.docx

DOCX document 96 KB Posted

Attached to
J045--Toilet & Urinal Flushometer Refurbishments Federal contract opportunity
Solicitation number
36C26222Q1474_1
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22

View the file

Other files for this federal contract opportunity

Other files attached to J045--Toilet & Urinal Flushometer Refurbishments, newest first.
File Type Posted
RFQ Photos.zip ZIP file
36C26222Q1474_1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

36C262

Department of Veterans Affairs Network Contracting Office (NCO) 22 3601 S. 6th Avenue Tucson AZ 85723

36C262

Department of Veterans Affairs Network Contracting Office (NCO) 22 3601 S. 6th Avenue Tucson AZ 85723 To all Offerors/Bidders

36C26222Q1474 09-26-2022

X

The purpose of this amendment is to answer questions submitted by potential offerors.

All other conditions and terms remain the same. All interested Offerors must submit information by email to aurora.salazar-alas@va.gov.

ANITA AMODIA

Contracting Officer

RFQ# 36C26222Q1474_1 – Toilet & Urinal Flushometer Refurbishments Answers To Contractor Submitted Questions

Q1. Please confirm bids are due at 1pm EDT on 9/28 and NOT 1pm PST.

Answer: Yes, quotes are due at 1 PM EDT on 9/28/2022.

Q2. Will the NTP provide 10 days’ notice before commencement of work?

Answer: No.

Q3. Will the VA consider extending the period of performance? With 4 weeks (20 working days) to complete just the 500 “rebuild and install 500 water closet flushometers” would require completing 25 per day. Considering getting to each location, finding shut-off valves, performing work and turning water back on, the four (4) week schedule is unreasonable.

Answer: Four (4) weeks is required. Offerors are urged to consider efficiency or staffing to meet the timeline.

Q4. Please clarify scope of work for B.2 Price/Cost Schedule Item Number 0002. Will VA consider providing an allowance for this line item? Without having quantities or known repairs how is contractor to price this Item?

Answer: The contractor will not price this line item at time of solicitation. The line item will be priced when/if it is identified that a toilet/urinal has a component not damaged but in need of repair. The contractor will notify the Government and provide a quote. The quote will be evaluated by the Contracting Officer (CO). The CO must approve all repairs/purchases of parts.

Q5. Please clarify scope of work for B.2 Price/Cost Schedule Item Number 0004. Will VA consider providing an allowance for this line item? Without having quantities or known repairs how is contractor to price this Item?

Answer: The contractor will not price this line item at time of solicitation. The line item will be priced when/if it is identified that a urinal has a component not damaged but in need of repair. The contractor will notify the Government and provide a quote. The quote will be evaluated by the Contracting Officer (CO). The CO must approve all repairs/purchases of parts.

Q6. If added repairs are necessary for Price/Cost Schedule Item Numbers 0002 and 0004, will time to complete work be extended as well?

Answer: Depending on the situation, time may be extended. Offerors are urged to not rely on time extensions.

Q7. Is contractor fully responsible to find and shut off the existing isolation valves - locate the affected rooms? This will also add time for investigation and coordination with the Facility.

Answer: Majority of shut-off valves are on toilet system.

Q8. The waterless urinals - each of these should have a water line (being referred to as “dead leg" in the solicitation) capped off at the wall. Please note that the existing water stub might need to be relocated for a new urinal type. This will require setting up containment (Bldg. 1), open wall, perform repair, new drywall, mud & tape, retile wall (may not be able to match existing tile).

Answer: Caps are exterior to wall. Price to install without having to relocate and utilize urinal even if more expensive to avoid having to relocate.

Q9. New Urinals - depending on the new urinal type, the location of in-wall backing may need to be relocated. This will require setting up containment (Bldg. 1), open wall, perform repair, new drywall, mud & tape, retile wall (may not be able to match existing tile).

Answer: Price to use Zurn.

Q10. New Urinals - Each urinal requires a clean-out. How many urinals do not have a clean-out and will need a clean-out added?

Answer: Price as all have clean-outs.

Q11. Statement of Work Section D-1.5(b)-(c) Please clarify the term rebuild kit. Specifically, does this include the rebuild kit for angle valve wall stop? This rebuild kit requires the water to be shut off at the interstitial.

Answer: Price as exclusion angle valve wall stop.

Q12. Statement of Work Section D-1.5(e)-(f) please clarify the phrase “not damaged by work, but in need of repair.” Specifically, what damages are being referred to here?

Answer: For example, wall stop does not hold. The price interstitial valve is shut off and needs repair.

Q13. How many toilets/urinals can be taken out of service at one time? If walls are opened with a containment set up and wall/tile repairs a fixture may be out for up to 5 days.

Answer: Price with no walls opened up.

Q14. Do the urinal changes include the flush meter?

Answer: Yes.