36C26219R0119-000.docx
DOCX document 129 KB Posted
- Attached to
- Research - Scoping Review of EBQI - 691C90410 Federal contract opportunity
- Solicitation number
- 36C26219R0119
About this file
36C26219R0119 36C26219R0119_1.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26219C0125-000.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26219R0119 FedBizOpps Combined Synopsis/Solicitation Notice
CLASSIFICATION CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
RESPONSE DATE (MM-DD-YYYY)
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
SET-ASIDE
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
ADDRESS
POSTAL CODE
COUNTRY
ADDITIONAL INFORMATION
GENERAL INFORMATION
PLACE OF PERFORMANCE
* = Required Field FedBizOpps Combined Synopsis/Solicitation Notice Rev. March 2010 A Research - Scoping Review of EBQI 90815 36C26219R0119 06-25-2019 N 611310 Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815 Corey R. Kline Contracting Officer
USA
www.va.gov VA's Homepage Corey.Kline@va.gov Work Email Scoping Review of EBQI for VA GLA
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
DUNS:
DUNS+4:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. 2/2012)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
691-19-3-611-0022 36C26219R0119 06-18-2019 Kline, Corey R.
562-766-2270 06-25-2019
10:00 AM
36C262 Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815 X 611310 $27.5 Million X N/A X 36C691 Department of Veterans Affairs VA Greater Los Angeles HCS 11301 Wilshire Blvd.
Los Angeles CA 90073 36C262 Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815
Department of Veterans Affairs Financial Services Center P.O. Box 149971 Austin TX 78714-9971 (Refer to subsequent pages) Contractor shall provide Research: Scoping Review of Evidence-Based Quality Improvement (EBQI) at VA GLA.
VA POC: Deborah Develan, Phone: 818-891-7711 Ext. 36101 Email: Deborah.Develan@va.gov VA Contracting POC: Corey R. Kline Phone: 562-766-2270 Email: Corey.Kline@va.gov
691-3680160-611-821500-2560 SP3FDP1A1
X X Corey R. Kline Contracting Officer Table of Contents
| SECTION A | 3 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS | 3 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 5 |
| B.1 CONTRACT ADMINISTRATION DATA | 5 |
| B.3 PRICE/COST SCHEDULE | 12 |
| ITEM INFORMATION | 12 |
| B.4 DELIVERY SCHEDULE | 13 |
| SECTION C - CONTRACT CLAUSES | 14 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (OCT 2018) | 14 |
| C.2 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999) | 19 |
| C.3 52.227-14 RIGHTS IN DATA—GENERAL (MAY 2014) | 19 |
| C.4 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 24 |
| C.5 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (DEC 2009) | 24 |
| C.6 VAAR 852.219-75 SUBCONTRACTING COMMITMENTS MONITORING AND COMPLIANCE (JUL 2018) | 24 |
| C.7 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 25 |
| C.8 VAAR 852.237-70 CONTRACTOR RESPONSIBILITIES (APR 1984) | 26 |
| C.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 26 |
| C.10 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS (MAY 2019) | 27 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 35 |
| D.1 SEE ATTACHED DOCUMENT: P07 - WAGE DETERMINATION. | 35 |
| SECTION E - SOLICITATION PROVISIONS | 36 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (OCT 2018) | 36 |
| E.2 ADDENDUM TO FAR 52.212-1 INSTRUCTIONS TO OFFERORS – COMMERCIAL ITEMS (OCT 2018) | 40 |
| E.3 52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018) | 41 |
| E.4 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016) | 42 |
| E.5 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (JUL 2016)(DEVIATION) | 43 |
| E.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 44 |
| E.7 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014) | 44 |
| E.8 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL ITEMS (OCT 2018) | 45 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C262 Kline, Corey R.
Department of Veterans Affairs Network Contracting Office 22 4811 Airport Plaza Drive Suite 600 Long Beach CA 90815
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [Upon Completion of Each Deliverable] |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
Department of Veterans Affairs Financial Services Center P.O. Box 149971
Austin TX 78714-9971 ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
B.2 STATEMENT OF WORK
1. INTRODUCTION:
The Contractor shall provide a Scoping Review of Evidence-Based Quality Improvement (EBQI) as an Implementation Strategy for Evidence-Based Practices (EBPs) for the VA Los Angeles HSR&D Center, located at the Department of Veterans Affairs, VA Greater Los Angeles Healthcare System. 11301 Wilshire Blvd. Los Angeles, CA. 90073. The scoping review will be used by CSHIIP researchers as background information for developing a self-assessment tool for assessing fidelity to the EBQI implementation strategy.
The Contractor shall furnish all labor, materials, travel, lodging and any other supplies or equipment necessary to perform the requirements as outlined in this Statement of Work (SOW).
2. PERIOD/PLACE OF PERFORMANCE:
The period of performance for the contract shall be from July 1, 2019 through June 30, 2020. This is a Firm Fixed Price Contract. The contract period shall be for one (1) base year.
The required scoping review service shall be performed at the Contractors Worksite.
3. SCOPE OF WORK:
The Contractor shall provide a scoping review to identify the components of the Evidence-Based Quality Improvement implementation strategy that have been used to implement evidence-based practices, available methods or instruments to assess fidelity (e.g., the extent to which the implementation strategy is used as intended) to the EBQI implementation strategy, and any evidence showing its effectiveness for promoting uptake of evidence-based practices. The scoping review will focus on identifying a variety of different implementation approaches, it will differentiate the components of the implementation strategies, and determine effectiveness signals for these strategies.
The scoping review shall be conducted according to established methodology (develop a protocol, define the scope of the review and formulate review questions, design an effective search strategy, develop transparent criteria for examples eligible for inclusion in the review, document identified examples in an evidence table, and summarize key subject-specific components) and the synthesis will be thorough and transparent. Upon finalizing, the protocol will be registered in the Open Science Network.
4. CONTRACTOR REQUIREMENTS:
The contractor shall develop a scoping review which includes the following:
a. Establish outline of detailed scoping review protocol.
b. Identifying a variety of implementation approaches.
c. Differentiate the components of the implementation strategies.
d. Determine effectiveness signals for these strategies.
e. Document results in comprehensive tables and figures.
f. Document study details for all included studies with an evidence table.
g. Establish a framework for components used in identified EBQI approaches with a components table.
h. Use meta-regression and subgroup analysis to identify components
i. Establish bibliography and link to the PubMed entry
j. Establish Journal Manuscript
5. TASKS & DELIVERABLES
The contractor shall complete the following tasks:
a. Define the scope of the review and formulate review questions.
b. Design a search strategy suitable to identify literature focused on EBQI.
c. Develop transparent criteria for examples eligible for inclusion in the review.
d. Document the identified examples in an evidence table
e. Summarize the identified EBQI implementation strategy components, fidelity measures/instruments, and evidence of effectiveness.
The contractor shall provide the following deliverables:
a. Scoping review protocol detailing search terms, search strategy, inclusion and exclusion criteria.
b. Documentation of methods, evidence table and synthesis showing results of scoping review on EBQI, and bibliography.
c. Manuscript ready for submission to a peer-reviewed scientific journal.
| Due Date |
| Deliverable |
| 2 months after contract award |
| Scoping review protocol |
| 9 months after contract award |
| Methods, evidence table, synthesis, bibliography |
| 12 months after contract award |
| Journal manuscript |
6. CONTRACTOR QUALIFICATIONS & OTHER RESPONSIBLITES
a. Contractor shall have experience and expertise in the Modified Delphi Method for conducting expert panels.
b. Contractor shall have experience in systematic evidence review methods, as exemplified by past completion of systematic reviews.
c. Contractor shall have familiarity with toolkit development procedures, as exemplified by past work relating to toolkits.
d. Contractor shall be responsible for any injury to himself/herself, his/her employees, or others, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by him/her or his/her employees’ fault or negligence. Contractor shall maintain personal liability and property damage insurance prescribed by the laws of the Federal Government.
The Government reserves the right to accept or reject Contractor’s employee for the rendering of services. Complaints concerning Contract Personnel’s performance or conduct will be dealt with by the Contractor and COR with the final decision being made by the Contracting Officer.
7. ACCEPTANCE
a. Any problems encountered during the acceptance phase will result in a reset of the acceptance phase, resulting in a new 3-week acceptance period.
b. Upon completion of the mandatory tasks and receipt of deliverables, the VAGLAHS shall monitor, monthly, and verify the completion of service by June 30, 2020.
8. QUALITY ASSURANCE PLAN (QAP)
The Contractor and the VAGLAHS shall jointly cooperate in the development and implementation of a Quality Assurance Plan (QAP). The QAP shall document the process that will verify and validate quality assurance in compliance with the requirements and ensure these requirements meet the VAGLAHS’s expectations.
The contractor shall develop a Quality Assurance Plan (QAP) based on accepted industry standards such as the CMMI SM, ISO 9000, IEEE 12207, or other accepted industry QA standards. The QAP shall detail the processes, procedures, and metrics for assuring quality. The QAP shall also include, at a minimum, a description of the following key activities:
a. Establishment of capable processes.
b. Development and implementation of procedures to identify, prevent, and ensure non-recurrence of defective services.
c. Establishment of mechanisms for feedback of performance.
d. Monitoring and control of critical processes.
e. Establishment of a designated point of contract (POC) to serve as the POC for quality control issues/complaints.
f. Establishment of reliable methods of record keeping and documentation of all corrective actions and process improvements undertaken during the acceptance period.
9. SAFETY REQUIREMENTS:
a. Contractor shall operate under, but not limited, to the following national codes, telecommunications industry standards and practices: National Electric Code (NEC), Building Industry Consulting Service International (BICSI), all standards, Electronic Industries Association/Telecommunications Industry Association EIA/TIA, Americans with Disabilities Act (ADA), National Fire Protection Association (NFPA), Underwriters Laboratories (UL), ITU and IETF and all applicable audio, video, communication, data and control standards.
b. Contractor shall provide all necessary tools, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely.
10. CHANGES TO STATEMENT OF WORK:
Only the Contracting Officer, acting within the scope of the contract has the authority to make changes which affect the contract in terms of quality, quantity, price or delivery.
In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change shall be considered to have been made without authority and no adjustment shall be made in the contract price to cover any increase in costs incurred as a result thereof.
11. CONTRACTOR’S KEY PERSONNEL
The Contractor shall be responsible for the assignment, managing and overseeing the activities of all Contractor personnel. The Contractor's management responsibilities shall include all activities necessary to ensure the accomplishment of timely and effective support, performed in accordance with the requirements contained in the statement of work.
The Contracting Officer may notify the Contractor and request immediate removal of any personnel assigned to the order by the Contractor that are deemed to have a conflict of interest with the government or if the performance is deemed to be unsatisfactory. The reason for removal will be documented and replacement personnel shall be identified within three business days of the notification. Employment and staffing difficulties shall not be justification for failure to meet established schedules.
12. SECURITY BACKGROUND CHECKS
All Contractor employees who require access to the Department of Veterans Affairs' computer systems shall be the subject of a background investigation and must receive a favorable adjudication from the VA Security and Investigations Center (07C).
The level of background security investigation will be in accordance with VA Directive 0710 dated September 10, 2004 and is available at: http://www.va.gov/pubs/asp/edsdirec.asp (VA Handbook 0710, Appendix A, Tables 1 - 3). Appropriate Background Investigation (BI) forms will be provided upon contract (or task order) award and are to be completed and returned to the VA Security and Investigations Center (07C) within 30 days for processing. Contractors will be notified by 07C when the BI has been completed and adjudicated. These requirements are applicable to all Subcontractor personnel requiring the same access.
If the security clearance investigation is not completed prior to the start date of the contract, the employee may work on the contract while the security clearance is being processed, but the Contractor will be responsible for the actions of those individuals they provide to perform work for the VA. In the event that damage arises from work performed by Contractor personnel, under the auspices of the contract, the Contractor will be responsible for resources necessary to remedy the incident.
13. CONTRACTOR SECURITY REQUIREMENTS
The Office of Security and Law Enforcement provides Department-wide policy on the assignment of appropriate position sensitivity designations associated with Department of Veterans Affairs (VA) positions involving national security and public trust responsibilities, and on the level of background investigations required for applicants for, and incumbents of, those positions.
The cost for such investigations shall be borne by the Contractor, either in advance or as reimbursement to the Government. The level of sensitivity shall be determined by the Government on the basis of the type of access required. The level of sensitivity will determine the depth of the investigation and the cost thereof. At this time, the current estimated costs for such investigations are as follows:
| LEVEL OF SENSITIVITY |
| BACKGROUND INVESTIGATION LEVEL |
| APPROXIMATE COST |
| Low Risk |
| National Agency Check with Written Inquiries |
| $ |
| 381.00 |
| Moderate Risk |
| Minimum Background Investigation |
| $ |
| 1,730.00 |
| High Risk |
| Background Investigation |
| $ |
| 4,431.00 |
The Contractor shall be required to furnish all applicable employee information required to conduct the investigation, such as, but not limited to, the name, address, and social security number of the Contractor’s personnel. The VA will provide all the necessary instructions and guidance for submission of the documents required to conduct the background investigation. Background investigations shall not be required for contract personnel assigned to Low Risk/Non-sensitive positions for 180 days or less under a single contract or series of contracts. However, a Security Access Clearance (SAC) background screening will be required for appropriate preliminary checks IAW VA Directive 0710.
The investigative history for contractor personnel working under this contract must be maintained in the databases of either the Office of Personnel Management (OPM) or the Defense Industrial Security Clearance Organization (DISCO). Should the contractor use a vendor other than OPM or Defense Security Service (DSS) to conduct investigations, the investigative company must be certified by OPM/DSS to conduct contractor investigations.
14. INFORMATION SECURITY
a. The contractor shall ensure adequate LAN/Internet, data, information, and system security in accordance with VA standard operating procedures and standard contract language, conditions laws, and regulations. The contractor’s firewall and web server shall meet or exceed the governments minimum requirements for security. All government data shall be protected behind an approved firewall. Any security violations or attempted violations shall be reported to the VA Project Manager and the VBA Headquarters Information Security Officer as soon as possible. The vendor shall follow all applicable VA policies and procedures governing information security, especially those that pertain to certification accreditation.
b. The contractor shall follow The Veterans Affair Acquisition Regulation (VAAR) security clause VAAR- 852.273-75 “SECURITY REQUIREMENTS FOR UNCLASSIFIED INFORMATION TECHNOLOGY RESOURCES”
c. The contractor and their personnel shall be subject to the same Federal laws, regulations such as U.S.C Chapter 21, 29, 31, and VA policies as VA personnel, regarding information and information system security. These include but are not limited to Federal Information Security Management Act (FISMA), Appendix III of OMB Circular A-130, and guidance and standards, available from the Department of Commerce's National Institute of Standards and Technology (NIST). This also includes the use of common security configurations available from NIST's Web site at: http://checklists.nist.gov. The contractor and their personnel agree to comply with Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974.
15. DATA RIGHTS
VA will retain all ownership rights to the data provided to the Contractor or collected by the Contractor and will maintain a complete record (original or copy) of all data obtained in accordance with privacy requirements, the Federal Records Act, and applicable federal records retention requirements.
16. CONTRACTOR POINT OF CONTACT
The Contractor shall assign a Point of Contact (POC) and an alternate POC for the purpose of ensuring compliance with all the terms and conditions of this contract and who shall be responsible for administration and clinical matters in the performance of services under this contract. The POC shall have full authority to act for the Contractor on all matters relating to the daily operation of this contract. The POC shall be available by telephone Monday through Friday, between 7:30 a.m. to 4:00 p.m. excluding National Holidays.
Point of Contact (Full Name):
Telephone Number:
E-mail Address:
Alternate Point of Contact (Full Name):
Telephone Number:
E-mail Address:
17. NORMAL WORKING HOURS:
Contractor will shall be performing services between the hours of 7:30 AM through 4:00 PM Monday through Friday, with exceptions to National Holidays.
18. OVERTIME AND NATIONAL HOLIDAYS:
Any overtime or holiday pay that may be entitled to the Contractor’s employees shall be the sole responsibility of the Contractor and shall not be billed to nor reimbursed by the Government.
In accordance with 5 U.S.C. 6103, Executive Order 11582 and Public Law 94-97 the following national holidays are observed and for the purpose of this contract are defined as “Legal Federal official holidays”:
| New Year’s Day |
| January 1st |
| Martin Luther King’s Birthday |
| Third Monday in January |
| President’s Day |
| Third Monday in February |
| Memorial Day |
| Last Monday in May |
| Independence Day |
| July 4th |
| Labor Day |
| First Monday in September |
| Columbus Day |
| Second Monday in October |
| Veteran’s Day |
| November 11th |
| Thanksgiving Day |
| Fourth Thursday in November |
| Christmas Day |
| December 25th |
When a holiday falls on a Sunday, the following Monday will be observed as a National Holiday. When a holiday falls on a Saturday, the preceding Friday is observed as a National Holiday by U.S. Government Agencies. Also included would be any day specifically declared by the President of the United States of America as a National holiday.
B.3 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deliverable One: Scoping review protocol detailing search terms, search strategy, inclusion and exclusion criteria.
Contract Period: Base POP Begin: 07-01-2019 POP End: 06-30-2020
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deliverable Two: Methods, evidence table, synthesis, bibliography
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deliverable Three: Journal Manuscript
| GRAND TOTAL |
| __________________ |
B.4 DELIVERY SCHEDULE
| ITEM NUMBER |
| QUANTITY |
| DELIVERY DATE |
| 1.00 JOB |
| 8/31/2019 |
| 1.00 JOB |
| 3/31/2020 |
| 1.00 JOB |
| 6/30/2020 |
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (OCT 2018)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
C.2 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days.
(End of Clause)
C.3 52.227-14 RIGHTS IN DATA—GENERAL (MAY 2014)
(a) Definitions. As used in this clause— "Computer database" or "database" means a collection of recorded information in a form capable of, and for the purpose of, being stored in, processed, and operated on by a computer. The term does not include computer software.
"Computer software"—
(1) Means
(i) Computer programs that comprise a series of instructions, rules, routines, or statements, regardless of the media in which recorded, that allow or cause a computer to perform a specific operation or series of operations; and
(ii) Recorded information comprising source code listings, design details, algorithms, processes, flow charts, formulas, and related material that would enable the computer program to be produced, created, or compiled.
(2) Does not include computer databases or computer software documentation.
"Computer software documentation" means owner's manuals, user's manuals, installation instructions, operating instructions, and other similar items, regardless of storage medium, that explain the capabilities of the computer software or provide instructions for using the software.
"Data" means recorded information, regardless of form or the media on which it may be recorded. The term includes technical data and computer software. The term does not include information incidental to contract administration, such as financial, administrative, cost or pricing, or management information.
"Form, fit, and function data" means data relating to items, components, or processes that are sufficient to enable physical and functional interchangeability, and data identifying source, size, configuration, mating and attachment characteristics, functional characteristics, and performance requirements. For computer software it means data identifying source, functional characteristics, and performance requirements but specifically excludes the source code, algorithms, processes, formulas, and flow charts of the software.
"Limited rights" means the rights of the Government in limited rights data as set forth in the Limited Rights Notice of paragraph (g)(3) if included in this clause.
"Limited rights data" means data, other than computer software, that embody trade secrets or are commercial or financial and confidential or privileged, to the extent that such data pertain to items, components, or processes developed at private expense, including minor modifications.
"Restricted computer software" means computer software developed at private expense and that is a trade secret, is commercial or financial and confidential or privileged, or is copyrighted computer software, including minor modifications of the computer software.
"Restricted rights", as used in this clause, means the rights of the Government in restricted computer software, as set forth in a Restricted Rights Notice of paragraph (g) if included in this clause, or as otherwise may be provided in a collateral agreement incorporated in and made part of this contract, including minor modifications of such computer software.
"Technical data", means recorded information (regardless of the form or method of the recording) of a scientific or technical nature (including computer databases and computer software documentation). This term does not include computer software or financial, administrative, cost or pricing, or management data or other information incidental to contract administration. The term includes recorded information of a scientific or technical nature that is included in computer databases. (See 41 U.S.C. 116).
"Unlimited rights" means the rights of the Government to use, disclose, reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly, in any manner and for any purpose, and to have or permit others to do so.
(b) Allocation of rights.
(1) Except as provided in paragraph (c) of this clause, the Government shall have unlimited rights in—
(i) Data first produced in the performance of this contract;
(ii) Form, fit, and function data delivered under this contract;
(iii) Data delivered under this contract (except for restricted computer software) that constitute manuals or instructional and training material for installation, operation, or routine maintenance and repair of items, components, or processes delivered or furnished for use under this contract; and
(iv) All other data delivered under this contract unless provided otherwise for limited rights data or restricted computer software in accordance with paragraph (g) of this clause.
(2) The Contractor shall have the right to—
(i) Assert copyright in data first produced in the performance of this contract to the extent provided in paragraph (c)(1) of this clause;
(ii) Use, release to others, reproduce, distribute, or publish any data first produced or specifically used by the Contractor in the performance of this contract, unless provided otherwise in paragraph (d) of this clause;
(iii) Substantiate the use of, add, or correct limited rights, restricted rights, or copyright notices and to take other appropriate action, in accordance with paragraphs (e) and (f) of this clause; and
(iv) Protect from unauthorized disclosure and use those data that are limited rights data or restricted computer software to the extent provided in paragraph (g) of this clause.
(c) Copyright—
(1) Data first produced in the performance of this contract.
(i) Unless provided otherwise in paragraph (d) of this clause, the Contractor may, without prior approval of the Contracting Officer, assert copyright in scientific and technical articles based on or containing data first produced in the performance of this contract and published in academic, technical or professional journals, symposia proceedings, or similar works. The prior, express written permission of the Contracting Officer is required to assert copyright in all other data first produced in the performance of this contract.
(ii) When authorized to assert copyright to the data, the Contractor shall affix the applicable copyright notices of 17 U.S.C. 401 or 402, and an acknowledgment of Government sponsorship (including contract number).
(iii) For data other than computer software, the Contractor grants to the Government, and others acting on its behalf, a paid- up, nonexclusive, irrevocable, worldwide license in such copyrighted data to reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly by or on behalf of the Government. For computer software, the Contractor grants to the Government, and others acting on its behalf, a paid- up, nonexclusive, irrevocable, worldwide license in such copyrighted computer software to reproduce, prepare derivative works, and perform publicly and display publicly (but not to distribute copies to the public) by or on behalf of the Government.
(2) Data not first produced in the performance of this contract. The Contractor shall not, without the prior written permission of the Contracting Officer, incorporate in data delivered under this contract any data not first produced in the performance of this contract unless the Contractor—
(i) Identifies the data; and
(ii) Grants to the Government, or acquires on its behalf, a license of the same scope as set forth in paragraph (c)(1) of this clause or, if such data are restricted computer software, the Government shall acquire a copyright license as set forth in paragraph (g)(4) of this clause (if included in this contract) or as otherwise provided in a collateral agreement incorporated in or made part of this contract.
(3) Removal of copyright notices. The Government will not remove any authorized copyright notices placed on data pursuant to this paragraph (c), and will include such notices on all reproductions of the data.
(d) Release, publication, and use of data. The Contractor shall have the right to use, release to others, reproduce, distribute, or publish any data first produced or specifically used by the Contractor in the performance of this contract, except—
(1) As prohibited by Federal law or regulation (e.g., export control or national security laws or regulations);
(2) As expressly set forth in this contract; or
(3) If the Contractor receives or is given access to data necessary for the performance of this contract that contain restrictive markings, the Contractor shall treat the data in accordance with such markings unless specifically authorized otherwise in writing by the Contracting Officer.
(e) Unauthorized marking of data.
(1) Notwithstanding any other provisions of this contract concerning inspection or acceptance, if any data delivered under this contract are marked with the notices specified in paragraph (g)(3) or (g) (4) if included in this clause, and use of the notices is not authorized by this clause, or if the data bears any other restrictive or limiting markings not authorized by this contract, the Contracting Officer may at any time either return the data to the Contractor, or cancel or ignore the markings. However, pursuant to 41 U.S.C. 4703, the following procedures shall apply prior to canceling or ignoring the markings.
(i) The Contracting Officer will make written inquiry to the Contractor affording the Contractor 60 days from receipt of the inquiry to provide written justification to substantiate the propriety of the markings;
(ii) If the Contractor fails to respond or fails to provide written justification to substantiate the propriety of the markings within the 60-day period (or a longer time approved in writing by the Contracting Officer for good cause shown), the Government shall have the right to cancel or ignore the markings at any time after said period and the data will no longer be made subject to any disclosure prohibitions.
(iii) If the Contractor provides written justification to substantiate the…