CTX Gutter Installation Questions Answers.docx

DOCX document 13 KB Posted

Attached to
J056--Amend: Correct RFQ and Post: Tech Qs & As, Sign-in, Site Map Gutter Installation Federal contract opportunity
Solicitation number
36C25723Q0928
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

View the file

Other files for this federal contract opportunity

Other files attached to J056--Amend: Correct RFQ and Post: Tech Qs & As, Sign-in, Site Map Gutter Installation, newest first.
File Type Posted
Gutter Buildings Map.pdf PDF
S02 36C25723Q0928 Corrected.docx DOCX document
36C25723Q0928 0001_1.docx DOCX document
Site Visit Sigin.pdf PDF
P07 Wage Determination 2015-5237.pdf PDF
36C25723Q0928_1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CTX Gutter Installation

RFQ 36C25723Q0928

1) Are old gutters still on the building and how much? There is an old down spout on 45E north side that needs to be removed. That is all I found when I walked the area.

2) What gauge guttering and downspouts are required? .032 minimum

3) Sect B states to remove any existing guttering but during the walkthrough the VA Rep stated they want to keep the new section of gutter on the north side of building 46E. Are we to leave that section of gutter alone? Are there any other areas like this? So correction to the walkthrough. They want all the gutter to be new. So, this section will need to be replaced.

4) Please confirm the contractor does not need to put new guttering on the corridor between buildings and where the corridor meets each building. That is correct, the central hallway does not need to have gutter.