Questions _ Answers.docx
DOCX document 14 KB Posted
- Attached to
- J065--Security Install Federal contract opportunity
- Solicitation number
- 36C25723Q0497
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25723Q0497_3.docx | DOCX document | |
| 36C25723Q0497_2.docx | DOCX document | |
| 36C25723Q0497_1.docx | DOCX document | |
| Wage Determination 15-5237.txt | TXT text file | |
| 36C25723Q0497.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Will floorplans be provided for the scope of work at each building?
· A: Yes
· Will the selected contractor be responsible for programming and testing access control equipment already installed but inactive in Building 47?
· A: Yes
· The work specs on page 5, section 1.1 A differ from the information provided on the site visit. We would like clarification on the following:
1. Is a new iStar control panel required for Building 44E? If so, where will it be located? A: No
1. Relocation of an installed reader to the other side of the door at 2nd floor reader in Building 44, going west. Door has an exit device going from west to east. Will door be reconfigured to move crash bar to the other side, or will it be secured by other means when the reader is moved? A: The door will be reconfigured.
1. Is each building to receive a new NVR? A: Yes
1. Is the Bosch intrusion system to be removed from Building 206? A: No