36C25720Q0559-000.docx

DOCX document Posted

Attached to
J045--New-Tie-ins for Temporary Boiler Federal contract opportunity
Solicitation number
36C25720Q0559
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

36C25720Q0559 36C25720Q0559_1.docx

View the file

Other files for this federal contract opportunity

Other files attached to J045--New-Tie-ins for Temporary Boiler, newest first.
File Type Posted
36C25720Q0559 P00001_1 REVISED.docx DOCX document
36C25720Q0559-001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Opportunity Combined Synopsis/Solicitation Notice

CLASSIFICATION CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

RESPONSE DATE (MM-DD-YYYY)

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

* = Required Field Contract Opportunity Combined Synopsis/Solicitation Notice J045 New-Tie-ins for Temporary Boiler 76504 36C25720Q0559 05-26-2020 N

SDVOSBC

238290 Department of Veterans Affairs

NCO 17

2002 Scott Blvd Temple TX 76504 Lynn Pettit Doris Miller VAMC 4800 Memorial Drive Waco, Texas 76711 Lynn.Pettit@va.gov lynn.pettit@va.gov VA Valley Coastal Bend Health Care Services intends to issue a construction contract. The project consists of:

The Contractor shall provide all labor, transportation, materials, equipment and supervision required for the removal and replacement of the electrical feed line to the HVAC roof top unit #8 located on the roof. Contractor is to also remove and replace damaged exterior electrical boxes and replace four (4) each 20amp GFCI receptacles. On conclusion of installation, Contractor is to verify and load new circuits to test equipment and wiring. Contractor will also clean-up and haul away any job-related debris.

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25720Q0559 05-13-2020 674-20-3-5065-1808 Department of Veterans Affairs

NCO 17

2002 Scott Blvd Temple TX 76504 Department of Veterans Affairs

NCO 17

2002 Scott Blvd Temple TX 76504 Lynn Pettit 254-899-6001 Waco VA Boiler Rental Boiler Tie-in IAW SOW.

Magnitude of construction: Between $100,000 and $250,000

SITE VISIT: MAY 19, 2020, 10:00AM CST

LOCATION: DORIS MILLER VAMC, 4800 MEMORIAL DRIVE, ENERGY CENTER BUILDING 225, WACO, TX 76711

Inform the VA of your intent to attend the site visit by email May 18, 2020, 2:30PM CST.

Any questions or concerns regarding this solicitation and site visit should be forwarded in writing via email to the Contracting Officer at Lynn.Pettit@va.gov. Questions inresponse to this solicitation and site visit are due no later than May 20, 2020, 12:00PM CST.

X X X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Department of Veterans Affairs

NCO 17

2002 Scott Blvd Temple TX 76504 This is accomplished through the Tungsten Network located at:

http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.

(877) 353-9791

(512) 460-5540

Table of Contents

PART I - THE SCHEDULE3
SECTION A - SOLICITATION/CONTRACT FORM3
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)3
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK4
A.3 PRICE/COST SCHEDULE7
ITEM INFORMATION7
A.4 SCOPE OF WORK8
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS14
2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)14
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)14
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)14
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)15
2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)16
REPRESENTATIONS AND CERTIFICATIONS17
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)17
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019)21
GENERAL CONDITIONS23
4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)23
4.2 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)24
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)25
4.4 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)25
4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2020)26
4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)29
4.7 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)32
4.8 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)32
4.9 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)34
4.10 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)35
4.11 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)36
4.12 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)36
4.13 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)37
4.14 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)39

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

LABOR COST: INSTALL OF BLOW DOWN CONDENSTATE LINES, WATER LINES, STEAM LINES, FUEL OIL LINES, GAS LINES, AND TIE-IN LINES.

LOCAL STOCK NUMBER: LABOR COST

1.00
JB
__________________
__________________

EQUIPMENT AND MATERIAL COST: MATERIAL-PIPING, ELBOWS, CONNECTIONS, WELDING MATERIALS, EQUIPMENT, CORING, INSULATION, AND ETC.

LOCAL STOCK NUMBER: EQ/MATERIAL COST

GRAND TOTAL
__________________

Page 1 of Page 1 of Page 1 of Page 1 of

A.4 SCOPE OF WORK

Building 225 VA Boiler Plant Rental Boiler Tie-In Waco VA Project

Requirements

The contractor shall provide all personnel, services, vehicles, transportation, tools, equipment, materials, supplies, facility supervision, administration supervision and any other item(s) necessary to perform and accomplish the services required for the Waco VA Boiler Rental Boiler Tie-in at Building 225, the Boiler Plant. Work shall be performed at the Doris Miller VA Medical Center (VAMC) in Waco, at 4800 Memorial Drive, Waco, Texas 76504 in Building 225. After all work is completed, the contractor will have a walkthrough with the VA COR and Operators to ensure all work is completed and ready to receive payment.

The contractor shall be familiar with all the terms, conditions, and requirements herein contained with warranty items and conditions in the contract. All work must comply with federal, state and local regulations. All welding work must comply with American Welding Society (AWS) as well American Society of Mechanical Engineers (ASME) codes for welding with Boiler and Pressure Vessel Certification (BPVC). All welds must be inspected and hydrostatic test by an independent contractor with a welding inspection certification prior to completion, (with no add cost to the VA).

The contractor shall provide the VA COR with a completed summary report, and list of any new deficiencies. If any other deficiencies arise that are not covered under this scope of work, the vendor will provide a quote for any needed corrective actions to the VA COR as soon as possible. The work will not be considered completed by the Government until the VA COR accepts the work.

All work shall be done according to the Infection Control Risk Assessment (ICRA) specified for the respective areas where work is performed.

Note: The Waco VA Boiler Rental Boiler Tie-in’s do not involve connectivity of any device/systems to the VA computer network and does not involve sensitive VA data. “The C&A requirements do not apply, and that a Security Accreditation Package is not required for this contract.”

Project Requirements

Base Bid – New Work Boiler Plant-Building 225

Contractor Responsibilities:

1. The Contractor shall visit the site to determine the full extent of the work. Failure to inspect the site will not constitute grounds for a claim after contract award. A site visit will be scheduled through the VA COR.

2. All permits for repair such as hot work permits, confined space entry permits, or etc. must be obtained from the VA Safety Department at least 24 hours in advance before work is to be done and coordinated with VA COR as well.

3. To ensure the uninterrupted operation of the medical facility, a shutdown will be conducted to install spool pieces with a valve to the existing piping. All valves are to be flanged for accessibility while the plant preforms normal operation.

4. Prior to attempting to tie in any connection, the contractor will verify the proper lock out/ tag out of all energy source.

5. Upon the completion of prefabrication, and coordination with the COR and plant operator on duty. The vendor will then conduct the installation of the rental boiler hook-ups connections. This will include tie ends to the existing steam header, natural gas line, fuel oil lines, and make-up water lines. This includes installation and insulation of pipe hangers, new valves, gaskets and blind flanges on each line ran.

6. (Note: VA Waco will be responsible for the required electrical power for the rental boiler. The vendor will provide the correct voltage and amperage prior to time of rental).

7. The service receipt will be provided to the customer upon completion of work.

8. At the end of the project clean up and haul off any debris, extra materials or waste that has accumulated during the project in accordance with EPA Guidelines and Regulations. Also, disposal of materials removed under this contract will comply with all local, state, and federal laws, regulations, and guidelines followed by contractor’s sole responsibility. The contractor shall adhere to all OSHA requirements concerning removal, transporting, and disposal of materials and hazardous materials.

Note: At the end of each workday, please clean-up all worked in areas.

1. Contractor will perform a final walkthrough with the VA COR or Alternative when completed.

A. Program Office Points of Contact:

a. Contracting Officer’s Representative (COR): Rene’ Flores, Engineering Tech (COR) – Engineering Service, 254-297-3722, Rene.Flores2@va.gov

b. Alternative (COR) Supervisory POC: Moses Briscoe, M&O Section Chief – Engineering Service, 254-709-0523, Moses.Briscoe1@va.gov

2. The following will be provided during final walkthrough.

a. Inspection summary reports.

b. Provide training to all essential VA Employees and Engineering staff about operations and new tie points for temporary boiler.

c. Document conditions, values and recommendations on Contractor provided forms and submit to the COR at the completion of inspection.

3. Coordinate with VA COR before the start of this service and completion. See information below:

A. Government Holidays:

(a) The Government hereby provides notice and Contractor hereby acknowledges receipt that Government personnel observe the listed days as holidays:

New Year's DayJanuary 1st
Martin Luther King's BirthdayThird Monday in January
Washington’s BirthdayThird Monday in February
Memorial DayLast Monday in May
Independence DayJuly 4th
Labor DayFirst Monday in September
Columbus DaySecond Monday in October
Veterans DayNovember 11th
Thanksgiving DayFourth Thursday in November
ChristmasDecember 25th

(b) In addition to the days designated as holidays, the Government observes the following days:

a. Any other day designated by Federal Statute

b. Any other day designated by Executive Order

c. Any other day designated by the President’s Proclamation

It is understood and agreed between the Government and the Contractor that observance of such days by Government personnel shall not otherwise be a reason for an additional period of performance, or entitlement of compensation. In the event the Contractor's personnel work during the holiday, they may be reimbursed by the Contractor, however, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, other than their normal compensation for the time worked.

4. Submit the proper documentation and reports to receive payment on this service. See information below:

A. Invoices and Payment

1. Payment to be made monthly, in arrears, following satisfactory performance by Contractor’s personnel and upon receipt of a properly prepared invoice.

1. Invoices submitted without correct purchase order/obligation document number and contract/purchase order number will not be processed.

1. Contractor shall be required to invoice through the Tungsten System at http://www.tungsten-network.com/us/en/veterans-affairs/. Additional information regarding Tungsten shall be provided upon award.

1. The contract shall have current registration in the System for Award Management (SAM) for this solicitation; URL: www.sam.gov.

1. The invoice MUST be itemized to include the following information. Any information listed below, and not provided on an invoice, will render that invoice incomplete and the invoice will be returned for immediate correction.

i. Time period being invoiced for.

ii. Description of services performed.

iii. Unit Cost billed.

iv. Extended amount due.

v. Invoice number, date, and;

vi. Contract and obligation numbers.

GENERAL INFORMATION

1. The Contractor shall notify the Contracting Officer’s Representative (COR) Moses Briscoe 254- 297-3762 prior to start of work. The Contractor shall schedule work through the COR, to ensure that all necessary parts, materials, tools are accounted for prior to the start of work. The Contractor shall coordinate work with COR NLT 7 days before starting work.

2. The scope work shall be completed within 60 days from the time the contract was awarded to the contractor.

3. Contractor shall provide all services including supervision, labor, travel, mileage, overtime and required parts/materials.

4. Contractors must have at a minimum R stamp to conduct tie-ins, and fabrication work present at location where work is performed.

5. The contractor shall be responsible for the verification of all requirements for this project. All measurements and conditions must be verified by the contractor. Any discrepancies between field conditions, project documents, and this SOW shall be immediately brought to the Contracting Officer’s attention.

6. The contractor will be required to submit a safety plan for VA review and approval prior to the performing work.

7. The contractor must comply with the requirements for Type C/Class II (Lowest Risk) Infection Control Risk Assessment (ICRA).

8. It is the contractor’s responsibility to provide adequate documentation verifying that any equipment and/or materials proposed will meet or exceed all federal government requirements. Majority of the work shall be performed during VA Normal Hours of Operations unless other wised noted by the COR. Normal working hours are 8:00 am – 4:30 pm, Monday – Friday.

a. Note: After Hours: Times vary and must be scheduled with Contracting Officer Representative (COR); generally, after 6:00 p.m. and before 6:00 a.m.

9. The contractor will be required to submit a phasing plan prior to performing work. The phasing plan shall be developed and coordinated with VA COR. The contractor’s supervisor shall always be available to address any needs the VA COR may have during the period of performance.

10. The contractor may be required to coordinate work activities and shutdowns with VA COR and M&O Supervisors.

11. The contractor shall thoroughly clean inside and outside of project site daily with contractor’s own equipment, including vacuums, mops, buckets, wash rags, dust mops, etc.

12. The contractor shall be responsible for the removal of project demo materials/debris /equipment from this facility when complete.

Codes and Standards The project shall be in accordance with the latest Uniform Building Code (UBC), National Fire Protection Associate (NFPA) standard, Uniform Federal Accessibility Standard (UFAS), American Welding Society (AWS), American Standards of Mechanical Engineers (ASME), VA Specifications and Standards, and local facility requirements. In the event there is a conflict between any of the standards/codes, the more stringent standard/code shall apply.

The contractor shall provide all applicable safety signage and barricades applicable to OSHA, VHA and DOD regulations. Contractor shall comply with VHA DIRECTIVE 2004-012 and all VA Center Policy Memorandums, including but not limited to the following:

(a) Protection of patients, visitors, and employees from traumatic injury, as well as occupational and facility–associated infections.

(b) Compliance with OSHA and State construction safety regulations. Construction contracts require that the general contractor’s on-site “competent person” have completed the OSHA 30-hour construction worker course and that all other general and sub-contractor’s workers have completed the OSHA 10-hour construction worker course or other relevant competency training. The determination for training is based on the project hazards and complexity, State and Federal regulations and VA requirements. Verification of completion of training will be required prior to performing work.

(c) Compliance with EPA and State environmental regulations.

SAFETY PLAN REQUIREMENTS

Prior to performing any work, the contractor will be required to submit a safety plan in accordance with OSHA and VA Regulations.

The safety plan shall include, but not limited to the following:

A. Safety and Health Policy (i.e. company policy) B. Safety and Health Objectives (i.e. company goals, procedures, etc.)

C. Job Site Inspections (i.e. safety inspection/potential hazards/prevention, etc.)

D. Contractor Safety Administrator (i.e. competent person/safety officer) E. Personal Protective Equipment (i.e. head, hearing, and eye protection, footwear, clothing, gloves, etc.)

F. Safety Rules (i.e. rules applicable to the work/task being performed, equipment, ladders, confined spaces, open flame, etc.)

G. Job Safety Training (i.e. OSHA, safety meetings, etc.)

· 30 Hour OSHA Construction Safety Course – competent person

· 10 Hour OSHA Construction Safety Course – all others H. Safety Discipline (i.e. correction of violations, etc.)

I. Hot Work Permit (i.e. responsibilities, procedures, etc.)

J. Emergency Procedures (i.e. responsibilities, procedures, etc.)

K. Written Hazard Communication Program (i.e. responsibilities, procedures, list of hazards, MSDS, etc.)

SAFETY INSPECTIONS

On a weekly basis, the VA will conduct a safety inspection of the work area. This inspection includes, but is not limited to the following:

A. Means of Egress

· Fire/Smoke Doors unlocked, free of obstructions

· Means of Egress (includes Exits) free of obstructions and clearly marked

B. Fire Alarm, Fire Detection, and Fire Suppression Systems.

· Fire Alarm Pull Stations are unobstructed

· Smoke Detector smoke caps in use, or removed at end of the day

· Hot Work Permits are current, in use

· Sprinkler Heads are unobstructed

C. Housekeeping and Traffic Control

· Trash and debris are removed promptly and transported outside the construction area

· Floor mats and dust tack mats are located at the entrance to construction area

· Tools and equipment are properly stored

· Signs installed to restrict patient access (doors locked as needed)

· Dust control measures are in place

· Barriers are in place and properly sealed

D. Hazardous Chemicals/Conditions

· Appropriate storage of hazardous chemicals

· MSDS sheets are readily available on-site

· Lock out/tag out procedures are in place

· Hot work permit is current and posted

E. Clothing

· PPE is available and properly worn

· Clothing is relatively dust free with the construction area and patient areas

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

FAR Number
Title
Date
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
FEB 1999

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— May 19, 2020, 10:00AM CST

(c) Participants will meet at—

4800 MEMORIAL DRIVE, ENERGY CENTER BUILDING 225

(End of Provision)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238290.

(2) The small business size standard is $16.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.

(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.

(D) If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause #
Title
Date
Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of Provision)

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEC 2019) The Offeror shall not complete the representation in this provision if the Offeror has represented that it “does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument” in the provision at 52.204-26, Covered Telecommunications Equipment or Services—Representation, or in paragraph (v) of the provision at 52.212-3, Offeror Representations and Certifications—Commercial Items.

(a) Definitions. As used in this provision— Covered telecommunications equipment or services, critical technology, and substantial or essential component have the meanings provided in clause 52.204–25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition. Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115–232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Contractors are not prohibited from providing—

(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.

(d) Representation. The Offeror represents that it [ ] will, [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation.

(e) Disclosures. If the Offeror has represented in paragraph (d) of this provision that it “will” provide covered telecommunications equipment or services, the Offeror shall provide the following information as part of the offer—

(1) A description of all covered telecommunications equipment and services offered (include brand; model number, such as original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable);

(2) Explanation of the proposed use of covered telecommunications equipment and services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b) of this provision;

(3) For services, the entity providing the covered telecommunications services (include entity name, unique entity identifier, and Commercial and Government Entity (CAGE) code, if known); and

(4) For equipment, the entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known).

(End of Provision)

GENERAL CONDITIONS

4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Clause)

FAR Number
Title
Date
52.203-19
PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS
JAN 2017
52.204-9
PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL
JAN 2011
52.204-10
REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
OCT 2018
52.204-13
SYSTEM FOR AWARD MANAGEMENT MAINTENANCE
OCT 2018
52.204-18
COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE
JUL 2016
52.204-19
INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS
DEC 2014
52.204-23
PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES
JUL 2018
52.204-25
PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT
AUG 2019
52.209-6
PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT
OCT 2015
52.209-10
PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS
NOV 2015
52.213-4
TERMS AND CONDITIONS—SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS)
JAN 2020
52.222-3
CONVICT LABOR
JUN 2003
52.222-6
CONSTRUCTION WAGE RATE REQUIREMENTS
AUG 2018
52.222-7
WITHHOLDING OF FUNDS
MAY 2014
52.222-8
PAYROLLS AND BASIC RECORDS
AUG 2018
52.222-9
APPRENTICES AND TRAINEES
JUL 2005
52.222-10
COMPLIANCE WITH COPELAND ACT REQUIREMENTS
FEB 1988
52.222-11
SUBCONTRACTS (LABOR STANDARDS)
MAY 2014
52.222-12
CONTRACT TERMINATION—DEBARMENT
MAY 2014
52.222-13
COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS
MAY 2014
52.222-14
DISPUTES CONCERNING LABOR STANDARDS
FEB 1988
52.222-15
CERTIFICATION OF ELIGIBILITY
MAY 2014
52.222-21
PROHIBITION OF SEGREGATED FACILITIES
APR 2015
52.222-26
EQUAL OPPORTUNITY
SEP 2016
52.222-27
AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION
APR 2015

4.2 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)

(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

(End of Clause)

FAR Number
Title
Date
52.222-50
COMBATING TRAFFICKING IN PERSONS
JAN 2019
52.222-55
MINIMUM WAGES UNDER EXECUTIVE ORDER 13658
DEC 2015
52.222-62
PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706
JAN 2017
52.223-5
POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION
MAY 2011
52.223-18
ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
AUG 2011
52.225-13
RESTRICTIONS ON CERTAIN FOREIGN PURCHASES
JUN 2008
52.228-2
ADDITIONAL BOND SECURITY
OCT 1997
52.228-11
PLEDGES OF ASSETS
AUG 2018
52.228-12
PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS
MAY 2014
52.232-5
PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS
MAY 2014
52.232-23
ASSIGNMENT OF CLAIMS
MAY 2014
52.232-27
PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS
JAN 2017
52.232-33
PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.232-39
UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS
JUN 2013
52.232-40
PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS
DEC 2013
52.233-1
DISPUTES ALTERNATE I (DEC 1991)
MAY 2014
52.233-3
PROTEST AFTER AWARD
AUG 1996
52.233-4
APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM
OCT 2004
52.236-2
DIFFERING SITE CONDITIONS
APR 1984
52.236-3
SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
APR 1984
52.236-5
MATERIAL AND WORKMANSHIP
APR 1984
52.236-6
SUPERINTENDENCE BY THE CONTRACTOR
APR 1984
52.236-7
PERMITS AND RESPONSIBILITIES
NOV 1991
52.236-8
OTHER CONTRACTS
APR 1984
52.236-9
PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS
APR 1984
52.236-11
USE AND POSSESSION PRIOR TO COMPLETION
APR 1984
52.236-12
CLEANING UP
APR 1984
52.236-13
ACCIDENT PREVENTION
NOV 1991
52.236-17
LAYOUT OF WORK
APR 1984
52.236-26
PRECONSTRUCTION CONFERENCE
FEB 1995
52.242-5
PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS
JAN 2017
52.242-14
SUSPENSION OF WORK
APR 1984
52.243-4
CHANGES
JUN 2007
52.243-5
CHANGES AND CHANGED CONDITIONS
APR 1984
52.244-6
SUBCONTRACTS FOR COMMERCIAL ITEMS
AUG 2019
52.246-12
INSPECTION OF CONSTRUCTION
AUG 1996
52.246-21
WARRANTY OF CONSTRUCTION
MAR 1994
52.249-2
TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) ALTERNATE I (SEPT 1996)
APR 2012
52.249-10
DEFAULT (FIXED-PRICE CONSTRUCTION)
APR 1984

4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 days after receipt of award. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by . The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of Clause)

4.4 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)

(a) The Contractor shall submit one of the following payment protections:

Payment Bond

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

(End of Clause)

4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2020)

(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other…