About this file

36C25220Q0337 0001 36C25220Q0337 0001.docx

View the file

Other files for this federal contract opportunity

Other files attached to N041--25 Ton Chiller Replacement, newest first.
File Type Posted
36C25220Q0337-003.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25220Q0337 0001

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 03-02-2020 556-20-1-5020-0416 None 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Road Building 1, Room 326 North Chicago IL 60064 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) Building 1, Room 326 3001 Green Bay Road North Chicago IL 60064 To all Offerors/Bidders

36C25220Q0337 02-25-2020

X X X Wednesday, March 18, 2020 @

10:00AM

Local Time 556-3600169-5020-754200-3223 070054100 Reference solicitation 36C25220Q0337 to replace the exisitng Chiller at the Captain James A. Lovell Federal Health Care Center (FHCC) in accordance with the Statement of WOrk (SOW). The purpose of this Amendment is to provide the following:

- Provide answers to questions submitted by interested parties (see continuation page 2)

- Schedule a non-mandatory site visit for interested parties (see continuation page 2)

- Extend the period of performance through May 15, 2020.

- Extend the cut-off date for questions from interested parties to Wednesday, Mar ch 11, 2020, 1:00PM Local Time

- Extend the offer due date to Wednesday, March 18, 2020, 10:00AM Local Time

All other terms and conditions of the solicitation remain unchanged.

Naqikah Greenfield Contracting Officer

CONTINUATION PAGE

Amendment 0001 for solicitation RFQ 36C25220Q0337 for 25 Ton Chiller Replacement at the Captain James A. Lovell Federal Health Care Center (FHCC) located in North Chicago, IL.

Questions and Answers:

Q1: Are you doing a walkthrough for this project?

A2: A non-mandatory site visit is scheduled for Monday, March 9, 2020 at 10:00AM Local Time. Please RSVP to the Contracting Officer via email at Naqikah.Greenfield@va.gov by 5:00PM Local Time on Friday, March 6, 2020. The site visit will be held at the following address:

Captain James A. Lovell Federal Health Care Center (FHCC) 3001 Green Bay Road Building 133, Main Lobby North Chicago, Illinois 60064

Point of Contact: Naqikah Greenfield, Contracting Officer Naqikah.Greenfield@va.gov

Q2: Please provide as-builts for this project in order to accurately assess the project.

A2: A site visit will be held to assess the project.

Q3: Do you have existing drawings, drawings for this project? Where are the panels located for electrical disconnects?

A3: A site visit will be held to assess the project.

Q4: Who is responsible for the discard of existing glycol, sometimes its VA, sometimes its contractor?

A4: Glycol will be saved and reused as stated in SOW. Any excess will be disposed of by VA. Contractor will provide Glycol if needed.

Q5: What are the BAS requirements for this project? ALC typically owns the facility controls and BAS, but is this JCI or other. This is a large component of the project that is not defined in the solicitation.

A5: ALC controls will be transferred from existing unit to new unit.

Q6: Commissioning is an extremely important part of this mechanical process. Who is the commissioning agent (CxA) for the job? Is the contractor expected to have 3rd party commissioning to ensure this equipment is properly tested, sequenced etc? Is the GC just the CxR?

A6: General contractor will be commissioning agent.

Q7: Does the facility require this to be a 1st, 2nd, or 3rd shift project?

A7: This project will need to be a weekend project completed between end of operating room hours on Friday through start of operations on Monday.

Q8: Does the facility have a logistics plan for the project? Meaning the pathway for the chiller to the location?

A8: Crane lift from loading dock at 133 to roof.

Q9: We do not understand the Period of Performance. Solicitation states date of award, but what is the legal contractual POP? Date of award says April 15th but then is says “One time service” not later than April 15th? What does this mean?

A9: The period of performance will begin on the Date of [Contract] Award through April 15, 2020 which has now been extended through May 15, 2020. This means that services can begin on the date of contract award and all work shall be completed in accordance with the Statement of Work no later than May 15, 2020.

Q10: What is the warranty duration for this project?

A10: Standard factory warranty.

Q11: What is the insulation lf’ expectation on this job? Are we just insulating at the chilled water piping that is removed? Are you expecting all new piping?

A11: Reinsulate new piping and fittings that were removed to install new unit.

Q12: US Government asks for 3 references for this job for past performance evaluation and this job was given 5 calendar days to bid? Are old PPQs allowable?

A12: The offer due date has been extended.

Q13: FAR requires a 50% cost of personnel as direct cost to the Prime Contractor. FAR 52.219-14. Is this waived for the project?

A13: No.

Q14: What are the supervision requirements of the Prime for this project? Full-time superintendent?

A14: Supervision requirements will be determined by the vendor.

Q15: Do I have to submit bid bond at the time of submitting proposal?

A15: No.