36C25219B0028-000.docx

DOCX document 96 KB Posted

Attached to
537-19-128 Repair Mechanical Systems Bed Tower 3 Federal contract opportunity
Solicitation number
36C25219B0028
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

36C25219B0028 36C25219B0028_1.docx

View the file

Other files for this federal contract opportunity

Other files attached to 537-19-128 Repair Mechanical Systems Bed Tower 3, newest first.
File Type Posted
36C25219C0122-000.docx DOCX document
36C25219B0028-0004000.docx DOCX document
36C25219B0028-0003001.pdf PDF
36C25219B0028-0003000.docx DOCX document
36C25219B0028-0003002.pdf PDF
36C25219B0028-0002001.pdf PDF
36C25219B0028-0002000.docx DOCX document
36C25219B0028-0001000.docx DOCX document
36C25219B0028-0001001.pdf PDF
36C25219B0028-006.pdf PDF
36C25219B0028-005.pdf PDF
36C25219B0028-003.pdf PDF
36C25219B0028-001.pdf PDF
36C25219B0028-002.pdf PDF
36C25219B0028-004.pdf PDF
36C25219B0028.docx DOCX document
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25219B0028

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25219B0028 X 02-14-2019 537-19-3-6985-0046 537-19-128 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee

WI

53214-1476 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Road Building 1, Room 329 North Chicago

IL

60064-3048 Megan Manis megan.manis@va.gov

PROJECT 537-19-128 REPAIR MECHANICAL SYSTEM BED TOWER 3RD FLOOR (BT3)

Jesse Brown VA Medical Center has a requirement for a Contractor to provide all tools, materials, labor, components, and supervision for construction/remodeling of a fully functional mechanical room, to include sequencing chill water loop, steam/water loop, installing a cage, & a work bench in the AC Shop, and installing security cameras that are integrated into the security camera system.

This acquisition shall be 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) concerns per the authority of 38 U.S.C. 8127 (Public Law 109-461). In accordance with VAAR 819.7003(b), at the time of submission of bids, and prior to award of any contract, the offeror must represent to the CO that it is (1) SDVOSB eligible under VAAR 819.70; (2) small business concern under the NAICS code assigned to this acquisition; (3) SDVOSB listed as verified in the VIP database www.vip.vetbiz.gov.

NAICS: 238220 Plumbing, Heating, and Air-Conditioning Contractors SBA Size Standard: $15M

The magnitude of construction is between $500,000 and $1,000,000.

A pre-proposal construction conference/site visit is scheduled IAW FAR 52.236-7.

Wage Rate Requirement for this acquisition is IL190009.

Award will be made to the responsible bidder who submits the lowest responsive bid. A single award will be made.

X X 52.211-10 X 12:00 pm CST 03-27-2019 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C252 Department of Veterans Affairs

GLAC-NORTH CHICAGO IL

3001 Green Bay Road Building 1, Room 329 North Chicago

IL

60064-3048 Department of Veterans Affairs Financial Services Center PO Box 149971 Austin

TX

78714-9971 877-353-9791 512-460-5540

Contracting Officer’s Special Instructions as follows:

After compiling all required information, submit the information in accordance with Block 13 of the SF 1442 (page 2 of this solicitation). Return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442 (page 2 of this solicitation).

CONTRACTOR'S SIGNATURE:

In accordance with Federal Acquisition Regulations Part 4, contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows:

(a) Individuals. Signed by the individual.

(b) Individual doing business as a firm. Signed by that individual, and the signature shall be followed by the individual's typed, stamped, or printed name and the words, "an individual doing business as __________________ (insert name of firm)".

(c) Partnership. Signed in the partnership name. Prior to award, provide list of all partners and designate which partners have authority to bind the partnership.

(d) Corporations. Signed in the corporate name followed by the word "by" and the signature, and title of the person authorized to sign. Prior to award, provide list of individuals who have authority to bind the corporation.

(e) Joint Ventures. Signed by each participant in the joint venture in the manner prescribed in (a) through (d) above.

(f) Agents. When an agent is to sign the contract, other than as stated in paragraph (a) through (e) above, the agent's authorization to bind the principal must be established by evidence satisfactory to the contracting officer.

CONTRACT ADMINISTRATION DATA

1. CONTRACT ADMINISTRATION: All contract administration matters will be handled by the following individual(s):

a. CONTRACTOR: ___________________________________ ___________________________________ ___________________________________ ___________________________________ Contact Person: _____________________ Telephone #: _____________________ Fax #: _____________________ e-Mail Address: ___________________ Tax Identification Number: _____________________ DUNS Number: _____________________

b. GOVERNMENT: Contracting Officer (36C252/90C) Department of Veterans Affairs, Great Lakes Acquisition Center (NCO 12) Capt. James A. Lovell Federal Health Care Center 3001 Green Bay Rd., Bldg. 1, Rm 329 North Chicago, IL 60064-3048

2. SUBMITTAL OF OFFERS: All bids/offers must be submitted to the attention of the Contracting Officer identified No Later Than the date/time specified. Bids/Offers will be received at: Contracting Officer – (36C252/90C), Department of Veterans Affairs, Great Lakes Acquisition Center (NCO 12), Capt. James A. Lovell Federal Health Care Center, 3001 Green Bay Rd., Bldg. 1, Rm 329, North Chicago, IL 60064-3048 until the date and time specified.

NO FAX/ FACSIMILE/EMAILED SUBMITTED BIDS WILL BE ACCEPTED.

All transmittal envelopes or other packaging shall be clearly marked with the solicitation number, offeror’s company name and return address. All offers shall be subject to all terms and conditions of this solicitation.

3. QUESTIONS: Requests for Information (RFI) to solicitation documents should be submitted in writing to the Contract Specialist at: megan.manis@va.gov by March 14, 2019 at 1:30 pm, CST. No telephone responses will be accepted. NOTE: All questions must reference in the Header or Opening Statement the Project #, the IFB #, and the Description of the project.

4. All offers must be submitted to the attention of the Contracting Officer identified and listed on the Standard Form 1442, Block 9a and to the address identified on the Standard Form 1442, Block 13.

STATEMENT OF WORK

Project Name:Repair Mechanical Systems Bed Tower 3rd Floor (BT3)
Project Number:537-19-128
Place of Performance:Building 40
Jesse Brown VA Medical Center
Chicago, IL 60612

Part 1: Project Scope of Work Overview:

Contractor shall provide all tools, materials, labor, and supervision for construction/remodeling of fully functional mechanical room, to include sequencing chill water loop, steam/water loop, installing a cage and a work bench in the AC shop, and installing security cameras that are integrated into the security camera system.

Part 2. Period of Performance (POP)

1. Complete all work including submittals, reviews, quality control within 362 calendar days from Notice to Proceed (NTP) as shown below.

Accommodate the Period of Performance by including accelerated equipment delivery costs as well as adjusting crews.

Part 3: Detailed Project Scope of Work:

To minimize impact to Jesse Brown VA Medical Center’s operations the contractor shall sequence chill water loop work during the heating season (October 15 – April 15) and steam/hot water loop work during the cooling season (April 15 – October 15).

Part 1: Hydronic System:
1. The contractor shall furnish and install 23 water flow measuring devices. Flow measuring devices shall be BACNET compatible. The contractor shall incorporate the measuring devices into the JBVAMC Johnson Controls Inc. (JCI) Metasys system. The contractor shall provide a new chill water system graphics page for the BAS. COR shall approve final location for all sensors. After installation contractor shall reinsulate to match surrounding.
a. P-3 and P-4 Discharge Header (Total Hot Water System)
b. Hot Water Bypass Valve
c. Chill Water Supply to Building 40
d. AHU-1
i. Pre-heat Coil
ii. Cooling Coil
e. AHU-2
i. Pre-heat Coil
ii. Cooling Coil
f. AHU-3
i. Pre-heat Coil
ii. Cooling Coil

g. AHU-4

i. Pre-heat coil

ii. Cooling coil

h. AHU-6

i. Pre-heat coil

ii. Cooling coil

i. AHU-7

i. Pre-heat coil

ii. Cooling coil

j. AHU-8

i. Pre-heat coil

ii. Cooling coil

k. AHU-9

i. Pre-heat coil

ii. Cooling coil

l. AHU-10

i. Pre-heat coil

ii. Cooling coil

1. The contractor shall furnish and install temperature sensors at the inlet and outlet of each of the following coils. Sensor shall be integrated into the BAS and temperature readings shall be integrated into each AHU’s graphic on the BAS.

a. AHU-1

i. Pre-heat coil

ii. Cooling coil

b. AHU-2

i. Pre-heat coil

ii. Cooling coil

c. AHU-3

i. Pre-heat coil

ii. Cooling coil

d. AHU-4

i. Pre-heat coil

ii. Cooling coil

e. AHU-6

i. Pre-heat coil

ii. Cooling coil

f. AHU-7

i. Pre-heat coil

ii. Cooling coil

g. AHU-8

i. Pre-heat coil

ii. Cooling coil

h. AHU-9

i. Pre-heat coil

ii. Cooling coil

i. AHU-10

i. Pre-heat coil

ii. Cooling coil

2. The contractor shall furnish and install pressure and temperature sensors for both the ESG supply and return chill water pipes to Building 40. The contractor shall integrate the sensors into the BAS and display the readings on the new chill water system graphics page. Additionally, the contractor shall provide two analog temperature and pressure gages for both the supply and return chill water pipes. After installation contractor shall reinsulate to match surrounding.

3. The contractor shall furnish and install local analog pressure gages at the differential pressure sensors for the AHU hot water loop. Pressure gages to allow JBVAMC maintenance personnel to verify reading from the differential pressure sensors.

4. The contractor shall furnish and install new sixteen (16) pump expansion joints. Expansion joints shall be stainless steel construction. Expansion joints to be installed on the suction and discharge of the following pumps:

a. P-5

b. P-6

c. P-9

d. P-10

e. P-11

f. P-12

g. P-13

h. P-14

5. The contractor shall furnish and install 16 motor actuated isolation butterfly valves.

a. Valves are to be installed on the 4 AHUs that can be served by both the ESG Chiller Plant and the Bed Tower Rooftop Air Cooled Chillers.

i. AHU-1

ii. AHU-4

iii. AHU-5

iv. AHU-7

b. Valves shall include a manual override for emergency operation.

c. For each AHU supply a motor actuated valve for the chiller plant supply, chiller plant return, BT rooftop air cooled chiller supply, and BT rooftop air cooled chiller return.

d. After installation contractor shall reinsulate to match surrounding.

e. Integrate the motor actuated valves into the JBVAMC BAS.

i. The valves normal configuration shall be for each AHU’s chill water to be supplied by the Bed Tower Rooftop Air Cooled Chillers.

ii. Contractor shall include control of the valves at the BAS front end.

iii. Valve control logic shall include an interlock so only one set of valves can be opened to each AHU at once.

iv. Valve control logic shall automatically switch over the source of chill water if chill water is lost.

v. Each AHU’s BAS graphic will include an indicator for chill water source.

6. The contractor shall furnish and install new humidifiers for the following AHUs. Replacement shall address any leaks from the humidifiers. After installation contractor shall reinsulate to match surrounding.

a. AHU-5 – Serves the Operating Suite

7. The contractor shall furnish and install new control valves to replace the steam control valves and actuators for the listed converters. Contractor shall also replace the isolation valves and filters for each control valve. After installation contractor shall reinsulate to match surrounding.

a. Converter 1

i. 3-inch 1/3 Control Valve

ii. 4-inch 2/3 Control Valve

b. Converter 2

i. 3-inch 1/3 Control Valve

ii. 4-inch 2/3 Control Valve

c. Converter 3

i. 3-inch 1/3 Control Valve

ii. 4-inch 2/3 Control Valve

d. Converter 4

i. 3-inch 1/3 Control Valve

ii. 4-inch 2/3 Control Valve

8. The contractor shall furnish and replace the 30 PSI Medium Pressure Steam Isolation Gate Valve serving AHU-2, AHU-3, and AHU-8 humidifiers. Contractor shall also repair the leak at the valve.

9. The contractor shall furnish and install a new glycol make up pump.

10. The contractor shall chemically flush the heating and cooling coil for each AHU.

11. The contractor shall clean the air side of each AHU include both the heating and cooling coils.

12. The contractor shall clean the intake screen and outside air damper box for each AHU.

13. The contractor shall clean and service the fan heaters in the mechanical space.

a. FCU-6 Entrance 3rd Floor Mechanical Pent House

b. UH-1 West Side of Pent House Bed Tower

c. UH-2 Entrance to Pent House Bed Tower

d. UH-3 East Side of Pent House Bed Tower

e. UH-4 West Side of 3rd Floor Bed Tower

f. UH-5 – located above the paint locker on the 3rd Floor Bed Tower. The contractor shall remove and replace in kind. Additionally, contractor shall repair the leak that caused UH-5 to fail. Contractor to test and verify operation.

Part 2: AC Shop Cage / Shelving:

1. The contractor shall furnish and install a cage for the AC Shop, as shown in the exhibits.

a. Cage enclosure shall match the existing cage enclosure style and height.

b. Cage enclosure door shall be a sliding barn style door secured with a padlock.

2. The contractor shall furnish and install a work bench.

a. Work Bench shall be heavy duty grade

b. Work Bench shall have edge guards

c. Work Bench shall have a bottom shelf.

d. Top material shall be stainless steel.

e. Minimum Dimensions

i. Depth 36 inches

ii. Width 60 inches

3. The contractor shall furnish and install 10 Bulk Storage Racks in the caged in area.

a. Each Bulk Storage Rack Shall have a minimum of 3 shelves

b. Racks shall be 24 inches deep

c. Racks shall be 96 inches wide

d. Shelve decking shall be smooth solid surfaces.

e. Minimum shelf capacity of 1500 lb.

f. Final shelving configuration shall be presented to the COR for approval prior to installation.

Part 3: Video Surveillance System:

1. The contractor shall furnish and install four (4) security cameras. One on each entrance to the roof /mezzanine and one facing each entrance to the mechanical space from the stair wells.

a. Contractor shall integrate the new cameras into the JBVAMC security camera system.

List of Exhibits or Drawings to be included:

537-19-128 AC Shop Space (2-A15) 537-19-128 Building 40 Chill Water Diagram Sensor Motor Actuator Valves 537-19-128 Hot Water and Steam System (2-H90) 537-19-128 Hot Water System Sensors (1-H88)

Special Testing for Acceptance for the work shall be:

EIA/TIA testing and certification Cat 6e for all communications cable

Construction Progress Meetings:

1. The Contractor’s Project Manager and Field Supervisor shall provide onsite weekly construction progress meetings with the COR for the entire period of performance.

a. Subcontractors are not required to attend.

b. Include minutes of the meeting and issue not later than one day after the meeting. Both PDF and Word/Excel format

c. Construction progress meetings minutes shall contain: list of attendees, list any issues or concerns, indicate days remaining per the contract, detail any safety incidents, RFI log, Shop Drawing Log, detailed 2-week look ahead and shutdown schedule.

2. At 25%, 50%, 75% and 95%, coordinate with the COR for walk through inspection with the VA Shops. The Contractor shall have the Foreman from all trades attend. The VA Shops that will attend is the following: AC, Electrical, Plumbing and Carpenter Shops. The purpose of the meeting / walkthrough is the VA Shops Leads talk with the respective Contractor Trade Forman / Superintendent

Daily Report:

1. The Contractor shall provide a Daily Report in compliance with VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL. The Daily Report shall contain: list any issues or concerns, indicate days remaining per the contract, detail any safety incidents, detail daily construction safety inspections including items checked and corrective actions taken, and include relevant construction progress photo(s). Email the Daily Report to the COR not later than 9 am the next working day.

Part 4: Submittals and Milestone Deliverables:

1. KICK-OFF MEETING with DOCUMENTATION

a. The Contractor’s Project Manager and Field Supervisor shall attend a Preconstruction Safety Meeting, to discuss the project details.

b. Submit: Provide a FULLY LOADED COST SCHEDULE meeting the requirements of the VAAR 852.236-84 SCHEDULE OF WORK PROGRESS. Not less than one item per subcontractor. In addition, include any expected system shutdowns and off hours work.

c. Submit: LIST OF ALL CONTRACTORS AND SUBCONTRACTORS: company names, office address and main point of contact name with telephone number

d. Submit: CONSTRUCTION SAFETY PRECAUTIONS with project specific procedures, processes, analysis and details including but not limited to:

i. CONSTRUCTION SAFETY PLAN, LOCK OUT TAG OUT (LOTO), PERSONAL FALL ARREST SYSTEM, CONFINED SPACE PLAN

ii. ACCIDENT PREVENTION PLAN (APP) project specific

iii. ACTIVITY HAZARD ANALYSIS (AHA) project specific

e. Submit: CONSTRUCTION INFECTION CONTROL / DUST CONTROL PRECAUTIONS including:

i. Provide project specific details for construction infection control / dust control precautions for review and approval of the VA.

ii. In preparation of this item: Coordinate and meet with the COR in completing the VA’s Infection Control Risk Assessment documentation which is needed to obtain approval of the CONSTRUCTION INFECTION CONTROL / DUST CONTROL PRECAUTIONS by VA Infection Control. Include one on-site meeting with the VA COR in perpetration and one on-site meeting with the VA COR and the VA Infection Control Staff.

f. Submit: SHOP DRAWINGS AND PRODUCT LOG:

i. List all shop drawings and products in the submittal log.

g. Submit: Scanned copy of all workers OSHA Construction Safety Training certificates.

2. SHOP DRAWINGS AND PRODUCT SUBMITTALS

a. The Contractor shall provide all shop drawings and product submittals by email to the COR.

b. Allow 21 calendar days for AE and VA review, unless otherwise stated in the Period of Performance Char.

3. MOBILIZATION ON SITE INCLUDING PERFORMANCE OF THE WORK

a. Contractor shall not mobilize on site until all KICK-OFF MEETING AND DOCUMENTATION and SHOP DRAWINGS AND PRODUCT SUBMITTALS are reviewed and accepted by the VA.

b. Approval to mobilize shall be in writing by the COR.

c. Post and maintain emergency contact information, VA Infection Control Risk Assessment, and other information required by the COR, on the wall at all entry points to the worksite.

4. ACCEPTANCE AND CLOSE OUT

a. Submit a written statement from the Contractor attesting that the Work is Substantial Complete:

i. The final construction inspection and the related work corrections shall be completed before the end of the period of performance. Prior to expected Substantial Completion, at 75% construction complete or as noted on the construction project schedule, notify the CO and COR. Provide the following:

1. This notification will allow the COR to coordinate with Designer of Record for final construction completion inspection.

2. This notification will allow the COR to coordinate with Operations and Maintenance Staff’s schedules to accommodate Demonstration and System Training.

3. With this notification, the Contractor shall provide the COR a list of items that are incomplete / incorrect. This list of incomplete / incorrect items will allow the Project Team to understand what work remains so that construction inspection findings are not incorrectly identified as a deficiency.

ii. At Substantial Completion, the Contractor shall notify the CO and COR in writing that work is complete and the Contractor has completed their quality control measures.

b. Demonstration that the work is complete

i. The Contractor shall demonstrate the operation of the system(s).

ii. Provide factory startup and certification of all systems.

iii. Newly installed piping and distribution system components shall be flushed and disinfected prior to being placed in service. Include documenting completion

iv. Schedule the demonstration with the COR, 21 days in advance so that the VA Operations and Maintenance staff and the Designer of Record can attend.

v. One demonstration of the correct operation of the system is required. Coordinate for during the day, however if staff and patients are impacted by the demonstration then it shall be scheduled at night or on the weekend.

vi. If the demonstration does not show expected operation, the Contractor shall make required system adjustments and reschedule and retest.

vii. This demonstration is not to be combined with the System Training functional performance testing.

c. System Training

i. Provide a written training plan to the COR for review and approval prior to scheduling the training. Include: a) list of systems, b) list of manufacturers, c) detailed training plans that include operating the equipment and functional performance tests, d) printed copies of the training plans for each trainee, e) list of items that the VA must have complete so that the training and the associated functional performance tests that occur during the training can be coordinated by the VA to minimize impact to Operations and Patient Care

ii. Provide factory personnel for training for all equipment

iii. Provide 4 sessions of training at 2 hour each. Three (3) trainings shall be during the regular business days with one (1) conducted on a Saturday.

1. Provide the COR a training plan 14 day in advance, include lesson plan and material handouts for participants.

2. Provide the COR with a training attendance sheet for each training session.

iv. Schedule the factory training with the COR not less than 21 days in advance.

v. Within 7 days after training is complete, provide and electronic copy of the training attendance sign in sheet as well as electronic copy of the training documents.

d. Closeout Records: Provide three printed sets and three compact discs with electronic files of the following:

i. Plan as built record drawings of the installed condition shall be CAD drawn. Turn over the CAD files (do not bind xrefs), PDF files and the red line field notes to the VA

ii. Approved shop drawings

iii. Operations and Maintenance Manuals

iv. Spare parts listing

Part 5: Applicable Performance Standards

1. All work shall comply with

a. All VA Policies including and not limited to: VA Construction Safety and VA Infection Control Policies.

b. Codes, Standards and Executive Orders (Topic 1) found http://www.cfm.va.gov/til/cPro.asp

2. All persons including subcontractors shall have completed the 30 Hour OSHA Construction Safety Training program.

3. The Prime Contractor shall have a Competent Supervisory Person on site at all times when any worker(s) or sub-contractors are present.

4. All persons working on any electrical systems rated 50 volts or more shall have the minimum qualification as a State Licensed Master Electrician or Registered Journeyman Electrician, all activities shall follow the safe work practices in compliance with NFPA 70E Electrical Safety in the Workplace.

5. The Contractor shall provide mitigating activities as outlined in the CONSTRUCTION SAFETY PRECAUTIONS and CONSTRUCTION INFECTION CONTROL RISK ASSESSMENT / DUST CONTROL PRECAUTIONS including but not less than the following:

a. Fire extinguishers, pedestal mounted in the area of work

b. Walk off dust mats, inside and outside all entry / exit points to the workspace, changed not less than daily or more as required by the construction or COR.

c. Block off all HVAC return ductwork and lovers so not to introduce dust into the HVAC system.

d. Provide a High-Efficiency Particulate Arresting / High-Efficiency Particulate Air Filtration (HEPA) recirculating air equipment inside the construction workspace. Include fire seal the existing openings in area of work needed to allow the HEPA exhaust equipment to make the area of work negative air pressure with respect to the surrounding area.

e. Including monitoring the negative pressure environment for the construction workspace:

i. Before the start of work provide pressure differential gage at the entry door to the construction area to prove that the construction area is under negative pressure. Maintain daily logs of reading and submit to the COR weekly. Remove at the completion of construction.

f. No trash, used packaging, or construction spoils shall be stored on site. Remove each day using covered gondolas.

g. Do not allow corrugated carboard into the surgical suite.

h. Broom sweep the work area at the end of each day. Provide HEPA vacuum and damp mop daily where broom-sweeping creates airborne dust.

6. All work will be provided with one-year parts and labor warranty from date of acceptance by VA.

Part 6: Jesse Brown VAMC Additional Requirements

1. Project number and the contract number in the subject line of all emails.

2. Comply with all Jesse Brown VAMC site-specific requirements and SOPs, including, and not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy.

3. Normal construction work hours are 7:00 AM to 3:30PM Monday through Friday.

a. Normal work hours can be modified only by written approval of the COR.

b. No work by the Contractor on Federal Holidays, and no work on the weekend when the Federal Holiday is on the respective Monday or Friday.

c. Work in stairs, or interior / exterior public areas shall be allowed between 6:00 PM through midnight, concluding by 6:00 AM on the following day.

d. Any work including, and not limited to: Noise, vibration, dust, odors, core drilling, hammer-drilling, saw-cutting, equipment moving in public corridors, soil compaction, or similar noise-producing activities shall be performed between 6:00 PM through midnight, concluding by 6 AM on the following day.

e. Crane lifts, any work that closes drive isles, closes building entries or closes public corridors shall be during low patient time and performed Sundays.

f. The Contractor shall check in (in person) with the Administrative Officer of the Day (AOD) which is located in Patient Admitting for any work between 6:00 PM through midnight to 6:00 AM or any time on weekends. Provide the name and cell number of the on-site supervisor to the AOD. At the completion of the work, check out with the AOD.

4. All building systems will be maintained in full operation at all times:

a. Request system shutdowns in writing not less than 21 calendar days in advance.

b. Shutdown work shall be during low patient demand times, and performed between Saturday 6 PM through midnight, concluding by 6 PM on the following Sunday.

c. All work impacting AHU-5 shall take place following the last surgical case on Friday through Saturday at Midnight.

i. The contractor shall schedule any AHU-5 shutdowns / work with the COR a minimum of 28 days in advance to allow for scheduling OR bypass.

ii. Prior to any work commencing on AHU-5 the contractor shall demonstrate to the COR that all material is available and onsite.

5. Provide uniform heat detection in the area of work, connected to the existing supervised building master fire alarm system, for the duration of the work whenever the: Ceiling tiles are removed, or sprinkler system is disabled.

6. Fire-seal all penetrations through any wall or floor with UL Listed fire-rated materials or assemblies manufactured for the purpose.

7. Deliveries, Parking, Elevators:

a. Deliveries only at the Polk Street dock, and coordinated with the COR. At time of delivery: provide vehicle information to the VA Police and remove the vehicle as soon as delivery is complete. Move materials in public corridors during low patient time and performed between 6 pm through midnight concluding by 6 AM on the following day.

b. No on-site parking or parking in the VA garage. Utilize street parking or other parking structures such as the Cook County Juvenile Parking Garage at their daily rate. The existing JBVAMC parking garage is at capacity and reserved for patients and staff.

c. Contractor shall use Freight Elevators. Do not move materials and employees in passenger elevators unless written approval by COR.

8. Contractor shall provide construction dumpsters with a surrounding safety fence. Pavement to be protected from damage of loading and unloading the dumpster and dumpster weight. Located on the Polk Street Dock. Provide recycling and receipts from the salvage / deposal service in compliance with VA’s GEMS Policy.

9. No on-site office or on-site storage / office container shall be allowed. Provide ‘just-in-time delivery and pickup’. Coordinate with COR for staging within the area of work.

10. No music radios. Two-way communications radios are allowed where broadcast frequency is approved by COR.

11. All work in the JB VAMC crawl spaces shall be planned and carried out as OSHA Permit Required Confined Space.

12. Immediately stop work and notify the COR if asbestos is noticed or suspected in the area of work.

13. Before starting work the Contractor shall give 21 days’ notice to the COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

14. No photography of VA premises is allowed without written permission of the COR.

15. VA reserves the right to close down or shut down the project site, and ask Contractor’s employees to leave the premises in the event of an emergency, or operational requirement. The Contractor may return to the site only with the written approval of the COR.

16. Locks and Keys: Door hardware shall be compatible with Best® 7-pin, F keyway, interchangeable core. Final pinout and keying is provided by the VA. Provide and turn over new blank cores to VA not less than 21 days in advance of construction completion. The final pinout and keying is provided by VA.

17. Exit Signs: All exit signs shall be City of Chicago approved red letters on white edge light LED

18. Sole Source Procurement: The Contractor shall provide fully functional complete systems, however include the following sole source procurements for the following special systems:

a. Building Automation: Components, programming and start up: BACnet communications protocol for Building Automation and Control (BAC) connected to the existing Johnson Controls head end equipment

b. Video Surveillance / Closed Circuit Camera System: Components, programming and start-up: Advent Systems

Page 1 of Page 1 of Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

1.1 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

1.2 52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)

The Contractor shall promptly furnish additional security required to protect the Government and persons supplying labor or materials under this contract if—

(a) Any surety upon any bond, or issuing financial institution for other security, furnished with this contract becomes unacceptable to the Government;

(b) Any surety fails to furnish reports on its financial condition as required by the Government; or

(c) The contract price is increased so that the penal sum of any bond becomes inadequate in the opinion of the Contracting Officer.

(d) An irrevocable letter of credit (ILC) used as security will expire before the end of the period of required security. If the Contractor does not furnish an acceptable extension or replacement ILC, or other acceptable substitute, at least 30 days before an ILC's scheduled expiration, the Contracting officer has the right to immediately draw on the ILC.

(End of Clause)

1.3 52.228-15 PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION (OCT 2010)

(a) Definitions. As used in this clause— "Original contract price" means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of Treasury
Financial Management Service
Surety Bond Branch
3700 East West Highway, Room 6F01
Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

(End of Clause)

1.4 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

When net changes in original contract price affect the premium of a Corporate Surety Bond by $5 or more, the Government, in determining the basis for final settlement, will provide for bond premium adjustment computed at the rate shown in the bond.

(End of Clause)

SUPPLEMENTAL INSURANCE REQUIREMENTS

In accordance with FAR 28.307-2 and FAR 52.228-5, the following minimum coverage shall apply to this contract:

(a) Workers' compensation and employers’ liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.

(b) General Liability: $500,000 per occurrences.

(c) Automobile liability: $200,000 per person; $500,000 per occurrence and $20,000 property damage.

(d) The successful bidder must present to the Contracting Officer, prior to award, evidence of general liability insurance without any exclusionary clauses for asbestos that would void the general liability coverage.

(End of Clause)

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a FIRM-FIXED PRICE contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
19.6%
6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

City of Chicago
County of Cook
State of Illinois

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Hand-Carried Address:
Contracting Officer
Great Lakes Acquisition Center
3001 Green Bay Road
Building 1, Room 329
North Chicago, IL 60064
Mailing Address:
Contracting Officer
Great Lakes Acquisition Center
3001 Green Bay Road
Building 1, Room 329
North Chicago, IL 60064

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.6 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— March 7, 2019 at 9:00 am CST

(c) Participants will meet at—

Department of Veterans Affairs
Jesse Brown VA Medical Center
820 S. Damen Avenue
Taylor Street Entrance
Engineering Suite – Conference Room 3295

(End of Provision)

2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer.

This is the start of the file's text. The full file is on GovTribe.