36C25218B0688-00001000.docx

DOCX document 28 KB Posted

Attached to
B98 Exterior Ductwork Insulation, 550-16-103 Federal contract opportunity
Solicitation number
36C25218B0688
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

36C25218B0688 00001 36C25218B0688 00001.docx

View the file

Other files for this federal contract opportunity

Other files attached to B98 Exterior Ductwork Insulation, 550-16-103, newest first.
File Type Posted
36C25218C0177-000.docx DOCX document
36C25218B0688-00001001.pdf PDF
36C25218B0688-005.pdf PDF
36C25218B0688-004.pdf PDF
36C25218B0688-002.docx DOCX document
36C25218B0688-003.pdf PDF
36C25218B0688-001.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2.

AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF

CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV.

11/2016) is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR

43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS

ENTERED INTO

PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14.

DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME

AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS

OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 00001 05-07-2018 550-18-3-6985-0183 550-16-103 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 3001 Green Bay Road Building 1, Room 329 North Chicago IL 60064-3048 To all Offerors/Bidders

36C25218B0688 05-07-2018

X X X 550-3680162-6985-854200-2580

23NRNR003

X

Building 98 Exterior Ductwork Insulation

The purpose of this amendment is to answer RFI questions.

See CONTINUATION PAGE

All other terms and conditions remain unchanged.

CONTINUATION PAGE

AMENDMENT 00001

The following questions and responses represent all questions submitted to the Contracting Officer regarding Solicitation 36C25218B0688 by the 20 April 2018, 5:00 pm CST deadline.

Q1. Can the VA provide a copy of the pre-bid meeting sign in sheet?

A1. Yes, attached.

Q2. Does the roof have a warranty and can the VA provide the roofing company contact information?

A2. No warranty. Sentry Roofing (Covington, IN) has been used for repairs on the roof membrane.

Q3. What is the height of Bldg. 98?

A3. Thirty (38) feet to the top of the roof slab. Fifty-three (53) feet to the top of the penthouse.

Q4. Lighting [sic] protection must be removed and re-installed following completion of the work on the duct and piping insulation. Is re-certification of the lightning protection system required?

A4. Yes.

Q5. Are there any existing utilities buried below grade that would prohibit the use of lifts in the grassy areas at the back of the building?

A5. North of the covered walkway, there is an underground fuel tank. It is well marked. Keep lift vehicle at least eight (8) feet from this fuel tank. South of the covered walkway there is a sewer manhole. Keep lift vehicle six (6) feet from this manhole.

Q6. Can lifts be used to work overhead of the covered walkway during normal working hours?

If yes, will the covered walkway have to be scheduled for closures? If yes, how many days’ notice is required for closures? If no, will work above the covered walkways have to be done after hours?

A6. Lifts may be used above the covered walkway. No closure is necessary. No restriction on hours due to the covered walkway.

Q7. May we have access to the fence in area on southeast side of building 98 for installation of trash chute to drop removed material from roof area to ground level?

A7. No.

Q8. Scope statement of work I.E. calls for 2” Polyiso Board Insulation installed in two 1” layers on all SA and RA duct. Is the double layers construction necessary? Could we install one 2” layer? This double layer installation cost is considerably more due to labor days of installation with limited benefit due to the relative low Delta T of this system.

A8. Yes, double layer construction is necessary. No, you cannot install one 2” layer.

Q9. Can we have a dumpster set on the east side of the building next to the ambulance dock and in between the fence of the existing AHU units? The VA let the contractor set it there on a previous job in Building 98.

A9. Dumpster must be outside of the fencing. It may be placed on the grass, just north of the ambulance dock. An alternate dumpster location is just north of the covered walkway, on the grass. Any resulting ruts or damage to the grass must be repaired.

10. There will be need for boom lift to do this project. [sic] Is a fence in area required to do this? You have parking spots back there now for some of the VA employees. You have a dock for the delivery that I am sure will need to be kept open.

A10. Yes, the boom lift needs to be fenced off while operating to protect the general public.

Q11. Who is responsible for removing and replacement of electrical conduit and equipment associated with existing ductwork?

A11. The Contractor is responsible.

Q12. Who is responsible for removing and replacement of the lightning arrestor system associated with the existing ductwork?

A12. The Contractor is responsible.

Q13. Will articulating boom lifts be allowed on the NE and SE grass areas?

A13. An articulating boom lift can be placed in three locations: (1) At the loading dock. (2) Outside of the fence, north of the ambulance dock. This would mean a lift over the fenced area. Keep lift vehicle six (6) feet from the sewer manhole in this area. (3) Just north of the covered walkway on the grass, no closer than eight (8) feet to the buried fuel tank. Any resulting ruts or damage to the grass must be repaired.

Q14. Is there a link I can go to in order to access/order plans for the above-mentioned project?

A14. Please visit www.fbo.gov to download a copy of the solicitation and supporting documents.

Q15. Is there an incumbent contractor currently performing these services or is this a new requirement? If there is an incumbent, could you please provide the contract number?

A15. This is a new requirement; there is no incumbent.

Q16. Regarding the electrical trace for the chilled water piping, will this be a single straight line trace or a multiple line trace?

A16. Due to the size of the chilled water lines (8” diameter & 5” diameter), multiple line electrical trace is required to properly freeze protect the lines.

See attached document: Site Visit_B98 Ext Ductwork.

(End of Amendment 00001)