36C24818Q0839-0003002.pdf

PDF 207 KB Posted

Attached to
Switchgear NiCad Battery Replacement Federal contract opportunity
Solicitation number
36C24818Q0839
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

36C24818Q0839 0003 Questions and Answers - 2.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Switchgear NiCad Battery Replacement, newest first.
File Type Posted
36C24818Q0839-0003000.docx DOCX document
36C24818Q0839-0003001.pdf PDF
36C24818Q0839-0002003.pdf PDF
36C24818Q0839-0002002.pdf PDF
36C24818Q0839-0002000.docx DOCX document
36C24818Q0839-0002001.pdf PDF
36C24818Q0839-0001004.docx DOCX document
36C24818Q0839-0001005.pdf PDF
36C24818Q0839-0001002.pdf PDF
36C24818Q0839-0001000.docx DOCX document
36C24818Q0839-0001001.pdf PDF
36C24818Q0839-0001003.pdf PDF
36C24818Q0839-001.pdf PDF
36C24818Q0839-000.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers – 36C24818Q0839 # 2

Question No 1: Is there a pallet jack on site available?

Answer: Yes.

Question No 2: How far into the building does this need to go?

Answer: An estimate as short as 20 feet to 200 feet between several doors of varying size. There are 4 racks of 96 batteries each in 4 different of the electrical utility/switchgear location of the CEP.

Question No. 3: How many doors does this have to go through (door and hallway widths and how many)

Answer: Including the entrance and the doors leading to the battery racks, between 3 and 4 doors total. Doors width range from 33” to 70” and hallways are wider.

Question No. 4: Does this need to go to different floor? If so, what floor?

Answer: Ground level.

Question No. 5: Is there a freight elevator on site?

Answer: N/A

Question No. 6: Does the floor need to be coo red (sic) by Masonite or plywood?

Answer: No.

Question No. 7: Can the items stay on the pallet? If no, are there specific requirements for getting the times to the UPS Room?

Answer: No to the first part of the question and do not understand the second part.

Question No. 8: Is a temporary battery required during changeout of the switchgear?

Answer: Brought to the room, yes. Stacked, no.

Question No. 9: Do t he (sic) pallets need to be taken off site when they are unloaded?

Answer: Yes.

Question No. 10: How long can batteries sit until disposal?

Answer: They need to be removed immediately.

Question No. 11: Where can batteries be stored for disposal?

Answer: They need to be removed immediately.

Question No 12: What does CEP stand mean?

Answer: Central Energy Plant.