36C24619Q1101-001.pdf

PDF Posted

Attached to
Resurface Catwalk Railing Surfaces Federal contract opportunity
Solicitation number
36C24619Q1101
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

36C24619Q1101 S02. SF1442 36C24619Q1101(FE).pdf

View the file

Other files for this federal contract opportunity

Other files attached to Resurface Catwalk Railing Surfaces, newest first.
File Type Posted
-18473.docx DOCX document
36C24619Q1101-0001000.docx DOCX document
36C24619Q1101-0001000.docx DOCX document
36C24619Q1101-002.pdf PDF
36C24619Q1101-003.pdf PDF
36C24619Q1101-004.pdf PDF
36C24619Q1101-005.pdf PDF
36C24619Q1101-001.pdf PDF
36C24619Q1101-004.pdf PDF
36C24619Q1101-003.pdf PDF
36C24619Q1101-002.pdf PDF
36C24619Q1101-005.pdf PDF
36C24619Q1101 36C24619Q1101.docx DOCX document
36C24619Q1101-000.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

{TC " SOLICITATION/CONTRACT FORM" \l 1}{TC "1.1 SF 1442 SOLICITATION, OFFER, AND

AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)" \l 2}

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________

(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 32

36C24619Q1101

08-28-2019

652-19-111

Department of Veterans Affairs

Network Contracting Office 6

100 Emancipation Drive

Hampton VA 23667

100 Emancipation Drive

Hampton VA 23667

Nicholas J Ruppert 757-726-6084

Request for Quote: Resurface Catwalk Railing Railing Surfaces

Hunter Holmes McGuire VA Medical Center, Richmond VA

See Statement of Work for details

Magnitude of Construction: Between $100,000 and $250,000

This is a Total SB Set-Aside

NAICS: 236350 | Size Standard: $15.0 Million

Contractors must be registered in the System for Award Management (https://www.sam.gov/SAM/) to be eligible

A Site Visit will be conducted on Wednesday, September 4, 2019 at 10:00 AM EST

Location: Hunter Holmes McGuire VA Medical Center

Bldg 500, 2nd Floor Room 2K-136

1201 Broad Rock Blvd

Richmond, VA 23249

Questions are due no later than Thursday, September 5, 2019 at 5:00 PM EST via email at Nicholas.Ruppert@va.gov

Quotes are due no later than Monday, September 3, 2019 at 3:00 PM EST

15 90

X X FAR 52.211-10

X N/A

1 3:00 PM EST

09-09-2019

X

{TC "1.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR

REPAIR)– BACK " \l 2}

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your

Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

LINE ITEM 0001: Contractor shall provide all labor, materials, tools, equipment, and supervision to perform all operations necessary to complete Project 652-19-111 in accordance with the Statement of Work.

100 Emancipation Drive

Hampton VA 23667

Financial Services Center

PO BOX 149971

Austin TX 78714-9971

Table of Contents

SOLICITATION/CONTRACT FORM

1.1 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION,

OR REPAIR)

1.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION,

OR REPAIR)– BACK

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

1.3 SCOPE OF WORK

1.4 PRICE/COST SCHEDULE

ITEM INFORMATION

1.5 WAGE DETERMINATION

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BASIS FOR AWARD

2.2 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF

THE WORK (MAY 2014)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

2.5 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-

OWNED SMALL BUSINESS EVALUATION FACTORS (JUL 2016)(DEVIATION)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)

GENERAL CONDITIONS

4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR

1984)

4.3 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011)

4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL

2013)

4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

4.6 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.7 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (DEC 2009)

4.8 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND

COMPLIANCE (JUL 2018)

4.9 VAAR 852.219-75 SUBCONTRACTING COMMITMENTS MONITORING AND

COMPLIANCE (JUL 2018)

4.10 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)

4.11 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.12 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

4.13 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)

4.14 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (APR 2019)

4.15 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) .. 31

CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

1.3 SCOPE OF WORK

Project Name – Resurface Catwalk Railing Surfaces

Project # 652-19-111

Overview: Fabrication and Installation of railing over caps with bench removal and replacement along the catwalk on the 2nd floor overlooking the mall area. All work accomplished IAW provided drawings as well as following specific guidelines for hospital listed standards of material quality, composition and appearance. Work must be accomplished IAW space availability scheduled during off peak hours, when walkway can be infringed upon foot traffic. https://www.cfm.va.gov/TIL/sDetail.asp

Scope of Work: Contractor to measure, order, and install railing over caps along the Catwalk of the second floor. Contractor is also to demolish old benches and back boards in 3 seating areas replacing with materials that meet or exceed requirements listed below. Contractor shall provide all labor, materials, tools, equipment, and supervision to perform all operations necessary to complete this project. All work and installation of all materials shall be completed in strict accordance with the SOW and provided drawings for the functions necessary within the Richmond VAMC areas. This equipment and work must meet or exceed the General Requirements for VAMC operations with considerations for employees and patients with all forms of mobility in the hospital.

All seams should line up with existing separations. In accordance with (IAW) scope of work (SOW) and drawings- all gray colored, non-solid surface material must be covered with new specified solid surface material and color.

the 3 seated areas along corridor C2H-9 are to be included, however along corridor C2A-7 that seating is to be removed by in house shops prior to installation of caps (matching the rest of caps for a uniform appearance).

The inaccessible smaller strip of railing/countertop across the food court is blocked off above the store near the bank that is not indicated in drawings provided with project is not included.

The drywall behind the backboard to be replaced when tearing out/replacing the backboard Only if damaged- all materials and surfaces impacted around benches and railings are to be at highest Hospital quality upon completion.

The benches are the corner guards to be replaced Only if damaged- all materials and surfaces impacted around benches and railings are to be at highest Hospital quality upon completion. There are no inside corner guards.

The new material to match the old, to be Corian, Wilsonart exactly as currently installed. At the benches, are the tops to be replaced IAW provided drawings and SOW

The benches are the outside portions on either side of the benches, where they butt up against the railing/countertops to be replaced only if damaged- all materials and surfaces impacted around benches and railings are to be at highest Hospital quality upon completion. The benches, are the new backs to match the existing layout (12”) https://www.cfm.va.gov/TIL/sDetail.asp

General Requirements Items:

Contractors Fabricating or Installing any products to be used at the VA Hospital are required to have the following for potential continuing maintenance/warranty of products installed:

a. Warranty Maintenance- Company facility must be within 20 miles of the McGuire Richmond

VA Hospital campus.

b. Seeking companies experienced in solid surface counter type installations in a hospital setting.

The catwalk Railing Cap and benches installation materials to be provided by the contractor are to meet or exceed the items that include but may not be limited to the following items listed below:

Completion Time: Contractor will have 90 days from notice to proceed to complete entirety of the

Contract, installation is anticipated to take no more than 3 days accomplished during off peak hours IAW hospital function and Catwalk availability.

Additional notes:

Contractor shall field verify all measurements, material quantities, and site conditions prior to submitting a bid.

Contractor is responsible for maintaining building life safety standards prescribed through an “Interim Life

Safety Measure risk assessment” permit with requirements, that is issued prior to any work beginning.

Contractor is responsible for dust control during construction and while hauling operations when traversing through the medical center. Contractor shall comply with Infection Control Risk Assessment permit requirements issued prior to any work beginning.

Provide submittals and samples for all finish materials depicting actual texture samples for approval.

Contractor shall provide 3 hard copies of each submittal with a separate transmittal sheet to each requirement. If applicable, submittals shall indicate the manufacturer’s full range of available colors, and from these, the COR will request full size samples for final color selection.

Contractor shall coordinate with COR for waste removal. All waste shall be removed at the end of each day. Contractor shall remove and dispose of waste in accordance with all legal and VA Specification 01 74

19 Construction Waste Management.

Line Qty Part Description ft

Corian solid surface- Fossil assembled approximately- 14” wide w/2 legs

7 ½” tall cut to fit in openings along Catwalk ft

Corian solid surface- Fossil assembled approximately 9 ¼” wide w/2 legs

2 ¾” tall cut to fit on benches along Catwalk ea

Adhesive as required for affixing Corian to existing surface

Sq/ft

Wilsonart/7909-60/Fusion Maple varying widths and lengths specific to each individual bench.

ea

Adhesive as required for affixing Fusion Maple Laminate to seating areas

All contractors shall complete safety training with Richmond VAMC Safety team prior to work beginning.

Contractor must comply with all requirements of VA Specification 01 35 26 Safety Requirements

Contractor shall store all materials offsite and only bring materials to be installed the same day to the project site. Contractor shall coordinate delivery, storage, and handling of all materials with the COR to designated prepared areas to minimize site storage time, impact to the hospital, and potential damage to stored materials, unless project has a specified lay down area.

Contractor shall protect all existing equipment, utilities, structures, etc. to remain. When the space is turned over to the contractor, the contractor will be responsible for repairing all damage within the construction site. If any damage is noticed prior to starting work that may be misconstrued as damage caused by the contractor, the COR shall be notified immediately, and the damage documented as existing prior to beginning demolition. Contractor is responsible for removing, storing and reinstalling any wall mounted items.

Contractor shall perform a pre-final inspection before requesting the final inspection with the COR and include time in their work plan for inspections and to repair any defective work after the final inspection has been made.

All contractors are required to be safety trained by VA Safety department prior to commencement of work.

Contractors are also required to minimally have an OSHA 10 Hour certificate within the last two years.

1.4 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBE

R

DESCRIPTION OF

SUPPLIES/SERVIC

ES

QUANTIT

Y

UNI

T UNIT PRICE AMOUNT

0001 1.00 JB ________________

Contractor shall provide all labor, materials, tools, equipment, and supervision to perform all operations necessary to complete project

652-19-111. All work shall be completed in strict accordance with

SOW, to include final clean up and completion of any punch list items.

GRAND TOTAL ________________

1.5 WAGE DETERMINATION

The DOL Wage Determination for the specific locality applies to this solicitation and any contract awarded is available at https://beta.sam.gov/. Please note the listing below is not all inclusive wage determination of each area of performance. It is the contractor’s responsible to obtain and evaluate each wage determination locality.

Wage Determination No.: VA20190166 as of 8/30/2019 https://beta.sam.gov/

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

2.1 BASIS FOR AWARD

This solicitation is issued IAW FAR Part 13 and will be evaluated IAW FAR 13.106-2. The contracting officer shall make a contract award by written or electronic notice within the time for acceptance specified in the request for quote to that responsible offeror, whose quote conforms to the technical capabilities of the solicitation, and will be most advantageous to the Government, considering only price. Award shall not be made until all required approvals have been obtained and the award otherwise conforms with the technical requirements of the solicitation.

Price. All CLIN items to include base and alternates in the Price Schedule must include a price, to include

Offerors cost breakdown in sufficient detail, to permit a complete analysis of labor, burden, materials, equipment, transportation, supervision, and disposal. The total evaluated price will consist of the offeror’s proposed price and the government’s independent cost estimate. The Government may determine that an offer is technically acceptable; however, the prices are significantly unbalanced. Price reasonableness will be performed by the Contracting Officer.

2.2 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE

(FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

FAR

Number

Title Date

52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE

REPORTING

JUL 2016

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO

ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR

CONSTRUCTION

FEB 1999

52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE I (FEB 1995) FEB 1995

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY

SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate

Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the

Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—

CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition

Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph

(b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND

VETERAN-OWNED SMALL BUSINESS EVALUATION FACTORS (JUL

2016)(DEVIATION)

(a) In an effort to achieve socioeconomic small business goals, depending on the evaluation factors included in the solicitation, VA shall evaluate offerors based on their service-disabled veteran-owned or veteran-owned small business status and their proposed use of eligible service-disabled veteran-owned small businesses and veteran-owned small businesses as subcontractors.

(b) Eligible service-disabled veteran-owned offerors will receive full credit, and offerors qualifying as veteran-owned small businesses will receive partial credit for the Service-Disabled Veteran-Owned and

Veteran-owned Small Business Status evaluation factor. To receive credit, an offeror must be registered and verified in Vendor Information Pages (VIP) database (https://www.vip.vetbiz.gov).

(c) Non-veteran offerors proposing to use service-disabled veteran-owned small businesses or veteran-owned small businesses as subcontractors will receive some consideration under this evaluation factor.

Offerors must state in their proposals the names of the SDVOSBs and VOSBs with whom they intend to subcontract and provide a brief description of the proposed subcontracts and the approximate dollar values of the proposed subcontracts. In addition, the proposed subcontractors must be registered and verified in the VetBiz.gov VIP database (https://www.vip.vetbiz.gov).

https://www.vip.vetbiz.gov/ https://www.vip.vetbiz.gov/

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT

2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238350.

(2) The small business size standard is $15 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal

Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality

Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony

Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the

Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast

Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative

Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--

Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate

I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate

II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its

Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification.

This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or

Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for

Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for

Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-

Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below

[offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause # Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

https://www.sam.gov/

GENERAL CONDITIONS

4.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

FAR

Number

Title Date

52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL

CONFIDENTIALITY AGREEMENTS OR STATEMENTS

JAN 2017

52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR

PERSONNEL

JAN 2011

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-

TIER SUBCONTRACT AWARDS

OCT 2018

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018

52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE

MAINTENANCE

JUL 2016

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS

AND CERTIFICATIONS

DEC 2014

52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE,

SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED

BY KASPERSKY LAB AND OTHER COVERED ENTITIES

JUL 2018

52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN

TELECOMMUNICATIONS AND VIDEO SERVEILLANCE

SERVICES OR EQUIPMENT

AUG 2019

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN

SUBCONTRACTING WITH CONTRACTORS DEBARRED,

SUSPENDED, OR PROPOSED FOR DEBARMENT

OCT 2015

52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED

DOMESTIC CORPORATIONS

NOV 2015

52.213-4 TERMS AND CONDITIONS—SIMPLIFIED ACQUISITIONS

(OTHER THAN COMMERCIAL ITEMS)

JAN 2019

52.222-3 CONVICT LABOR JUN 2003

52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS AUG 2018

52.222-7 WITHHOLDING OF FUNDS MAY 2014

52.222-8 PAYROLLS AND BASIC RECORDS AUG 2018

52.222-9 APPRENTICES AND TRAINEES JUL 2005

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988

52.222-11 SUBCONTRACTS (LABOR STANDARDS) MAY 2014

52.222-12 CONTRACT TERMINATION—DEBARMENT MAY 2014

52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE

REQUIREMENTS AND RELATED REGULATIONS

MAY 2014

52.222-14 DISPUTES CONCERNING LABOR STANDARDS FEB 1988

52.222-15 CERTIFICATION OF ELIGIBILITY MAY 2014

52.222-21 PROHIBITION OF SEGREGATED FACILITIES APR 2015

52.222-26 EQUAL OPPORTUNITY SEP 2016

52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS

FOR CONSTRUCTION

APR 2015

52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES JUL 2014

52.222-50 COMBATING TRAFFICKING IN PERSONS JAN 2019

52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 DEC 2015

52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 JAN 2017

52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW

INFORMATION

MAY 2011

52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT

MESSAGING WHILE DRIVING

AUG 2011

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES JUN 2008

52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS DEC 2007

52.228-13 ALTERNATIVE PAYMENT PROTECTIONS JUL 2008

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS

MAY 2014

52.232-23 ASSIGNMENT OF CLAIMS MAY 2014

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS JAN 2017

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM

FOR AWARD MANAGEMENT

OCT 2018

52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS JUN 2013

52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL

BUSINESS SUBCONTRACTORS

DEC 2013

52.233-1 DISPUTES MAY 2014

52.233-3 PROTEST AFTER AWARD AUG 1996

52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM OCT 2004

52.236-2 DIFFERING SITE CONDITIONS APR 1984

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE

WORK

APR 1984

52.236-5 MATERIAL AND WORKMANSHIP APR 1984

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984

52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991

52.236-8 OTHER CONTRACTS APR 1984

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,

EQUIPMENT, UTILITIES, AND IMPROVEMENTS

APR 1984

52.236-10 OPERATIONS AND STORAGE AREAS APR 1984

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984

52.236-12 CLEANING UP APR 1984

52.236-13 ACCIDENT PREVENTION NOV 1991

52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES APR 1984

52.236-17 LAYOUT OF WORK APR 1984

52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995

52.242-14 SUSPENSION OF WORK APR 1984

52.243-5 CHANGES AND CHANGED CONDITIONS APR 1984

52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS JAN 2019

52.246-12 INSPECTION OF CONSTRUCTION AUG 1996

52.246-21 WARRANTY OF CONSTRUCTION MAR 1994

52.249-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT

(FIXED-PRICE) (SHORT FORM)

APR 1984

52.253-1 COMPUTER GENERATED FORMS JAN 1991

(End of Clause)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days after notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

4.3 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011)

As prescribed in 19.508(c), insert the following clause:

Notice of Total Small Business Set-Aside (Nov 2011)

(a) Definition. “Small business concern,” as used in this clause, means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on

Government contracts, and qualified as a small business under the size standards in this solicitation.

(b) Applicability. This clause applies only to-

(1) Contracts that have been totally set aside or reserved for small business concerns; and

(2) Orders set aside for small business concerns under multiple-award contracts as described in

8.405-5 and 16.505(b)(2)(i)(F).

(c) General.

(1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.

(2) Any award resulting from this solicitation will be made to a small business concern.

(d) Agreement. A small business concern submitting an offer in its own name shall furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United

States or its outlying areas. If this procurement is processed under simplified acquisition procedures and the total amount of this contract does not exceed $25,000, a small business concern may furnish the product of any domestic firm. This paragraph does not apply to construction or service contracts.

(End of clause)

4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM

REREPRESENTATION (JUL 2013)

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to

Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate https://www.acquisition.gov/content/19508-solicitation-provisions-and-contract-clauses#i1100931 factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the

Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and

Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code 238350 assigned to contract number .

[Contractor to sign and date and insert authorized signer's name and title].

http://www.sba.gov/content/table-small-business-size-standards

Name: Date:

Title:

Signature:

(End of Clause)

4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause—

"Commercially available off-the-shelf (COTS) item"—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Component" means any article, material, or supply incorporated directly into construction material.

"Construction material" means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

"Cost of components" means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

"Domestic construction material" means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

No excepted materials

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the

Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the

Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting

Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is…

This is the start of the file's text. The full file is on GovTribe.