S02 Amd 36C24422B0007 0001 6c (2).docx
DOCX document 27 KB Posted
- Attached to
- Z2DA--693-17-101 Replace Wall Tile in Stairwells Federal contract opportunity
- Solicitation number
- 36C24422B0007
About this file
This document provides details on a federal contract opportunity for stairwell wall tile repair work at the Department of Veterans Affairs Medical Center in Wilkes-Barre, Pennsylvania. The scope of work involves removing and replacing sections of wall tile on two stairwells and includes patching, spackling, and painting associated ceiling areas. The work must follow all applicable federal, state, and local codes and regulations and will be performed between 8:00AM and 4:30PM on weekdays excluding holidays. The contract is valued between $250,000 and $5,000,000 and has a performance period of approximately 180 calendar days. This opportunity is open only to service-disabled veteran-owned small businesses with active registrations in the System for Award Management and Vendor Information Pages. The NAICS code is 236220 and the small business size standard is $39.5 million. A pre-proposal site visit will be held within two weeks of solicitation issuance. The solicitation will post on or around July 25, 2022 and questions can be directed to the named contracting officer.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C24422B0007 0001.docx | DOCX document | |
| S02 Solicitation 36C24422B0007.docx | DOCX document | |
| S02 SafetyHealthDuringConstruction 18S-15-346.pdf | ||
| 36C24422B0007.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 693-17-101 00244 Department of Veterans Affairs Network Contracting Office 4 Wilkes-Barre VAMC Acquisitions (049E) 1111 East End Blvd Wilkes-Barre PA 18711 00244 Department of Veterans Affairs Network Contracting Office 4 Wilkes-Barre VAMC Acquisitions (049E) 1111 East End Blvd Wilkes-Barre PA 18711 To all Offerors/Bidders
36C24422B0007 08-17-2022
X X X
X This amendment is issued to provide Q&A information as a result of the site visit on 8/31/22.
Scot Plank Contracting Officer
Q & A for Replace Stairwell Tiles
1. Please confirm that only Stairwells #1 and #2 are within the Scope of Work. Yes, the work is only in stairwell 1&2.
1. Please confirm that only (1) Stairwell can be under Construction at a time. You can only work on 1 stairwell at a time.
1. How many Floors can be under Construction, concurrently? You can have 2 floors shutdown at one time.
1. Please confirm the Floor signage needs to be replaced in-kind. This would pertain to only the Floors under Construction. Yes, replace the wall signal with the SAME color and style.
1. The only ceiling that receives paint would be Stairwell #2, Floor 10? Stairwell #1 & #2 floor 10 will receive patch and paint on the ceilings.
6. Please confirm what Floor per Stairwell may be used to remove all debris.
Correction: All debris should be removed at the exit to outside, that is 1st floor outside exit.
End of Document