36C24419B0041-001.docx

DOCX document 118 KB Posted

Attached to
Curb and Sidewalk Replacement Project No. 542-19-112 Federal contract opportunity
Solicitation number
36C24419B0041
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

36C24419B0041 36C24419B0041.docx

View the file

Other files for this federal contract opportunity

Other files attached to Curb and Sidewalk Replacement Project No. 542-19-112, newest first.
File Type Posted
36C24419C0171-000.docx DOCX document
36C24419B0041-002.pdf PDF
36C24419B0041-004.pdf PDF
36C24419B0041-005.pdf PDF
36C24419B0041-003.pdf PDF
36C24419B0041-000.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24419B0041 X 06-11-2019 542-19-3-5306-0059 542-19-112 36C244 Department of Veterans Affairs Network Contracting Office 4 Construction East 1700 S. Lincoln Ave.

Lebanon PA 17042 Department of Veterans Affairs Network Contracting Office 4 Construction East 1700 S. Lincoln Ave.

Lebanon PA 17042 Lev Stowe | Lev.Stowe@va.gov (717)304-9291 Curb and Sidewalk Replacement, Project No. 542-19-112

This project shall generally consist of, but is not limited to; Providing all labor, supplies, transportation, and equipment required to construct new sidewalks, curbs, gutter curbs, accessible ramps, handrails, steps, slopes, and landscaping at the Coatesville VA Medical Center (CVAMC) in accordance with the Statement of Work, the solicitation attachments, and while remaining in compliance with all applicable Federal, State, and local codes.

This solicitation is issued under the authority of 38 U.S.C. 8127, Total Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside. As such, this project is 100% set-aside for SDVOSB concerns. Bidders must be verified as SDVOSB per the Center for Veterans Enterprises (CVE) www.vetbiz.gov website.

The magnitude of construction is between $100,000 and $250,000.

The small business size standard is $36.5 million. The North American Industry Classification System (NAICS) code is 236220.

All documents for this solicitation will be available on the FedBizOpps website http://www.fedbizopps.gov. It is the responsibility of the contractor to check this website frequently for updates and amendments to this solicitation.

Instructions To Bidders: Details on Page 10.

Questions regarding the solicitation: Details on Page 10.

Site Visit: Details on Page 15.

This procurement is conducted under FAR 36 & 13 under Simplified Acquisition Procedures.

X X 52.211-10 X 10:00 AM (Local) 06-26-2019 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

**SEE COST/PRICE SCHEDULE** PAGE 5

36C244 Department of Veterans Affairs Network Contracting Office 4 Construction East 1700 S. Lincoln Ave.

Lebanon PA 17042 Austin Payment Center Department of Veterans Affairs PO Box 149971 Austin TX 78714-9971

(877) 353-9791

(512) 460-5429 X Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
COST/PRICE SCHEDULE5
STATEMENT OF WORK6
INFORMATION REGARDING BIDDING MATERIAL, SITE VISIT, GENERAL INFORMATION, AND GENERAL REQUIREMENTS10
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS14
2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)14
2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) ALTERNATE I (MAY 2014)14
2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)15
2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)15
REPRESENTATIONS AND CERTIFICATIONS17
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)17
GENERAL CONDITIONS21
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)21
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)22
4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)22
4.4 52.223-20 AEROSOLS (JUN 2016)24
4.5 52.223-21 FOAMS (JUN 2016)24
4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)25
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)28
4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)30
4.9 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)30
4.10 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)31
4.11 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)32
4.12 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)32
4.13 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)35
4.14 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)36
4.15 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)37
4.16 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)38
4.17 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)38
4.18 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)38
4.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)41
4.20 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018)41
4.21 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)41
4.22 LIST OF ATTACHMENTS42
4.23 CONSTRUCTION WAGE RATE REQUIREMENTS STATUTE42

COST/PRICE SCHEDULE

A. BASE BID: Statement of Work located on Page 6.

ITEM I, BASE BID: The contractor shall Provide all labor, supplies, transportation, and equipment required to construct new sidewalks, curbs, gutter curbs, accessible ramps, handrails, steps, slopes, and landscaping at the Coatesville VA Medical Center (CVAMC) in accordance with the Statement of Work, the solicitation attachments, and while remaining in compliance with all applicable Federal, State, and local codes. Attachment A – Drawings, Attachment B – Specifications, Attachment C – Safety and Health During Construction – VHA Directive 7715, and Attachment D – CVAMC Campus Map – Areas 1 – 7, are attached for reference.

LUMP SUM BASE BID: $ _____________________________

Write bid amount in words

STATEMENT OF WORK

FOR

CURB AND SIDEWALK REPLACEMENT

PROJECT NO. 542-19-112

COATESVILLE VA MEDICAL CENTER

DESCRIPTION:

This project includes all necessary work associated with the construction of new sidewalks, curbs, gutter curbs, accessible ramps, handrails, steps, slopes, and landscaping for the Coatesville VA Medical Center, at various locations throughout the facility. The contractor shall comply with the Department of Veteran’s Affairs (VA) performance requirements listed herein, as well as all applicable Federal, State, and local codes.

PLACE OF PERFORMANCE:

The Coatesville VA Medical Center (CVAMC) - 1400 Blackhorse Hill Rd, Coatesville, PA 19320;

1) Area 1 will be located outside Building 138, with a walk way size of approximately 12’x 20’ and a curb size of approximately 25’x 2’. The type of work done in this area will include installation of new sidewalk, gutter curb, accessible ramp, truncated dome and landscaping.

2) Area 2 will be located outside Building 138, will involve two walk ways sized approximately 23’ x 19’ and 52’ x 9’, as well as a curb size of 25’ x 2’. The type of work involved in this area will include installation of sidewalk, gutter curb and landscaping.

3) Area 3 will be located outside Building 57, with a walk way size of approximately 58’ x 5’. The type of work involved in this area will include sidewalk, reinstall hand rail, slopes and landscaping.

4) Area 4 will be located outside Building 38, with a walk way size of approximately 32’ x 6’. The type of work involved in this area will include a sidewalk and landscaping.

5) Area 5 will be located outside Building 9, with a walk way size of approximately 72’ x 6’ and a curb size of approximately 48’ x 8”. The type of work involved in this area will include a sidewalk, curb and landscaping.

6) Area 6 will be located outside Building 8, with a walk way size of approximately 120’ x 6’. The type of work involved in this area will include a sidewalk and landscaping.

7) Area 7 will be located outside Building 10, with a walk way size of approximately 14’ x 6’, as well as a curb size of approximately 7’ x 18”. The type of work involved in this area will include sidewalk, steps, reinstall handrail, accessible ramps, truncated dome and landscaping.

PERFORMANCE REQUIREMENTS:

The contractor shall provide all labor, supplies, transportation, and equipment required to construct new sidewalks, curbs, gutter curbs, accessible ramps, handrails, steps, slopes, and landscaping at the Coatesville VA Medical Center (CVAMC) in accordance with the Statement of Work, the attachments provided, and while remaining in compliance with all applicable Federal, State, and local codes.

A. Attachments List:

· Attachment A – Drawings

· Attachment B – Master Construction Specifications

· Attachment C – Safety and Health During Construction – VHA Directive 7715

· Attachment D - CVAMC Campus Map - Areas 1 – 7

B. Construction:

1) The contractor shall provide the following in accordance with attachments; A, B, C, and D. Work will include, but is not limited to;

a. Sidewalks that present a safety hazard due to any of the following: heaved, cracked, depressions, missing sections and/or drop-offs along the sides; will be replaced.

b. Curbs that are either; missing, cracked, or are not in compliance with pedestrians with disabilities when transitioning to asphalt will be replaced. American with Disabilities Act (ADA) tactile warning signs will be installed at curb ramps which meet with asphalt roads.

c. Sidewalks which exhibit a slope greater than 1:12, and 8.33%, must be redesigned to meet a slope of 1:12 (8.33%) in accordance with federal, state, and local regulations to comply with handicap accessibility.

d. Handrails and Accessible Ramps will be reinstalled in accordance with Federal, State, and local regulations to comply with handicap accessibility.

C. Contractor’s Responsibilities:

1) The contractor is responsible for verifying all site conditions prior to performing any work under this contract, and follow all guidelines and standards, applicable to the task, as described in the Construction Safety Standards and Master Construction Specifications.

2) Before opening any excavation for repairing slopes of sidewalks, it is the contractor’s responsibility to verify the existence of underground utilities prior to excavation. As-built drawings are available for review, however, the contractor shall not rely on drawings as sole source of locating underground utilities.

3) Contractor shall verify all site dimensions prior to demolition and construction.

4) The contractor is responsible for submitting a list of parts and materials to the COR for approval prior to use.

5) The contractor is responsible for protecting adjacent structures, equipment, vehicles, pedestrians, and vegetation while performing under this contract.

6) The contractor is responsible for replacing concrete walkways that were removed, disrupted, or damaged during this project. This includes all grounds, pavements, and any other damages caused by the contractor during this project. Damages shall be replaced, not repaired.

7) Contractor is responsible for landscaping restoration in areas where damages occurred while demo or replacing during the project.

8) The contractor shall be responsible for the actions of all individuals provided to work under this contract. If in the event damages arise from work provided by contractor personnel, the contractor shall be responsible for all resources necessary to remedy the incident (including damages to landscaping) at no additional cost to the Government.

9) The contractor shall be responsible for ensuring that all individuals provided to work under this contract are properly licensed to operate a motor vehicle, if operating a motor vehicle on VA property is required.

10) The contractor shall adhere to all Occupational Safety and Health Administration (OSHA) regulations, as well as the safety regulations of the CVAMC while performing under this contract; see Attachment C - Safety and Health During Construction.

11) The contractor shall ensure the worksite is properly cleaned up during construction and when work is complete.

12) The contractor shall dispose of all residues off-site in strict accordance with all applicable Federal, State and Local regulations.

D. Warranty:

All services provided by the contractor, as well as parts replaced shall come with a one (1) year warranty (minimum). All labor, tools, supplies, transportation, and equipment associated with the replacement of warranty items shall be provided by the contractor at no additional cost to the Government.

E. Interference in Performance Requirements:

The following provisions shall be adhered to by contractor personnel throughout the duration of this contract:

1) The contractor may be required to interrupt their work at any time so as not to interfere with the normal functioning of the facility; e.g. utility services, emergency responses, the passage of facility patients/personnel, etc.

2) In the event of an emergency, contractor services may be stopped and rescheduled at no additional cost to the Government.

F. Construction Barrier:

The contractor shall provide a safety barrier around the construction site / work area, comprised of fences, signs, cones, caution tape, etc.

G. Materials:

The contractor shall only supply new items that are equivalent to the existing equipment. All materials or items to be supplied by the contractor that are not listed in an attachment must first be submitted to the Contracting Officer Representative (COR) and the Contracting Officer (CO) for approval prior to installation.

H. Contractor Required Reporting:

1) Prior to the completion of all weekly work activities, the contractor shall exclusively supply the COR, with his/her company’s work-documentation (daily logs).

2) The contractor shall supply the COR with any product literature and maintenance requirements for all items installed under this contract.

I. Required Contractor Notifications:

1) Contractor personnel shall inform the COR of the need to gain access to secured areas. If access is required to secured areas, prearranged scheduling will be coordinated between the contractor and the COR.

2) The contractor shall coordinate all pedestrian traffic at least 2 weeks prior.

3) If work is required beyond the terms of this contract, the contractor shall provide the Contracting Officer (CO) and the COR with a written cost estimate for any additional work or materials at no cost to the Government. The contractor shall not perform any work or make any purchases beyond the terms of this contract without approval from the CO.

J. Project Completion:

1) The contractor shall complete all contract work and schedule a final inspection within the specified performance period. During the final inspection, the contractor shall demonstrate for the COR that all newly constructed items under this contract are functioning properly prior to the Government’s final acceptance.

2) Should the Contractor fail to complete the contract work (including scheduling of the final inspection), and it is determined by the Government to be a contractor-caused delay, the Contractor shall be in default status.

PERFORMANCE SCHEDULE:

A. Normal Working Hours:

1) Normal working hours will be from 7:00 AM to 4:30 PM, Monday through Friday (excluding Federal holidays).

2) Off-hour work may be required to accommodate special circumstances.

B. Commencement of Work:

The contractor shall be required to commence work under this contract within ten (10) calendar days of receipt of the notice to proceed.

C. Period of Performance:

The contractor shall complete all work no later than one hundred and twenty (120) calendar days of receipt of the Notice to Proceed.

Page 1 of Page 1 of INFORMATION REGARDING BIDDING MATERIAL, SITE VISIT, GENERAL INFORMATION, AND GENERAL REQUIREMENTS

INSTRUCTIONS TO BIDDERS

INFORMATION REGARDING BIDDING MATERIALS:

A. Bidders are required to submit sealed offers in accordance with the instructions outlined in Section 13 (cover page of Standard Form 1442) and by submitting a bid amount on the Cost/Price Schedule, located on Page 5. Electronic submittals will not be accepted.

B. Bids shall be hand-delivered to the Department of Veterans Affairs, Lebanon VA Medical Center, 1700 S. Lincoln Ave. Building 99, Room 43 (Conference Room), Lebanon, PA 17042.

C. Bid materials consisting of drawings, specifications and contract forms may be obtained by qualified General (Prime) Contractors interested in submitting Bids directly to the Department of Veterans Affairs.

D. Questions regarding the solicitation must be submitted to the Contract Specialist by email at Lev.Stowe@va.gov, no later than June 20, 2019, at 4:00 PM (Local), after which time questions will not be answered.

SITE VISIT:

In accordance with FAR 52.236-27 – Site Visit (FEB 1995), interested parties are encouraged to attend the scheduled Site Visit, which will be held at the Department of Veterans Affairs, Coatesville VA Medical Center, 1400 Blackhorse Hill Road, Building 70 (Conference Room), Coatesville, PA 19320, on June 14, 2019 at 10:00 AM (Local).

GENERAL INFORMATION:

A. Solicitation Details:

1) Project Name:Curb and Sidewalk Replacement
2) Project Number:542-19-112

3) Magnitude of Construction: Between $100,000 and $250,000.

4) NAICS:236220
5) Size Standard:Small Business $36.5M

B. Set-Aside Requirement:

As required by the statutory requirement pertaining to the Veterans Benefits Act of 2003 (15 U.S.C. 657f) and in accordance with FAR 6.206, this procurement will be set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) concerns. Only SDVOSB concerns who are verified in the Vendor Information Page (VETBIZ) and registered in System for Award Management (SAM.gov) will be eligible to submit a bid.

C. Minimum Standards of Workmanship:

All work shall be performed in compliance with all Federal, State and Local Laws and Regulations. In addition, work will meet equipment’s manufacturer and generally accepted industry standards of good workmanship. All waste materials shall be disposed of by the contractor in compliance with Federal, State, and Local laws and regulations.

D. Contracting Officer Representative (COR):

1) (In accordance with VAAR 1.604 and 1.602-2) the COR assists in the technical monitoring or administration of a contract. Limited authority is given in writing by the Contracting Officer’s letter of designation describing the COR’s duties and responsibilities.

2) The COR has no authority to make any commitments or changes that affect price, quality, quantity, delivery, or other terms and conditions of the contract (or provisions of the solicitation).

3) The COR’s authority is limited to contract administration functions delegated in writing by the Contracting Officer.

E. Point of Contact:

1) All questions related to the contract are to be directed to the Contracting Officer.

2) Do not contact any A/E firm that may be identified herein. The A/E firm does not have the authority to share information with others or bind the government.

F. Privacy & Confidentiality:

1) Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information maybe overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this agreement or its attached documents in accordance with the contracted services.

2) Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of the privacy and confidential should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

GENERAL REQUIREMENTS:

A. Security Requirements:

1) Prior to the commencement of any work under this contract, upon arrival to the CVAMC, contractor personnel shall first check-in with the VA Police (Building 1) to obtain a VA visitor badge.

2) The contractor employee shall be responsible for safeguarding the badge and immediately report if the badge has been lost, stolen, or destroyed to the VA Police.

3) Contractor personnel shall properly display their employee identification badge and VA visitor badge at all times while on VA property so that their name, photo, and the company they work for can easily be seen.

4) All contractor personnel shall properly sign out with the VA Police upon the completion of all daily work activities.

B. Keys:

1) All keys provided to the contractor, or any subcontractor for use during the project shall be returned to the Contracting Officer Representative (COR) at the completion of the work, or upon request.

2) No keys shall be reproduced by the contractor or any subcontractor.

3) There shall be a charge for each key that is lost or not returned to the COR.

C. Safety or Environmental Violations and Experience Modification Rate:

1) All bidders shall submit information pertaining to their past safety and environmental record. The information shall contain, at a minimum, a certification that the offeror has no more than three (3) serious, or one (1) repeat, or one (1) willful OSHA, or any Environmental Protection Agency (EPA) violation(s) in the past three years. All bidders shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the offeror’s insurance company and be furnished on the insurance carrier’s letterhead.

2) Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

D. Determination of Responsibility:

1) A determination of responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the System for Award Management (SAM.gov), Vendor Information Pages (VETBIZ), Experian Credit Risk Score and Financial Stability Risk Score (Experian) and/or DUN and Bradstreet, Federal Awardee Performance and Integrity Information System (FAPIIS) accessed through the Past Performance Information Retrieval System (PPIRS), Small Business Administration (SBA), Office of Inspector General-Health and Human Services (OIG-HHS), OSHA, Veterans’ Employment & Training Services (VETS 4214) reporting database, and EPA online inspection history databases will be used to make the Determination of Responsibility. Any information received by the Government that would cause for a negative Determination of Responsibility may make the offeror ineligible for award.

2) This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

E. Training:

1) Effective July 31, 2005, all employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course.

2) The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course.

3) Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. Failure to present the proper training documentation will result in the individual being removed from the job; the individual may only return after the proper documentation has been provided. There shall be no exceptions to this requirement.

F. Wage and Hour Laws:

The Contractor shall be responsible for the correct title classification of workers and compliance with all applicable wage and hour laws.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.2 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) ALTERNATE I (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute shall submit the request with its offer, including the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.3 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— June 14, 2019 at 10:00 AM (Local)

(c) Participants will meet at— The Coatesville VA Medical Center, 1400 Blackhorse Hill Road, Bldg 70 (Conference Room), Coatesville, PA 19320.

(End of Provision)

2.4 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/ (End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-34
SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE
APR 1991
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
FEB 1999
52.232-38
SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH OFFER
JUL 2013

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $36.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xx) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.

(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.

(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan—Certification. This provision applies to all solicitations.

(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certifications. This provision applies to all solicitations.

(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and

(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[X](i) 52.204-17, Ownership or Control of Offeror.

[X](ii) 52.204-20, Predecessor of Offeror.

[](iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

[](iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment—Certification.

[](v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services—Certification.

[](vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).

[](vii) 52.227-6, Royalty Information.

[](A) Basic.

[](B) Alternate I.

[](viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause #
Title
Date
Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of Provision)

GENERAL CONDITIONS

4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)

(a) Definitions. As used in this clause— Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.

Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).

Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

Safeguarding means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures. (1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

(End of Clause)

4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

4.3 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)

(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of…