36C24219B0050-002.pdf

PDF 277 KB Posted

Attached to
528A6-19-601 REPLACE CONCRETE SLAB B106 Federal contract opportunity
Solicitation number
36C24219B0050
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

36C24219B0050 P09 - SOW - Replace Concrete Slab B06 - 528A6-19-601.pdf

View the file

Other files for this federal contract opportunity

Other files attached to 528A6-19-601 REPLACE CONCRETE SLAB B106, newest first.
File Type Posted
36C24219B0050-0001003.zip ZIP file
36C24219B0050-0001002.zip ZIP file
36C24219B0050-0001001.pdf PDF
36C24219B0050-0001000.docx DOCX document
36C24219B0050-005.zip ZIP file
36C24219B0050-004.zip ZIP file
36C24219B0050-003.pdf PDF
36C24219B0050-001.docx DOCX document
36C24219B0050-000.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NO. 528A6-19-601

REPLACE CONCRETE SLAB, B-106

VAMC BATH, NY 12/30/2019

Scope of Work

REPLACE CONCRETE SLAB, B-106

528A6-19-601

Contractor shall provide all labor, materials, supplies, equipment, tools, and supervision necessary to remove and replace existing concrete slab-on-grade of the existing B-106 Canteen

Pavilion located at the VA Medical Center in Bath, New York. Unless otherwise directed by the

COR, work shall be performed in accordance with construction drawings and specifications and other standards and regulations as detailed or specified.

The General Contractor shall be responsible for; removing existing concrete slab-on grade and sidewalks. The G.C. shall provide material to replace concrete and sidewalks. The G.C. shall provide and install, replace or tie into existing drainage structures as well as provide proper draining slopes in all new concrete work. The contractor shall provide and install all grading material and provide site restoration. This contract shall include other items as shown on the contract drawings and specifications.

Construction shall be completed 90 days from notice to proceed.